How to Increase Block Machine Output Without a New Press

7 November 2026 · 6 min read

Quick answer

Block machine output is set by the slowest link in the line, not by the press alone. A QST6-15 runs a 15 to 23 s cycle and is rated at 8,640 to 11,520 hollow blocks in an 8 hour shift, and it reaches that band only when pallets, cuber, mixer and curing racks keep pace with the same cycle. Measure each link against the cycle before ordering a bigger press.

Get a price on WhatsApp Or send a written enquiry

How to increase block machine output starts with a stopwatch, not a purchase order. The press is the most expensive part of a block line and rarely the idlest, so the first gain usually sits in pallets, the cuber, the mixer or the mould change, and each costs a fraction of a second press. One number decides where to look, the forming cycle in seconds, because every station after the press has to finish its work inside that window.

The line is a chain with a press in the middle. Mixer, distributor, mould, stacker and curing racks each carry a job timed against the same cycle. A station that needs longer than the press does not slow it down gradually, it stops it in bursts, and a press standing still with a full mould is the only output figure that counts at the end of a shift.

What does a block machine deliver in one shift?

Take the QST6-15 as the reference, whose output is published per product. The forming cycle runs 15 to 23 s. On a 390 x 190 x 190 mm hollow block the mould carries 6 pieces, and the machine is rated at 8,640 to 11,520 blocks in an 8 hour shift. Check that against the cycle: 8,640 divided by 6 is 1,440 presses, 8 hours holds 28,800 seconds, and 1,440 presses across that total is 20 seconds each. The top figure is 1,920 presses at 15 seconds. The arithmetic closes, and that is the first test any claimed output has to pass.

Change the mould and the same frame produces something else. A 240 x 115 x 51 mm standard brick runs 32 to 36 per mould and 46,080 to 61,440 in the same 8 hours. Divide 61,440 by 8,640 and the gap is 7.1 times, from one press, one motor and one crew. Nothing changed except the mould and the pieces per cycle. That is why an output complaint is often a product mix complaint, and why the first question to a buyer is what he moulds, not how many machines he owns.

Where does the line lose its cycles?

Time each handover over ten cycles and put every reading beside the forming cycle. Four stations cause most of the loss, not the press.

StationWhat to time it againstHow the delay shows up
Pallet feedOne empty pallet for every press cycle, 15 to 23 sPress stands with a full mould waiting for a pallet
CuberQS-1000G-A at 16 to 18 s a layer, about 1,700 pallets a shift; QS-1200A at 15 to 18 s, about 3,800Loaded pallets queue at the stacker and block the press from behind
Mixer and skipQS-1200 series at 25 to 75 m3/h against the batch one cycle consumesHopper empties and the mould is filled light
Curing racksPallets held in the racks against the pallets one 8 hour shift fillsThe fleet dries up and the press waits on an empty pallet again

Five fixes that need no new machine

Work these in order, and judge each one on the same stopwatch.

  • Pallet count and turnaround. Count the pallets in the racks, then watch the press for ten cycles and write down every time it waits for an empty pallet. One wait in ten cycles means the fleet is short, and adding pallets is cheaper and faster than adding a press.
  • Cuber match. Time one layer. The QS-1000G-A builds a layer in 16 to 18 s at about 1,700 pallets a shift; the QS-1200A builds one in 15 to 18 s at about 3,800. If a layer takes longer than the press cycle, loaded pallets queue at the stacker and the press is blocked from behind.
  • Feeding continuity. Watch the hopper level across a whole shift and record every time it runs low. The QS-1200 mixer series delivers 25 to 75 m3/h depending on size, so the batch has to be ready before the mould empties, not after.
  • Mould change standard. Time a full change on the clock, first piece included. On an order book with several products this is the largest single loss, and it shrinks with a written checklist, saved parameters and a first block measured before the run starts.
  • Start-of-shift inspection and spare stock. Check vibrator bolts, oil level, limit switches and pallet thickness before the first cycle, and keep the wear parts that stop the line on the shelf. An unplanned stop costs more output than any speed setting.

Which machine has to wait first?

Compare two machines in the same family before assuming force equals speed. The QST6-15 works at 34.4 kW with 68 kN of excitation force and 25 MPa of rated pressure on a 980 x 680 x 20 mm pallet. The QST8-15 works at 44.9 kW with 95 kN and 31.5 MPa on a 980 x 860 x 22 mm pallet. Both are listed on a 15 to 23 s forming cycle.

The larger machine therefore carries more force and a bigger mould, and it promises no shorter cycle. That force compacts a larger area of mix and fills corners that a weaker head leaves light. The cycle is set by how fast the hydraulic system lifts and lowers the head, and by how long the distributor needs to fill the mould evenly. A plant that buys force to cure a slow cycle pays for the wrong variable, and the queue stays exactly where it was.

How many pallets does the shift actually need?

Count pallets from the cycle, because every press takes one pallet out of the fleet and returns it only after the block has cured. On the QST6-15 at 20 seconds the press makes 3 strokes a minute, which is 180 an hour and 1,440 in an 8 hour shift. Hold them in the racks for a full shift and the working fleet is 1,440, plus the pallet under the head and the one in the stacker. At 15 seconds it is 240 an hour and 1,920 in the shift, a third more steel.

Two conclusions follow. The pallet line moves with the cycle, so a faster press needs a larger fleet, not a smaller one. And the number is not something to buy by the truckload. Count what the racks, the machine and the stacker hold, and compare with what one shift fills. A plant that owns 1,440 pallets and cures longer than one shift must buy more pallets or slow the press, and slowing the press costs more than the pallets.

When is a bigger machine the right answer?

The next tier in the same family is the QST1000 and QST1200, at 48.9 kW and 57.6 kW, with 105 kN and 150 kN of vibration force and pallets of 1,100 x 880 mm and 1,350 x 880 mm. Above them sit the QST1500 and QST1800 at 69.1 kW and 104 kW, 220 kN and 280 kN, weighing 20 t and 34 t. Read those figures as mould area and compaction capacity, not as a speed promise, because the cycle windows stay at 15 to 23 s and 15 to 25 s.

Three conditions must hold at once before a new press earns its place.

  • The order book stays above current output season after season, and the plant turns work away or buys blocks in to keep up.
  • The press is the measured slowest station after pallets, cuber, mixer, racks and mould changes have been fixed. A bigger press behind a short pallet fleet waits just as long.
  • The site and the power allow it. A 104 kW machine needs a transformer, a cable run and a foundation to match, and the supply has to be checked before the model is chosen.

Send the product list with block sizes, the measured cycle, the pallet count in the racks, the shift length and the power at the site. Those five answers locate the short link, and the short link is almost always cheaper to fix than the press.

Frequently asked questions

How much output can I gain without buying a new press?

On most lines the gain comes from pallets and the cuber, not the press. A QST6-15 is rated at 8,640 to 11,520 hollow blocks in an 8 hour shift on a 15 to 23 s cycle. If the press waits for an empty pallet even once in ten cycles, or the cuber builds a queue behind it, the plant runs below that band. Fix the slowest link, then time the cycle again.

Which part of a block line is the bottleneck most often?

The pallet loop. Every press needs an empty pallet at the start of the cycle and returns a loaded one to the racks, so a fleet sized for one shift cannot feed a press filling 1,440 to 1,920 pallets. The cuber comes second, because a QS-1000G-A builds a layer in 16 to 18 s at about 1,700 pallets a shift while the press keeps cycling.

Does more vibration force mean more blocks per shift?

No. Force compacts the mix, it does not shorten the cycle. The QST6-15 works at 68 kN and the QST8-15 at 95 kN, and both are listed on a 15 to 23 s forming cycle. The higher force on the larger machine covers a bigger mould, 980 x 860 mm against 980 x 680 mm, so each press yields more pieces. Output per shift follows pieces per cycle and cycles per hour.

How many pallets do I need to run two shifts?

Count presses, not pallets in the yard. At a 20 second cycle the press makes 180 presses an hour, so an 8 hour shift fills 1,440 pallets. If blocks cure across two shifts before they are cubed, double that figure and add the pallet under the head and the one in the stacker. Buy to the count you calculate, because a short fleet stops the press.

When should I move up to a larger block machine?

Three conditions together: the order book stays above current output across seasons, the press is the measured slowest station after pallets, cuber, mixer and mould changes are fixed, and the site can carry the power. The step up, the QST1000 and QST1200, draws 48.9 kW and 57.6 kW with 105 kN and 150 kN of vibration force on 15 to 23 s and 15 to 25 s cycles.

Price guides
Machines that fit this
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us