Block Machine Storage and Restart After a Delayed Project
18 November 2026 · 5 min read
Quick answer
A machine is often paid for before the building that will hold it exists, so it stands for months. Storage damage is small and predictable if four decisions are taken on the day it lands: a covered concrete floor, bare steel and mould faces under an oil film, hydraulic ports blanked and the panel kept dry, and a written card recording what was done and when. Restart then follows five steps in order: foundation and level, electrical insulation and phase order, hydraulic oil and filter, a dry cycle with the mould off, and a mould trial whose first blocks are measured and kept.
A block machine is usually paid for before the building that will hold it is finished. It arrives, gets unloaded onto a slab, and stands. Three months, six months, sometimes a year. Nothing about that is unusual in a project that is waiting on a foundation, a power connection or a licence.
What happens during that wait is predictable: machined faces rust, hydraulic oil takes in water, seals flatten against a stationary rod, the panel collects humidity, mould cavity faces stain, and pallets warp in the sun. All of it is cheap to prevent on the day the machine lands and expensive to correct on the day the crew arrives.
What actually degrades while a machine waits?
Five things, in the order they cause trouble on restart.
- Bare steel and machined ways. Condensation does the damage, not rain, which is why a humid shed can be worse than a dry yard with a roof over the machine only.
- Hydraulic oil and seals. Water settles in the tank, seals take a set against a rod that has not moved, and the filter holds everything that settled out of the oil.
- The control panel. Humidity, heat, a dead backup battery, insects in contactors, and a screen that has not been energised for a year.
- Mould cavity faces and base plates. Staining, nicks at the cavity edge from handling, and a base plate that has been used as a workbench for someone else's job.
- Pallets. A 30 mm board that stands on edge in the sun for a season comes back as a pallet that no longer measures 30 mm flat.
Where should the machine stand?
Under a roof, on a concrete slab, blocked off the floor on timber or steel so air moves under the frame, and away from the cement store. Cement dust plus humidity is the worst combination a hydraulic system can meet, and a machine parked beside a silo vent collects both.
Leave the lifting route open. A 34 t QST1800 or a 20 t QST1500 needs a crane with a plan, and only the marked lift points on the frame should take the load. If the machine has to stand outdoors, put it on a drained pad, sheet the top and let the sides breathe; wrapping a machine in plastic traps the condensation you were trying to avoid.
What should be preserved, and with what?
Preservation is thin, clean and recorded. Thick grease traps grit, and grit grinds on the first start. A film is what protects a machined face, not a coat.
- Machined ways and unpainted faces: a film of grease, renewed at each inspection date.
- Mould cavity faces: oil film, base plate flat and supported, nothing stacked on it.
- Hydraulic ports and hose ends: blanked and capped, including the ones opened for transport.
- Panel: desiccant inside, door sealed, and one hour of power a month where the supply is stable. Where it is not, remove the battery and label it.
- Vibration motors: shaft turned by hand at each inspection so the bearings do not sit in one position.
- A card on the machine with date, action and initials. That card is the difference between a warranty discussion and an argument.
What about the mould and the pallet fleet?
Moulds are the most expensive thing that rusts quietly. Store them flat, cavity face down on a clean timber pallet, or cavity face up under a cover that does not touch the edges. Never stand a mould set on its edge, and never let a base plate carry another load.
Pallets are a fleet, and a fleet stored badly is a fleet bought twice. Stand them flat on dunnage, off the ground, out of direct sun, with the boards supported at both ends. A 30 mm pallet that has warped by a few millimetres shows up later as a height variation in the block and as a jam at the cuber, and by then nobody remembers it spent a summer on edge.
Restart step one: foundation and level
The foundation is poured to the latest general arrangement drawing, and the drawing in the crate is not always the latest one. Confirm the revision before the concrete goes in, then let it cure for the period the drawing or your engineer specifies. The machine does not level a slab. The slab levels the machine.
On restart, check anchor torque, check the frame for level on both axes, and look for cracks or settlement at the corners. A frame that has stood a year on a settling slab shows it here, and shimming and re-grouting now is cheaper than discovering it later as a block height drift nobody can explain.
Restart step two: electrical
Before any power reaches the panel: insulation resistance on the motors and the main feeder, phase order checked at the incoming side, earth continuity confirmed, and the panel opened, dried and cleaned. Remove the desiccant, replace the backup battery, and check that no contactor has stuck shut.
Confirm voltage and frequency against the machine plate before the first start. A panel built for one supply and connected to another will run, badly, and the faults it produces look hydraulic until somebody measures the supply.
Restart step three: hydraulics
Drain the water from the sump, not the oil. Replace the filter element before the first start, because a year of settling puts fine particles exactly where the new oil will pick them up. Fill to the grade in the manual, not to whatever drum is on site.
The system is rated at 31.5 MPa and the relief setting is not a tuning screw. If pressure has to be raised to make the machine cycle, something else is wrong, and the shift log will show it as a longer cycle before it shows it as a weak block.
Restart steps four and five: dry cycle, then a mould trial
With the mould off, jog every motor for direction, then run a full dry cycle at low speed: feeder, vibrator, press, demould, stacker. Listen for a change in sound between the first and the tenth cycle, and watch the ammeter on the vibration motors rather than the blocks, because there are no blocks yet.
- Dry cycle: no mould, no mix, every limit switch proven by hand once.
- Mould on, one pallet, half a batch of mix: check fill, check demould, check that the pallet releases square.
- Trial run: three pallets at cycle speed, blocks measured for height and length, three blocks kept and dated.
- Yard: keep those three blocks for seven days, then check corners and cracks.
If the first pallet comes out short in height, the cause is usually pallet thickness or the demould setting, not the mix. The pallet is the reference the whole cycle is built on, which is why the fleet is checked before the trial and not after it.
Who signs, and when does the warranty start?
Warranty normally starts at commissioning, not at the invoice, so the date on the commissioning record decides a year of cover. Write the date, the model, the serial number and the storage period on that record, and keep the storage card with it.
If the machine stood for more than a few months, say so at the start of the restart and not after the first fault. Storage conditions change what the restart needs, and a machine that waited in a humid shed needs a hydraulic flush that a machine installed on arrival does not.
What do we need to support a restart?
Six items: the model and serial number, the date the machine was unloaded, where it stood and for how long, photographs of the panel interior, the oil sight glass and the mould faces, the foundation drawing revision you built to, and the voltage and frequency measured at the site.
With those we can say whether the restart is a supervised commissioning or a technician visit, and which parts should be on the pallet before the crew starts, instead of finding out halfway through the first dry cycle.
Frequently asked questions
Can a block machine stand outdoors for a year?
It can, on a drained pad, with the top sheeted and the sides left open, a film of grease on machined faces, ports capped and the panel kept sealed with desiccant. What must not happen is a plastic wrap over the whole frame, which traps condensation against the steel.
Does the hydraulic oil have to be replaced after storage?
Drain the water from the sump and replace the filter element before the first start. If the oil comes out milky, the tank took water and the charge should be replaced rather than topped up. Top up to the grade named in the manual.
When does the warranty start if the machine waits?
At commissioning in the usual case, which is why the commissioning record carries the date, the model, the serial number and the storage period. A machine that stood for a year should have that stated at the start of the restart.