Block factory setup in Saudi Arabia: plant sizing
25 October 2026 · 6 min read
Quick answer
Sizing a block factory in Saudi Arabia runs in three steps. First fix the product mix, because hollow block, solid block, pavers and kerbstones each set a different mould count and cycle. Then convert the sellable daily output into pieces per cycle and cycles per hour, with real stops deducted. Then size the pallet fleet and the covered yard to one full shift of production, because the yard caps the plant before the press does.
Block factory setup in Saudi Arabia is a sizing problem before it becomes a purchasing decision. The product mix fixes the mould count and the cycle, the cycle fixes what one press makes in a shift, and the curing yard has to hold every piece the press makes until it is hard enough to cube. Reverse that order and the buyer ends up with a press his yard cannot feed, or a yard that starves a press he has already paid for.
Four product families set four different plant configurations. Hollow blocks need cores and a stacker that keeps layers separate. Solid blocks and interlocking pavers need pressure and a platen wide enough for a full set. Kerbstones need a press that holds the edge square and, for a textured face, a finishing unit behind it. Each family also changes the pallet count per shift, which is the figure most feasibility studies leave out.
How does the product mix change the mould count and the cycle?
The cycle belongs to the press, the pieces per cycle belong to the mould. The double-direction hydraulic press family holds 31.5 MPa at an 18 to 22 second cycle with a moulding area up to 1,440 x 850 mm. The single-direction family runs a 20 to 25 second cycle across 850 x 700 mm up to the same 1,440 x 850 mm platen. On the wide platen a paver set fills the area, while a hollow block mould of 390 by 190 by 190 mm carries far fewer pieces for the same stroke.
Cores are what limit a hollow block mould. Every cavity needs steel between it and the next one, and the deep pockets must fill without bridging, which is why a hollow block mould holds fewer pieces on the same platen than a paver mould. Kerbstone moulds are long and narrow, pressed slowly with high force so the edge stays square and the tall blank releases clean. Output per hour follows the mould, not the tonnage.
How do you size the press from the daily output you can sell?
Start from the pieces you can sell in a day, then divide by the hours you will really run. QST8-15 is rated up to 90,000 standard bricks per 8 hour shift, QST1200 up to 120,960 and QST1800 up to 220,000 on the same basis. Those figures are standard brick, so they compare machines with each other and say nothing about a 390 by 190 by 190 mm hollow block. The conversion is the mould: pieces per cycle multiplied by cycles per hour.
Divide 3,600 seconds by the cycle to get cycles per hour, then derate. A 20 second cycle gives 180 cycles an hour on paper; take 60 minutes out of a shift for mould cleaning and a mix change and you run 7 hours, which is 1,260 cycles. Multiply by the cavities in your mould and you have blocks per shift at the press. Compare that figure with the blocks you can sell before you compare machine prices.
Why is the curing yard the real bottleneck?
Every cycle puts a pallet into circulation and keeps it there until the block can be cubed. A shift on a 20 second cycle is 1,260 pallets standing in the yard at once, plus the pallets in the return path and the ones under the cuber. The fleet, not the press, sets the ceiling on a pallet line, and the feeder has to keep pace: it cycles in about 13 seconds and holds three stacks in its bin.
Then choose the handling. A fixed cuber rated about 1,700 pallets per shift and a simple cuber rated about 2,000 pallets per shift set the pace the yard must feed. Pallet-free cubing removes the return system instead of speeding it up: QSMT1000 is rated up to 135,000 bricks of 240 x 115 x 50 mm per 8 hour shift and stacks the wet block as it leaves the mould, so no pallet travels back to the press. A forklift clamp then takes up to 10 layers of standard brick or 5 layers of hollow block straight to the truck.
What must the civil works be designed against?
The machine is a dynamic load, not a weight sitting on a slab. QST6-15 delivers 68 kN of excitation force on every cycle from a frame weighing 12 t on a 9450 by 3300 by 2700 mm footprint. The foundation has to absorb that repeated force without differential settlement, because a press that goes out of level throws the mould off line and the block dimensions drift with it.
Two documents decide the slab and neither comes from the machine supplier: a soil investigation with bearing capacity at the founding level, and the finished floor level of the yard with its drainage fall. Ask for both before the machine order. A soil report that arrives afterwards redesigns a foundation around a machine already in production, and the buyer carries that change alone.
Water belongs on the same drawing. A curing yard, a mixer washout and a wet press all put water at the machine feet, so the slab must fall away from the anchors and the settlement joints must stay clear of the vibrating frame. Cutting a joint into a cured slab beside a running press is the expensive way to learn where it should have been.
How should the investment be phased into two steps?
Stage one is one press, the batching and mixing that feeds it, and a covered yard sized for a full shift of production. Stage two is either a second press or a cuber, and which comes first depends on where stage one hurts. If the yard is the constraint, the cuber buys throughput for less capital than a press. If selling is the constraint, the second press buys output and the yard has to grow with it.
Build stage one so stage two is cheap. Leave the bay length for a second machine on the same line, run the batching above what one press draws, put the electrical room where a second feed can be added, and keep the yard rectangular so a second curing lane fits without moving the first. Those four decisions cost almost nothing at design stage and force a rebuild later.
Which four inputs do we need from you before we size anything?
Sizing starts from four answers, not from a machine model. With one of them missing, any configuration we send is a guess dressed as a quotation. The four are the product, the output, the site and the handling.
- Block spec and strength class: the exact dimensions of every product you will sell, the hollow rate, and the compressive strength class your customer will test against.
- Target daily output: pieces per day by product, taken from orders you can repeat, not from the capacity printed on a brochure.
- Site supply details: the aggregate and cement you can buy locally, the water you have, the power you can bring to the machine, and the soil and slab data for the foundation.
- Finished-product handling plan: whether you cube on pallets, cube pallet-free, or load straight to the truck with a clamp, because that choice sizes the yard and the pallet fleet.
Frequently asked questions
How many bricks per shift should I plan for when sizing a block machine?
Plan from standard brick ratings and convert with your own mould. QST8-15 is rated up to 90,000 standard bricks per 8 hour shift, QST1200 up to 120,960 and QST1800 up to 220,000. Divide 3,600 seconds by the cycle to get cycles per hour, remove 60 minutes for mould cleaning and mix changes, then multiply by the cavities in the mould you will actually run.
Why does the curing yard limit output more than the press does?
Because every cycle adds a pallet that cannot return until the block is hard enough to cube. One shift at a 20 second cycle keeps 1,260 pallets in the yard at once, plus the ones in the return path and under the cuber. If the covered area or the fleet is short, the press waits at the stacker however fast its cycle is.
Should I buy a cuber or a second block machine first?
Buy the cuber first when the yard and handling are the constraint, and the second press when orders are the constraint. A cuber lifts the pallets per shift the plant can process, roughly 1,700 on a fixed machine and 2,000 on a simple cuber, without adding moulding capacity. A second press adds blocks that still need covered floor to cure on.
What site data must be ready before the machine order?
A soil investigation with bearing capacity at the founding level, and the finished floor level of the yard with its drainage fall. Both decide the slab thickness, the reinforcement and the anchor design, and neither can be read off a machine datasheet. An excitation force such as 68 kN from a 12 t frame is a repeated load, so the foundation is designed against it, not against static weight.
Can a pallet-free line still stack hollow block?
Yes, within limits. Pallet-free wet cubing suits standard solid bricks and small hollow blocks, and QSMT1000 is rated up to 135,000 bricks of 240 x 115 x 50 mm per 8 hour shift. Tall hollow block, thin wall sections and textured pavers normally stay on pallets because the green strength cannot carry a stack that tall. Send the block list and the choice follows from it.
What changes if I add kerbstones to the product list?
Kerbstones add a long, narrow mould with few cavities per stroke, a slower demould to protect the edge, and usually a texturing or polishing unit behind the press. They also add floor area plus water and dust handling for that unit. Keep the bay length and the services for it in the stage one drawing even if you buy the unit in stage two.