Block Plant Shift Log: Six Numbers per Shift
18 November 2026 · 6 min read
Quick answer
A machine rating is a ceiling, not a result: QST1800 is quoted at up to 220,000 standard bricks per 8-hour shift. What your plant actually did is six numbers written during the shift, not reconstructed at month end. Pallets formed, blocks per pallet with the mould number, rejects with the gate where they were caught, stopped minutes with a reason, cement and aggregate issued, and pallet turns. Divided by run time, those give output per hour, availability and cement per block, and those three are what a spare parts order, a cost per block figure or a warranty claim is really about.
Every block machine is sold with a rating. QST1800 is quoted at up to 220,000 standard bricks per 8-hour shift, QST1200 at up to 120,960, and both figures assume a standard brick, a good mould, pallets in front of the machine and a supply that does not drop. None of that describes your plant. The rating is what the machine can reach on a good day, with nothing else in the way.
A shift log closes the gap with six numbers, all written while the shift is running. Once they exist, output per hour, availability and cement per block stop being opinions, and they become the only honest basis for a spare parts order, a cost per block calculation or a warranty discussion.
Why does the first month never match the rated output?
The rated output is counted at a cycle time of 15 to 25 seconds, with the mould closed, a pallet waiting and mix ready. In the first month the machine is rarely the slowest element. Pallets are still arriving, the crew is learning the mould change, cement comes by pickup, and the yard has no room for a third day of curing. The machine can be running perfectly while the plant produces half its rating.
So the useful question is not how far output sits below the rating. It is which of the six numbers is holding it there. A week of logs answers that faster than a site visit, because the pattern repeats every shift and the numbers show it.
The six numbers, and what each one decides
Six rows fit on half a page. What makes the sheet work is that every row has a unit and a place to write it, so a blank row is visible from across the office. A log with a column called problems is not a log, it is a diary, and nobody reads a diary twice.
| Number | How it is captured | What it decides |
|---|---|---|
| Pallets formed | Stacker counter read at each hour, or a tally at the cuber | Output per hour, and whether the cycle or the handling is the limit |
| Blocks per pallet, with the mould number | Read once from the mould drawing, confirmed on the first and last pallet | Converts pallets into blocks, and keeps one day comparable with the next |
| Rejects, with the gate where they were caught | Counted at demould, at the cuber and in the yard at seven days | Whether the cause is mix, mould or handling |
| Stopped minutes, with a reason | One clock, one line per stop, reason from a fixed list | Availability, and the next capital purchase |
| Cement, sand and aggregate issued | Bags counted or silo reading at the start and end of the shift | Cement per block, and cost per block |
| Pallet turns, and pallets set aside | Pallets in circulation against pallets pulled for repair | Fleet size, and the replacement order |
Why are pallets the first number, not blocks?
The machine forms one pallet of blocks per cycle. How many blocks sit on that pallet is a property of the mould, not of the machine. Counting blocks therefore mixes two variables and makes two products incomparable. Counting pallets keeps the machine side of the sum clean, and the block figure is then pallets multiplied by cavities, adjusted for the products you actually ran.
This matters most on a mixed shift. Two hours of hollow blocks and six of pavers cannot be averaged in blocks without a cavity count for each. They can be compared as pallets per hour, which is exactly what the stacker and the cuber see.
What should the reject line look like?
A rejection rate without the gate is not actionable. A chipped corner seen at the cuber points at clamp pressure and guide wear. The same chip seen at demould points at the mould edge, the vibration setting, or a mix that is too dry. A crack that appears in the yard on day seven points at curing, not at the press.
Three gates are enough: demould, cuber, and the yard at seven days. Write the count and one line on appearance. Measure the first and last pallet of the shift as well, height and length, because a drift across the shift is a different fault from a constant error.
How do stopped minutes become a purchase decision?
Availability is run time divided by run time plus stopped time. It is the number that decides whether the next money goes into a machine, a mould or a pallet fleet. For that, the reason must come from a fixed list and not from free text.
- Mould change: planned, and the first candidate for a quick change fixture.
- Material wait: cement, sand or pallets missing, which is a purchasing problem no machine will fix.
- Power: a drop, a lost phase or a generator changeover, which is an infrastructure problem.
- Hydraulic or vibration fault: maintenance, and the hours feed the spare parts forecast.
- Cuber or stacker jam: handling, and the fix is usually guides, sensors or pallet condition.
- Crew: absence, training, or a handover that swallows the first hour.
One month of that list tells a buyer more than a demonstration. If material wait dominates, a bigger machine only buys idle capacity. If mould changes dominate, the answer is a second mould set, not a second press.
What does cement per block prove?
The cement line is the cheapest audit in the plant. A 390 by 190 by 190 mm hollow block weighs about 17 kg, and 1,000 of them hold 8.45 cubic metres of concrete once the voids are deducted. At a dose between 180 and 250 kilograms per cubic metre, the bags issued per 1,000 blocks can be checked against the blocks counted, without a laboratory.
When the two do not agree, one of three things is true: the dose has drifted, the block count is wrong, or material is leaving the plant. All three are worth knowing before a strength test fails, and none of them appears in a monthly total.
Why measure pallet turns at all?
A pallet leaves the machine, carries its blocks through curing, and comes back to the feeder. The number of turns per day is set by the curing period, not by the machine, and it is the other half of the capacity question. A plant with a 1,350 by 1,150 by 30 mm pallet fleet sized for two days of curing cannot run a three day cycle at the same output, whatever the press does.
Writing the turns next to the pallets set aside for repair also builds the replacement order on evidence. A fleet that loses four pallets a week has a maintenance problem, and a fleet that loses four a day has a stacker or cuber problem.
What does a month of logs buy you?
Four things that are otherwise argued about. A cost per block built on your own cement, power and pallet numbers rather than on a supplier's example. A spare parts forecast built on cycles rather than on calendar months. A warranty conversation with dates and stops on the table. And a capacity figure you can put in front of a bank or a customer without apologising for it.
It also settles the question buyers ask at month three: is the machine short, or is the plant short? The stop list answers it in one page, and the answer decides whether the next cheque goes to a machine, a mixer, a yard or a crew.
What should the sheet look like on paper?
Header: date, shift, model, mould number, crew size. Six number rows. Three lines of notes, one of them reserved for anything that will repeat tomorrow. Signature of the shift leader, and once a week the plant manager's.
Paper for the first month, a spreadsheet once the crew trusts the numbers, a screen after that. Starting with software is the usual reason a log dies in week two: the person at the machine has gloves on and a pallet waiting.
Keep the sheets. They are the only record that the machine was run as specified, and the only defence when a block fails on a customer's site.
What do we need to set your targets?
Shift targets are set from your configuration, not from a brochure: the model, the mould drawing with its cavity count, the pallet size and the number of pallets in circulation, shift length and breaks, cement dose and aggregate source, the product mix, and what your supply does on a bad day.
Send those seven items and you get a target sheet with pallets per hour, a cement allowance per 1,000 blocks and a stop budget, so the log has something to be measured against instead of a brochure number nobody can reach.
Frequently asked questions
How many lines should a shift log have?
Six number rows and three note lines. Every extra column is filled for a week and then left blank, and a blank column is worse than no column because it looks like a zero. Six rows are enough to calculate output per hour, availability and cement per block.
Can the log be completed at the end of the shift?
The stopped minutes and the pallet count cannot. Both are estimates by the time the shift ends. The material lines can be closed at the end, because the bags and the silo reading are physical counts. Write stops as they happen, on a board by the machine if the sheet is in the office.
How long should the sheets be kept?
At least the warranty period, and longer if a customer may dispute a block. The sheets are the evidence of how the machine was run, which is what a warranty claim and a capacity review both turn on.