Block Machine Factory Acceptance Test: Four Measurements to Witness
15 November 2026 · 6 min read
Quick answer
A factory acceptance test is a measured run of the machine in the factory, after the deposit and before the balance and the container. Four measurements decide it: ten consecutive forming cycles against the rated 15 to 25 s, the pressed block measured against the mould drawing, hydraulic pressure held at the rated 31.5 MPa under load, and current draw per phase against installed capacity. The buyer leaves with a signed report carrying the machine serial number, because that sheet is the only record that survives the voyage.
A block machine is bought on a datasheet and delivered as steel, and the factory test is the only hour when the two can be compared while engineers still stand beside the frame. Skip it and the first real measurement happens in your own yard, after freight is paid.
The test is not a demonstration. A demonstration is a machine making a block for a photograph. A test is a machine making ten blocks while somebody writes numbers down: cycle in seconds, height in millimetres, pressure on the gauge, amperes per phase.
What is the test measured against?
Every check compares a measured value with a figure that already exists on the machine page, so nothing is invented at the factory gate. A QST8-15 carries 44.9 kW installed, runs 15 to 23 s per cycle on a 980 x 860 x 22 mm pallet and develops 95 kN of vibration force. A QST1800 carries 104 kW and 280 kN on a 1,400 x 1,400 x 30 mm pallet, at 15 to 25 s per cycle and 34 t.
Write the same lines into the contract before the test: model, rated cycle range, pallet size with thickness, installed capacity and the rated pressure of 31.5 MPa. The acceptance clause then reads as measurements rather than an opinion, and it protects the seller too, who knows exactly what will be tested.
Which measurements carry the test?
Four measurements and one visual walk cover the machine, all taken with the production mould fitted, because the cavity count sets the output. Run them in this order: the cycle is timed before the cuber joins the loop, and the pressure is read while the machine is still hot.
- Cycle time. Time ten consecutive cycles from mould close to mould open and average them. A QST1200 rates 15 to 25 s, a QST8-15 rates 15 to 23 s. Multiply into your shift hours and compare with the rated output of 90,000 standard bricks on a QST8-15 or 220,000 on a QST1800.
- Pressure under load. Read the gauge during pressing, not at idle. Rated pressure is 31.5 MPa on the QST8-15, QST1200 and QST1800, and 25 MPa on the QST6-15. Watch for a drop during the hold, then walk the manifold and cylinder glands for weeps while the system is warm.
- Current draw. Clamp each phase against installed capacity: 34.4 kW on a QST6-15, 44.9 kW on a QST8-15, 57.6 kW on a QST1200, 104 kW on a QST1800. A phase far above its neighbours is a supply or wiring fault that will travel with the machine.
- Vibration and density. Confirm the frequency sits inside the 3,800 to 4,500 times per minute band and take blocks from the front, middle and back of one pallet. A low reading is invisible on the machine and appears three days later as a soft top layer and a reject rate nobody can explain.
| Measurement | What you record | Figure to compare |
|---|---|---|
| Cycle time | Average of ten cycles | 15 to 25 s, or 15 to 23 s on a QST8-15 |
| Pressure | Gauge during press and hold | 31.5 MPa, or 25 MPa on a QST6-15 |
| Block | Height, wall thickness, mass, corners | The mould drawing and cavity volume |
| Current | Amperes per phase | Installed capacity on the datasheet |
What does the block itself have to prove?
The block is the product, so the block is the evidence. Weigh one and divide its mass by the volume of the mould cavity to get a density figure you can repeat at home, then keep that block so the first block made in your yard can be weighed against it.
Then look at what a photograph never shows: the chamfer, the core walls and the face. A crumbling corner, a core wall that changes thickness along its length or a horizontal line across the face are all visible in the factory and much harder to argue about later. Keep three blocks with the date and serial number written on them.
What is checked on the panel and the safety circuit?
The electrical side is where a bare machine and a specified machine look most alike, because both have a cabinet and a screen. Open the cabinet, read the wire labels against the diagram, confirm the controller program is backed up on a medium that leaves with you, and check the screen language.
Then test the safety chain instead of looking at it. Each emergency stop should cut the cycle, and each guard should carry an interlock. Record which items were tested and which were only pointed at, because the difference matters at the first accident review.
- Panel sealing and cable entries, because a block yard is a dust yard.
- Motor protection settings recorded against each rating plate, so a tripped breaker can be traced later.
Who witnesses it, and what document comes out?
Either the buyer, the buyer's engineer, or an inspector appointed for the day. Where travel is impossible, ask for a live call during the run with the serial plate in frame and a stopwatch on the cycle. A video of a machine making blocks is not a test; a video of a stopwatch and a gauge is.
The report carries the model, the serial number, the date, the measured values, every deviation and the remedy agreed for each. Photograph the nameplate and the packing list against the crate numbers before the doors close.
On money, most contracts put the balance before shipment, which places it on the wrong side of the test. The cleaner order is deposit, test, report, balance, shipment, and it costs the seller nothing when the machine passes.
The test closes on the machine and the crate closes on the paperwork: foundation drawing with anchor bolt positions, electrical diagram, operation and maintenance manual, spare parts list, test report and mould drawing, in English and in Arabic when the crew reads Arabic. Add one complete set of foundation bolts and shims.
Then the packing: mould locked in the transport position, pallet magazine tied, cylinders retracted, machined faces coated, lift points marked on two opposite faces. A machine that passed its test and arrived with a bent base has failed twice.
What do you send us to quote a machine with a test plan?
Four items let the criteria go into the offer instead of being added after the invoice, so the quotation returns with the figures the test will be measured against rather than a range.
- The product list with sizes, and the pallet size and thickness you intend to run.
- The output you need per shift, and how many hours that shift really runs.
- The power supply at the site: voltage, phases and transformer rating.
- Whether you or an inspector will attend, and the language your crew reads.
Send those four and we answer with the model, the mould set, the pallet size, the rated figures the test will be measured against, and the spare parts that should travel in the same crate. If the test has to happen before a fixed date, send that date too, because the mould and the run are scheduled together.
Frequently asked questions
What is a factory acceptance test on a block machine?
A measured run of the finished machine in the factory before the balance payment and before shipment. The buyer or an inspector records ten cycle times, block dimensions against the mould drawing, hydraulic pressure under load, current per phase and vibration frequency, then signs a report with the serial number on it.
How long does the test take?
Plan a working day for the machine alone. Ten cycles at 15 to 25 s each is a few minutes of running, but measuring the blocks, walking the pressure circuit, checking the panel and timing a mould changeover fill the rest. Add a second day when a cuber or packing unit is tested with the line.
Can the test be done by video?
Partly. Ask for a live call during the run, the serial plate in frame, a stopwatch on the cycle and the pressure gauge visible, with the same numbers written into the report. Video gives you the sequence; it does not give you the block in your hand, so ask for three sample blocks to travel with the crate.
What happens if a measurement misses the rated figure?
That depends on the clause written before the test. The usual settlement is a remedy within a stated period and a retention held until the machine meets the figure on site. Without the clause, a missed figure becomes a discussion about what normal variation means, and that discussion happens after the freight is paid.