Block Making Machine in Ghana: What to Specify Before You Compare Quotes

11 October 2026 · 6 min read

Quick answer

A machine is specified before it is priced. Give shift output in the product you sell most, product mix with sizes in millimetres, available power at your panel and pallet size, and the configuration follows, covering the press with its installed power and steel weight, the mould sets, the pallet handling and curing around it, and freight to your port. A quotation that lists a model number alone has not told you what you are buying.

Choosing a block making machine in Ghana starts with a written specification, not a price list. A supplier asked for a machine will send a machine. A supplier given your shift output, product mix, available power, pallet size and yard area will send a configuration that actually runs on your site. The sections below cover the four items to settle before you request any quotation, plus the two that decide whether the first quotation is even comparable to the second. Nothing here asks you to know Ghana. It asks you to know your own yard.

1. Fix the shift output before you ask for a price

Output comes first because it sets the frame size, the power and the price at the same time. Three figures show the steps on one standard product: the QST8-15 reaches 90,000 standard bricks in an 8 hour shift, the QST1200 reaches 120,960, and the QST1800 covers 165,000 to 220,000 on the same 240 x 115 x 51 mm brick. Write your target as blocks per shift, not blocks per day, and state the shift length you really run.

A buyer who writes 8,000 blocks a day is specifying a different plant from one who writes 60,000 a day, and no quotation can hide that gap. Once the shift figure is fixed, everything downstream gets a size: the mould area, the pallet, the hydraulic unit and the power supply.

Give the figure in the product you sell most, because a press rated at 220,000 standard bricks in 8 hours makes 27,000 to 36,000 hollow blocks of 390 x 190 x 190 mm in the same shift. Each cycle fills a bigger mould, so the count falls while the machine works just as hard.

2. The product mix decides the mould and the pallet

The mix of products you sell decides the tooling, and the tooling decides what the machine can be asked to do. Three shapes cover most yards: a solid standard brick of 240 x 115 x 51 mm, a hollow block of 390 x 190 x 190 mm, and a paver of 200 x 100 x 60 mm. Each one needs its own mould, and the hollow block returns far fewer pieces per shift than the solid brick.

Write the sizes in millimetres and say which product carries your volume. A yard that sells mostly pavers should be specified around pavers from the start. A yard that sells mostly 390 x 190 x 190 mm blocks should make the hollow mould the default and treat the solid brick as the changeover, not the other way round.

3. Write your available power in kilowatts

Power is the item most often left blank and the one that cannot be changed later by better negotiation. Our presses step from 22.9 kW on the QT4-15, to 37.4 kW on the QT5-15, to 44.9 kW on the QST8-15, to 57.6 kW on the QST1200, and up to 104 kW on the QST1800. Write the figure you can hold at the panel, not the number on the transformer plate.

Induction motors pull roughly 5 to 7 times their rated current at start, so a 44.9 kW line does not behave like a 44.9 kW load when it kicks. Tell us whether you run on the grid, on a generator, or on both, and the voltage you have. We build the machine to the supply you name. The QST8-15 needs about 45 kW of supply and a workshop of roughly 10 x 4 m, so your first two numbers set both the electrical room and the building.

4. Pallet size and blocks per mould

The pallet is the surface each block is formed on, and its size sets the mould layout. Three sizes cover our range: 980 x 860 x 22 mm on the QST8-15, 1,350 x 880 x 25 mm on the QST1200, and 1,400 x 1,400 x 30 mm on the QST1800. A larger pallet carries more blocks per mould, so a line with a bigger pallet needs fewer cycles to reach the same shift figure.

Blocks per mould is the number to put beside the pallet, because the cycle time is fixed. The QST1200 produces 63 standard bricks per mould, and the QST1000 produces 51. When you request a quotation, ask for the pallet dimensions and the pieces per mould in writing. A quotation that lists only a model number and a price has not told you what you are buying.

5. Site, curing area and cycle time

The cycle time of the press is between 15 and 25 seconds, depending on the model and the product. At a 15 second cycle the machine starts and stops more than 140 times an hour, so the electrical supply, the hydraulic oil temperature and the pallet handling all have to keep up. Match the handling and the curing area to that rate before you order, because green blocks have to leave the machine as fast as it makes them.

Curing is not a machine function. Strength develops over several days of hydration, and it depends on temperature and humidity in the yard, not on the press. Keep the water to cement ratio between 0.35 and 0.45. Adding water to loosen the mix raises the cement bill and lowers strength at the same time, so plan a covered or shaded curing area sized to hold your daily output, including the pallets standing in it.

6. The six lines to put on your enquiry

Send these six lines and our engineers can size the plant in one pass:

  • Shift output in blocks per 8 hour shift, in the product you sell most.
  • Product mix and sizes in millimetres, such as 240 x 115 x 51 mm or 390 x 190 x 190 mm.
  • Available power in kilowatts, and whether it comes from the grid, a generator or both.
  • Preferred pallet size, or the pallet size you already use if you are replacing a line.
  • Yard and building area in metres, including the space you can give to curing.
  • A sample of your raw material, so we can check the mix before we quote a mould.

What happens after the six lines arrive

With those lines on the page, a quotation becomes a proposal you compare line by line instead of a number you have to guess at. We check the power figure against the model, the product mix against the mould list, and the pallet against the mould layout, then come back with the model and the numbers that fit your shift. The aim is that the first quotation you read is already the one you can act on.

Frequently asked questions

How many blocks per shift can a block making machine in Ghana produce?

It depends on the model and the product. The QST8-15 reaches up to 90,000 standard bricks in an 8 hour shift, the QST1200 reaches 120,960, and the QST1800 covers 165,000 to 220,000. In 390 x 190 x 190 mm hollow blocks the QST1800 runs 27,000 to 36,000 per shift, because each cycle fills a larger mould.

What power supply does a block machine need?

Our presses step from 22.9 kW on the QT4-15 to 104 kW on the QST1800. The QST8-15 needs about 45 kW of supply, and the QT5-15 draws 37.4 kW. Induction motors pull 5 to 7 times rated current at start, so give us the voltage you have and whether it comes from the grid or a generator. We build to the supply you name.

Which pallet size should I specify?

Pallet size follows the model. The QST8-15 uses 980 x 860 x 22 mm, the QST1200 uses 1,350 x 880 x 25 mm, and the QST1800 uses 1,400 x 1,400 x 30 mm. A larger pallet carries more blocks per mould, so state your pallet choice and your blocks per mould together. If you already run pallets, send the dimensions and we match the line to them.

Why should I fix output before asking for a price?

Price follows configuration, and configuration follows output. A plant built for 8,000 blocks a day and one built for 60,000 blocks a day share no frame, mould, hydraulic unit or power supply. Once your shift output is written down, every supplier quotes the same plant and the figures become comparable. Without that number, two quotations can look similar and mean two different factories.

What product sizes can one machine make?

One press handles several shapes with a mould change: a solid brick of 240 x 115 x 51 mm, a hollow block of 390 x 190 x 190 mm, and a paver of 200 x 100 x 60 mm. Each mould has its own cycle, and the hollow block gives far fewer pieces per shift than the solid brick. Tell us which product carries your volume so we size the line around it.

Does curing depend on the machine I buy?

No. Strength comes from hydration over several days, and it depends on temperature and humidity in your yard, not on the press. Hold the water to cement ratio between 0.35 and 0.45 and keep a covered curing area sized to your daily output. Adding water for workability raises the cement bill and lowers strength at the same time, so plan the yard before the machine arrives.

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us