Block factory setup in Kuwait: plant sizing and dispatch

26 October 2026 · 6 min read

Quick answer

Block factory setup in Kuwait is sized from the dispatch cycle back: lorries per day, blocks per lorry counted in clamp bites, cubes standing in the yard, and only then press cycles. A clamp bite carries 500 to 800 standard bricks or 40 hollow blocks, so the gate sets the day. A plant sized from the press instead ends up with cubes it cannot load.

Get a price on WhatsApp Or send a written enquiry

Block factory setup in Kuwait is a sizing problem that runs backwards from the gate. Start with the lorries you can load and sell in a day, work out the blocks each lorry carries, and only then ask how many cycles a press must deliver. Every machine number in the quotation has to fit inside that chain, or the plant produces stock nobody collects.

The usual order is the opposite: pick a press, read its output, then look for a yard for the surplus. Sized that way, a press on a 15 second cycle forms blocks faster than your own sales clear them, and the difference sits in the yard as cubes paid for in cement and never invoiced.

Three numbers decide the plant: blocks per lorry, cubes standing in the yard at any hour, and cycles per shift. Batching, mixing, curing and cubing are sized from those three. Get the order wrong and the plant is either short of blocks at the gate or long on stock it cannot sell.

Why does the lorry set the plant size, not the press?

A plant earns money at the gate, when a lorry leaves loaded and invoiced. Everything before that is cost. The day's sellable output is the lorries you can load before the gate closes, multiplied by the blocks each one carries. That figure is the real capacity of the plant.

Blocks per lorry are counted in clamp bites, not pieces. A forklift clamp takes 500 to 800 standard bricks or 40 hollow blocks in one bite, up to 10 layers of standard brick or 5 of hollow block, on a 2,000 kg load capacity. The yard must present each stack square and ready.

The cubing station enters the sizing here. A cuber builds square stacks of 1,000 to 1,200 mm at 13 to 16 seconds per layer, so the stack it hands over has a fixed footprint. Clamp arms open across 680 to 1,150 mm. Order a 1,200 mm stack against a 1,150 mm clamp and one of the two must change.

How do you turn a dispatch figure into press cycles?

Take the blocks a day you can sell, add your reject allowance, and divide by the pieces one mould carries. That gives the cycles you need. Compare that with what the machine delivers. The QST6-15 lists a 15 to 23 second forming cycle, so an hour holds 240 cycles at 15 seconds, because 3,600 divided by 15 gives 240.

A shift is never 480 working minutes. Mould cleaning, a mix change and two jams cost an hour. Run 7 hours at 240 cycles and you have 1,680 cycles. Multiply by the cavity count: a mould yielding 40 pieces of 200 by 100 by 60 mm tile gives 67,200 pieces a shift.

When the two figures disagree, do not stretch the machine to close the gap. Trim the product range, or plan two shifts on the days the yard is full. A press held at 240 cycles for 7 hours makes 1,680 mould loads whether a lorry arrives or not, and the surplus is cement already paid for.

Where the pallet fleet lands in the plant budget

A pallet-based line puts a board under every block, and the board count is working capital before the first block is sold. The cuber range quotes about 1,700 pallets per shift on a fixed cuber, 2,000 on a simple cuber, 3,800 on a double-station cuber, and 1,300 pallets a day on a mobile yard cuber.

Every one of those pallets must be fed, returned, cleaned and replaced. The pallet feeder holds three stacks and delivers one every 13 seconds on 3 kW. Board sizes differ by machine family, 980 by 680 by 20 mm on one and 1,100 by 650 by 20 mm on another.

A pallet-free line removes the fleet. The wet block is cubed as it leaves the mould, so no board enters the process, and the cuber builds self-retaining forklift holes into the stack so a clamp lifts it onto the lorry. The QSMT1000 is documented at up to 135,000 bricks of 240 by 115 by 50 mm per 8 hour shift.

How narrow can the mould count stay in one market?

A plant selling into one market does not need a catalogue. Each product is a mould set: frame, core, base plate, guides and positioning parts in wear-resistant alloy steel, heat treated to micron tolerance. That is capital on a rack, and every changeover costs cycles from the shift you counted.

Two moulds usually carry a small plant: one load-bearing hollow block for walls, one paver or kerb for the paving and municipal side. Both run on the same press, and one clamp handles standard brick, hollow brick, paving brick and aerated block without a change of attachment.

Whether a third mould earns its place is decided by annual pieces, not ambition. Ask what volume the extra specification takes in a year and divide the mould cost by it. A few thousand pieces does not pay for a mould set plus the changeover, so buy that block in and keep the press on products that fill lorries.

What must you supply before anything is sized?

Sizing is an input problem. Four site facts and three product facts decide the layout, and no supplier can guess them honestly. Send them with the enquiry, or the quotation gets built on assumptions you will pay for later.

  • Site power: the capacity you can deliver at the panel, with the supply voltage and frequency. One press family lists 34.4 kW plus 3.0 kW for the stacker, another lists 37.4 kW including a 2.25 kW feeding motor.
  • Water: volume and pressure at the mixer, and whether the supply runs through a tank. A batching line draws water on every batch, all shift.
  • Yard: paved area, stacking height, and the distance from press to curing area to gate. A cuber stack stands 1,000 to 1,200 mm square, and the cubes present at any hour set the floor.
  • Block spec: a drawing of every product with dimensions and the cavity count you expect per mould, since cavities turn cycles into blocks.
  • Mix: cement grade, aggregate source and the proportions you will run, because cycle time and strength follow the mix.
  • Logistics: pallet size if the line uses pallets, the payload your trailers carry, and the port the machine lands at.

How do you verify the machine claim on your own slab?

Take a stopwatch to the trial. Time 30 forming cycles on the mix you will actually run and compare the average with the 15 to 23 second band the sheet quotes. Cycle time moves with moisture, aggregate grading and operator, so only your own mix gives a budgetable number.

Then measure the product, not the shift total. Pull ten blocks from mid-shift, check dimensions against the drawing, weigh them, and cube-test for the strength your market wants. A 25 MPa rated pressure and a 68 kN excitation force hold those values only when mix and mould are right.

Finish by building one cube and lifting it. The cuber should hand over a stack of 1,000 to 1,200 mm square, the clamp should take it in one bite at full layers, and the lorry should load with nobody touching a block. Hands at the stack mean the layout is wrong.

Frequently asked questions

How do I work out the daily output a block plant has to reach?

Count the lorries you can load and sell in a day, then multiply by the blocks each lorry carries. A clamp bite takes 500 to 800 standard bricks or 40 hollow blocks, up to 10 layers of solid brick or 5 of hollow block, so a lorry fills in bites. Add your reject allowance and you have the daily forming target.

What does a pallet-free block machine remove from the plant?

The pallet fleet. A pallet-based cuber moves roughly 1,700 to 3,800 pallets a shift depending on the model, and every one must be fed, returned, cleaned and replaced. A pallet-free machine cubes the wet block as it leaves the mould and builds forklift holes into the stack, so the clamp loads the lorry directly.

How many moulds does a plant selling into one market need?

Usually two. One load-bearing hollow block for walls and one paver or kerb for paving work cover most local orders, and both run on the same press with the same clamp. A third mould is justified by annual pieces, not ambition: divide the mould cost by the yearly volume, and if the answer is a few thousand pieces, buy that block in.

What information do you need before sizing a block plant?

Site power at the panel with voltage and frequency, water volume and pressure at the mixer, paved yard area and stacking height, the drawing of every product with its cavity count, cement grade and aggregate source, pallet size if pallets are used, trailer payload, and the port the machine lands at. Without those, any output figure is a guess.

Can I check a machine's cycle time before I buy it?

Yes, with a stopwatch on your own mix. Time 30 forming cycles and average them, then compare with the 15 to 23 second band the sheet quotes. Mould the product, weigh ten blocks, cube-test for strength, and build one full cube for the clamp. A cycle that holds on your aggregate is the only figure worth budgeting with.

Price guides
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us