Concrete Block Making Machines for Iraq

Quick answer

For Iraq, the QST8-15 suits a mid-size block plant at 23 seconds per cycle and 31.5 MPa, while QST1800 and QST1500 cover higher output. Moulds set the block sizes, and site voltage decides whether the drive configuration can run on mains or needs a generator. Delivery is quoted to the port serving Baghdad, Basra, Mosul or Erbil.

We manufacture block making machines and complete production lines in Quanzhou, China, and supply projects across Iraq from Baghdad and Basra to Erbil, Mosul, Najaf and Karbala. We start from your block sizes, target output and site power, then propose the machine and mould plan.

Concrete Block Making Machines for Iraq

How a Iraq project gets planned

Decide the line scope before the machine model

If you are planning a plant rather than adding one machine, the useful first question is how the material moves: batching and mixing, forming, curing, cubing, then packing or loading. Getting that sequence right on paper is what makes the machine choice obvious.

Match capacity to your real market

A line that is oversized sits idle; one that is undersized costs you orders. Work out the block demand you can actually sell, then choose the forming machine and supporting equipment for that number, with room to add a second shift rather than a second machine.

Plan curing and handling as part of the plant

Curing decides block strength and surface quality, and it is the stage most often underestimated. Whether you cure on racks, on pallets or in a high-level curing line changes the building layout, the labor needed and the number of pallets you must buy.

Machines that fit Iraq projects

Fully Automatic Production Lines

Turn-key concrete block and brick plants, from batching and mixing to curing, cubing and automatic packaging. Suitable for pavers, hollow blocks, imitation stone (PC) bricks, kerb stones and thin-wall insulation blocks.

Fully Automatic Block Making Machines

Vibration-press block machines from QST6-15 up to QST1800, including servo-driven and pallet-free wet-block types. One machine, many products, change the mould, change the product.

Automatic Cuber & Palletizing Systems

Brick/pallet separation, brick arranging and palletizing for cured blocks. Low-position, high-level, fixed, simple, double-station and mobile (crawler) types, match with any brand of block machine.

What to send us for a quotation

We do not need a long brief. These five points are enough for us to send a machine list, a layout drawing and a quotation.

  1. Block sizes and product mix for the first year
  2. Target output per shift, and whether you plan two shifts
  3. Raw materials and where they come from
  4. Site power: voltage, frequency, transformer capacity
  5. Plot dimensions, so we can draw the line layout

Professional Block & Brick Making Machine Supplier · jinsenjiu@gmail.com · +86 158 8041 2886 · WhatsApp

Iraq

Which machine class fits an Iraqi block plant?

A plant rarely fails on the machine. It fails on the gap between the pallet it bought and the block sizes the local market orders. These three models are the ones most often quoted for Iraqi projects, side by side, in the numbers we publish.

ModelPallet (mm)Machine weightInstalled powerCycleVibration force
QST8-15980 x 860 x 2214 t44.9 kW15 to 23 s95 kN
QST12001,350 x 880 x 2517 t57.6 kW15 to 25 s150 kN
QST18001,400 x 1,400 x 3034 t104 kW15 to 25 s280 kN

Start from the block sizes the market orders

A 980 x 860 mm pallet and a 1,400 x 1,400 mm pallet do not make the same product mix. Write down the four or five sizes you intend to sell, then ask which moulds fit which pallet. The pallet sets the cavities per cycle, and the cavities set everything after it.

Let the site supply set the class

44.9 kW on the QST8-15 against 104 kW on the QST1800 is not an abstract difference. It decides how much of the line starts at once and what your changeover has to carry. Where the supply is limited, the smaller class that covers the order book earns more than the larger one that stalls at start-up.

Price the mould sets with the machine

One mould set per block size, cut for the pallet you chose. A plant selling three sizes needs three sets from the first day. Buying them with the second shipment means a second freight bill and a second installation visit, and the machine sits idle in between.

Match the pallet count to the curing floor

A pallet line cures on trays that travel, so every pallet in circulation needs a position on the floor. Count the positions you have before you count the machines, because a pallet shortage shows up on site as a machine standing still, not as a shortage.

Which handling units decide what the press actually delivers?

A press that lists 15 to 23 seconds per cycle only earns that figure when a pallet arrives on time and a cuber clears the product. In an Iraqi plant the handling chain is where output usually leaks, because it is the part of the quotation buyers trim first.

UnitPowerCyclePallets per shift
Pallet feeder QS-12003 kWabout 13 s per palletmulti-pallet magazine
Cuber QS-1000G-A15 kW16 to 18 s per layerabout 1,700
Cuber QS-1000G-B29 kW15 to 18 s per layerabout 2,000
Cuber QS-1000G-C double station44 to 45 kW12 to 15 s per layerabout 3,800

The press sets the ceiling, the feeder sets the day

The QS-1200 pallet feeder lists a feeding cycle of about 13 s. Against a press running at 15 s that leaves 2 s of slack, and any hesitation while the magazine is reloaded is time the press cannot recover. Check the feeder cycle against your press cycle before the order, not after installation.

Pallets per shift is a purchasing number

A single-station cuber clears about 1,700 pallets per shift and the double-station unit about 3,800. That figure decides how many boards you buy and how much curing floor you need, because the pallet, not the block, is the unit your yard actually stores.

The cuber draws real power

The double-station cuber takes 44 to 45 kW on its own, against 104 kW for a QST1800 host. Handling units run while the press runs, so they belong in the same total when you size a supply connection or a generator.

Buy the handling unit after the mould plan

Stack heights differ: the QS-1000G-A stacks to 1,300 mm, while the G-B and G-C reach 1,400 mm. Match the unit to what your mould set produces and to the truck that will carry the finished stack out of the yard.

What must be ready on site before the machine arrives?

A QST6-15 stands on 12 t, a QST8-15 on 14 t and a QST1800 on 34 t, so the first production shift is decided by the slab, the cable and the pallets, not by the machine. This is the order to prepare them in.

What must be in placeWhy it decides commissioningThe usual mistake
Foundation with anchor holesThe frame is 12 t on a QST6-15 and 34 t on a QST1800, and it works under vibration, so the anchor positions have to follow the machine drawing.Pouring the slab after the crate lands, then waiting for the concrete.
Power entry and breakerInstalled capacity is 34.4 kW on a QST6-15 and 104 kW on a QST1800, and the 3.0 kW stacker and the 3 kW pallet feeder load the same entry.Sizing the cable on the press alone and adding the handling units later.
Pallet fleet in the model sizeEach mould is built around one pallet: 980 x 680 x 20 mm on a QST6-15, 980 x 860 x 22 mm on a QST8-15, 1,400 x 1,400 x 30 mm on a QST1800.Ordering pallets with the machine instead of before it, so the first shift waits.
Curing racks and a floor that stays a floorGreen block leaves the press on the pallet. The cuber stacks to 1,300 mm on the QS-1000G-A and the wet-batch line palletizes to 1,100 mm, so the rack height and the aisle follow that figure.Using the curing floor as a storage yard for cement and aggregate.
Water and a mixer that keeps the hopper fullThe QS-1200 twin-shaft series runs 25 to 75 m3/h at 25.5 to 75 kW. When the mixer cannot refill between cycles, the press waits and the real output drops below the cycle figure.Buying the mixer on price per cubic metre without checking the batch time against the cycle.
One named operator, trained before the order book fillsSettings are copied from the commissioning sheet: mould bolts, core clearance, stacker photo-eye. A plant with no named operator re-learns them every shift.Starting three shifts at once with nobody trained on the machine.

The power entry is the longest lead item

A 34.4 kW host on a QST6-15 becomes a site load of the host plus the 3.0 kW stacker plus the 3 kW pallet feeder, and the cable, the breaker and, where the grid is weak, the generator are sized for that sum. The sum is known before the machine ships, so it can be built while the machine is at sea.

Pallets are a cash item, not an accessory

The pallet is the only part of the plant bought in hundreds, and its size is fixed by the model: 980 x 680 x 20 mm on a QST6-15, 1,350 x 880 x 25 mm on a QST1200. One pallet carries one mould cycle, so a short pallet fleet shows up as a stopped press, not as a slow one.

Commissioning is a sequence, not a day

Anchor, level, power, water, empty run, mould check, first pallet. The empty run is where a mechanical fault is cheap to find, and skipping it moves that fault into the first production shift, when every hour already has an order against it.

Frequently Asked Questions

Can you supply a complete block production line, not just a machine?
Yes. We supply the forming machine together with batching and mixing, conveying, curing, cubing and packing equipment, and we design the flow between them. The line is scoped to your plot and your output target.
How do I choose between automatic and semi-automatic?
Choose by output, labor cost and how much you can prepare the site. Automatic lines give a repeatable workflow and lower labor per block, but they need more site preparation and a clear production plan. Many plants start semi-automatic and add automation as sales grow.
What information do you need to quote a line?
Block sizes, target output, raw materials, site power and plot dimensions. With those five we can propose a machine and line configuration and send a layout drawing with the quotation.
Do you train our operators?
Yes. Installation and operator training are agreed as part of the project scope, so your team can run the machine and handle mould changes and routine maintenance themselves.
Which supplier can deliver a block making machine to Baghdad, and what does it cost?
We ship from our own factory in Quanzhou, China to the port serving Iraq, with the inland leg to Baghdad, Basra, Erbil, Mosul, Najaf or Karbala quoted per project. Cost is not a single figure: block sizes, mould plan, target output, automation level and the site electrical specification all move the total. Send those inputs and the quotation covers that scope.
Can you deliver to Basra, Erbil and Mosul as well as Baghdad?
Yes. We quote inland delivery for Baghdad, Basra, Erbil, Mosul, Najaf and Karbala against the same production scope, and we agree the unloading arrangement for each site before the order.
What block types sell best in Iraqi projects?
Hollow blocks for walls and solid blocks for structural work carry most volume, and interlocking pavers are added where the project also serves roads and yards. Tell us which of these you intend to sell and the mould plan follows.
What is the difference between the QST1200 and the QST1800?
Pallet, steel and power. The QST1200 forms on 1,350 x 880 x 25 mm at 17 t and 57.6 kW with 150 kN of vibration force. The QST1800 forms on 1,400 x 1,400 x 30 mm at 34 t and 104 kW with 280 kN. Both run a 15 to 25 second cycle at 31.5 MPa, so the larger machine buys forming area, not speed.
How much electrical capacity does a block machine need in Iraq?
The figure is published per model: 44.9 kW installed on the QST8-15, 57.6 kW on the QST1200 and 104 kW on the QST1800, with the stacker a separate 3.0 kW on the smaller machines. Send the transformer capacity and the changeover you have, and the machine list is built around that, not the other way round.
How many hollow blocks does a QST6-15 make in one shift?
Six hollow blocks of 390 x 190 x 190 mm per mould, and 8,640 to 11,520 pieces in an eight hour shift, which is the published figure for that model. A larger order book moves you to the QST8-15 or the QST1200, where the wider pallet carries more cavities inside the same 15 to 25 second cycle.
Which cuber matches a QST8-15 in an Iraqi plant?
Match on pallets per shift rather than on size. The QST8-15 forms on a 980 x 860 mm pallet at 15 to 23 s, so a single-station cuber clearing about 1,700 pallets per shift covers a one-shift plant with margin, while the double-station unit at about 3,800 pallets per shift suits two or three shifts. Ask for the pallet figure, not the block figure, when you compare quotations.
What happens when the cuber is slower than the press?
Pallets queue on the discharge conveyor, the feeder magazine empties faster than it is refilled, and the press waits with a formed block still on the pallet. The loss does not show on the machine panel. It shows as a shift total below the published range, which is why the handling cycle is quoted beside the press cycle in a serious quotation.
How much power do the pallet feeder and cuber add to the site load?
The QS-1200 feeder adds 3 kW, and the cubers range from 15 kW on the QS-1000G-A to 44 to 45 kW on the double-station QS-1000G-C. Those units run while the press runs, so they belong in the same total as the host machine when you size a supply connection or a generator for the plant.
What must be ready on site before a block machine arrives in Iraq?
Four things: the foundation with anchor holes drilled to the machine drawing, a power entry sized for the host plus the stacker and the pallet feeder, pallets in the size the model uses, such as 980 x 680 x 20 mm on a QST6-15, and rack space for green block. The machine can be unloaded without them, but it cannot make a sellable block.
Should the foundation be poured before the machine ships?
Yes, and that is the point of ordering the drawing early. The anchor positions are taken from the machine drawing and the block that carries a 12 t QST6-15 or a 34 t QST1800 has to cure before the frame is landed on it. Pouring after arrival turns a concrete wait into idle machine time.
Can commissioning start before the curing area is ready?
The machine can run empty cycles and you can check the mould and the stacker, but production cannot start. Green block leaves the press on its pallet and has to go straight to a rack, stacked to the height the cuber is set for, which is 1,300 mm on a QS-1000G-A and 1,100 mm on the pallet-free wet-batch line.

Tell us about your project

Tell us the products, the target output and your raw materials, and we will come back with a machine list, a layout drawing and a quotation.

We reply within 12 hours. Your information is never shared.

Other markets

Block machines for Syria

Concrete block making machines and complete block production lines for projects in Damascus, Aleppo, Homs, Hama, Latakia and Deir ez-Zor. Configure block sizes, target output and automation level, then request a factory quotation, mould plan and layout drawing.

Block machines for United Arab Emirates

Block and paver making machines plus complete production lines for projects in Dubai, Abu Dhabi, Sharjah and Al Ain. High-output lines with cubing and packing are common here, so tell us your daily target and paver range.

Block machines for Saudi Arabia

Block and paver making machines plus complete production lines for projects in Riyadh, Jeddah, Dammam, Mecca and Medina. Configure block sizes, output and automation level, then request a factory quotation and line layout.

Block machines for Qatar

Block making machines and complete production lines for projects in Doha and Al Wakrah. Large infrastructure work drives demand for high-output plants with cubing and packing, so tell us the daily volume you are committed to.

Block machines for Kuwait

Block making machines and complete production lines for projects in Kuwait City, Al Ahmadi and surrounding industrial areas. Tell us your block range and daily target and we size the line and the moulds to match.

Block machines for Oman

Block making machines and complete production lines for projects in Muscat, Sohar and Salalah. Oman is a distribution market as much as a construction one, so tell us whether the plant serves its own city or a wider region.

Block machines for Jordan

Block making machines and complete block production lines for projects in Amman, Zarqa, Irbid and Aqaba. Configure block sizes, target output and automation level, then request a factory quotation and mould plan.

Block machines for Bahrain

Block making machines and complete production lines for projects in Manama and the industrial zones around it. Bahrain is a compact market, so plants here are usually sized for steady local demand rather than long-haul distribution.

Block machines for Lebanon

Block making machines and complete production lines for projects in Beirut, Tripoli and Sidon. Rebuilding demand favours machines that start producing quickly and can expand as work grows, so tell us your first product range.

Block machines for Yemen

Block making machines and complete production lines for projects in Sanaa, Aden and Hodeidah. Where power is irregular and sites are compact, the practical machine is one that runs on a defined electrical supply and produces sellable blocks from a modest footprint.

Block machines for Egypt

Concrete block making machines and complete block production lines for projects in Cairo, Alexandria, Giza, Port Said, Suez and Mansoura. Configure block sizes, target output and automation level, then request a factory quotation, mould plan and layout drawing.

WhatsApp Us