Quick answer
Block machine shipping insurance is bought against a declared value, not against the model, and the party that declares it carries the risk under both FOB and CIF from the moment the goods are on board. Cover the machine, the moulds, the pallets and the spares as separate lines, confirm the exclusions in writing before loading, and write any damage on the delivery receipt while the carrier is still present. A machine of 12 t or 34 t is too expensive to leave uninsured for a voyage.
Block machine shipping insurance is the line on an order that decides who owns the loss when a crate arrives with a bent frame or a mould set missing. It is not in the freight rate or the machine price. Cover is bought separately, against a value the buyer declares, and that declaration is where most disputes at destination begin. A buyer who reads the policy before the vessel sails has one conversation with an insurer. A buyer who reads it after the surveyor has gone has a file and no leverage. Machine mass runs from 12 t on a QST6-15 to 34 t on a QST1800, and every tonne of it is declared value.
Who carries the risk under FOB and CIF?
Under FOB the seller's risk ends when the goods are loaded on board at the load port. Under CIF the seller arranges the carriage and buys cover to the destination port, but the risk passes at the same point, and the policy the buyer inherits is the one the seller chose, usually the minimum the term allows. Two gaps follow. A buyer on FOB terms who assumes the seller insures to arrival owns an uninsured machine from the moment the crane lets go. A buyer on CIF terms who assumes the cover matches the invoice owns a policy that may not. In both cases the machine in its crates is uninsured unless somebody bought cover, and the bill of lading does not prove that anybody did.
Stow matters as much as term. A QST1800 measures 15,500 × 5,500 × 3,200 mm at 34 t and runs its hydraulics at 31.5 MPa, and where a machine that size travels on deck or as breakbulk rather than inside a container, a policy written for goods under deck does not describe the voyage. Deck stow is agreed separately, in writing, before loading. Ask while the machine is still in the yard; once the hatches close, the answer is whatever the wording already says.
What moves the premium?
The insurer quotes against four things: the value you declare, the route, the number of handling points, and how the machine is packed and braced for its own mass. The model number does not enter the quote. A 12 t QST6-15 and a 34 t QST1800 attract different premiums because the declared values differ and the bracing problem differs, not because they are different products. A 43 t QS1500 and a 14 t QST8-15 do not take the same bracing method, and the method is part of what is priced. Every extra movement on the route adds a handling point, and each handling point is a place where a crate can be set down hard. The insurer sets the rate; no supplier can quote it on their behalf.
Declare what it costs to put a working machine on your yard, not the figure printed on the invoice. Replacement at destination carries the freight you have already paid and the moulds that travelled with the machine. Declaring low to save premium is the most common reason a settlement comes back short, because many policies pay in the proportion that the declared value bears to the actual value. Confirm that basis in writing. Declaring high costs premium you cannot recover.
What should the cover name?
Name every item that travels on the same bill of lading, not the machine alone. The mould set, the pallet fleet and the spare parts are separate lines on the packing list and separate decisions on the policy. A mould set shipped as loose cargo is the item that most often disappears, because it is small enough to handle on its own, heavy enough for a forklift, and valuable enough to be worth moving. What the certificate does not name, it does not insure, whatever the machine is insured for.
Pallets are the same argument at lower value per unit. A QST6-15 runs a 980 × 680 × 20 mm pallet, and a fleet of them is a stack of flat steel that leaves a quay one bundle at a time. Put the count and the value on a separate line, or accept that the pallets are the buyer's loss.
| Item | Why it needs its own line | Where the file proves it |
|---|---|---|
| Machine | The mass that drives the bracing and the lifting plan, from 12 t to 43 t | Commercial invoice and bill of lading |
| Mould set | Ships loose, handles on its own, disappears first | Mould list on the packing list |
| Pallet fleet | Steel pallets leave one bundle at a time, 980 × 680 × 20 mm on a QST6-15 | Pallet count in the quotation |
| Spares and tooling | Low value per item, high cost per day of stoppage | Spare parts list |
| Crates, dunnage and braces | The packing method is what the packing exclusion is tested against | Bracing photographs and the packing specification |
What do policies normally exclude?
Four exclusions reach block machine buyers more often than any other: inadequate packing, delay, rust or corrosion from a wet container, and parts removed after arrival. Inadequate packing matters most: it is the exclusion an insurer reaches for first, and the one the supplier answers with bracing photographs. Delay is excluded as a commercial loss, not physical damage.
Rust from a wet container sits in a grey area. Condensation inside a sealed box is a normal result of a long voyage through a temperature swing, and many policies treat it as wear unless the container was flooded or the machine was shipped without protection. Parts removed after arrival fall outside cover because custody has already ended. Get all four answered in writing before loading, clause by clause, not as a general assurance that the cargo is covered.
- Packing: the bracing standard the wording expects, and who signs off that the crates meet it.
- Delay: written confirmation that a late machine is a commercial matter outside the cover.
- Rust: whether condensation inside a sealed container counts as damage or as wear here.
- Removal: the moment cover ends, and what the buyer must not open or strip before the survey.
How does a claim become a paid claim?
A claim is won or lost in the first hour at destination. Note the damage on the delivery receipt while the carrier is still present: which crate, which face, what is visible, how many photographs were taken. A receipt signed clean and a telephone call the next morning is the weakest position a buyer can hold. Photograph the crates and the markings before anything is opened, call the surveyor before the cargo leaves the quay or the yard, and keep the packing and the damaged parts until the survey is agreed in writing.
- The delivery receipt, with the damage noted and countersigned by the carrier.
- Photographs of every crate face, the markings, the seals and the damage, with a scale in frame.
- The surveyor's report, commissioned before the cargo was moved.
- The insurance certificate and the wording in force on the sailing date.
- Commercial invoice, packing list and bill of lading, with values that agree with each other.
- The bracing specification and the loading photographs from the supplier.
- A repair quotation or a replacement invoice from the destination market.
Where does insurance sit in the landed cost?
Insurance is a small line beside freight and a decisive one when something goes wrong. In the landed cost it belongs under the freight line and above handling at destination: freight moves the machine, insurance makes the freight recoverable when the machine does not arrive in the condition it left.
The usual error is to insure the machine invoice value and stop there. Freight already paid is not recovered from that figure, and the moulds are not covered unless they are named. When a crate is lost, the buyer pays the freight again to replace the machine and buys the mould set again, out of a settlement that covered the machine alone. Declare machine, moulds, pallets and freight together, and check that the certificate says so.
Frequently asked questions
Is the machine insured under CIF terms?
Not necessarily. CIF obliges the seller to arrange cover to the destination port, and the seller usually buys the minimum the term allows, often on the invoice value alone. Freight you have paid and moulds that travelled with the machine can sit outside that figure. Read the certificate before loading and ask for the wording that will be in force on the sailing date.
What value should I declare for insurance?
Declare what it costs to replace a working machine on your yard: the machine, the moulds, the pallets, the spares and the freight you have already paid. Declaring low reduces the premium now and the settlement later, because many policies pay in the proportion the declared value bears to the actual value. Confirm that basis in writing with the insurer.
Does the policy cover the moulds, pallets and spares?
Only if the certificate names them. A mould set often ships as loose cargo and is the item most likely to disappear in transit, and a pallet fleet leaves a quay one bundle at a time. Ask for each to appear as its own line with its own value, and check that the count on the packing list matches the number on the certificate.
What should I do first if a crate arrives damaged?
Note the damage on the delivery receipt while the carrier is still there, describing which crate and which face, and photograph the crate and its markings before anything is opened. Then call the surveyor and leave the cargo where it stands. Moving a damaged crate before the survey is the fastest way to lose a claim, and keeping the packing is what lets the surveyor judge the bracing.
Why do insurers refuse claims for rust?
Condensation inside a sealed container is normal on a long voyage through a temperature swing, and many wordings treat it as wear rather than physical damage. A refusal usually rests on whether the machine was protected and whether the container was flooded. Ask before loading how your wording treats condensation, and get the answer in writing rather than as an assurance.
Can freight be insured along with the machine?
Yes, and it should be, because freight is money you lose twice when a crate is lost: you pay it again to move the replacement. Declare the freight you have paid as part of the insured value, keep the freight invoice in the claim file, and check that the certificate states the basis. A policy written on the machine invoice alone leaves that money exposed.
Want an engineering opinion on your project?
Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.