Machine Arrival: The Inspection Before You Sign the Receipt

20 November 2026 · 5 min read

Quick answer

A block machine arrives as crates whose mass runs from 12 t on a QST6-15 to 34 t on a QST1800, and the inspection starts before the truck is unloaded. Count the cases against the packing list, photograph the crate exterior and its markings, check the lifting points against the weight painted on the case, and write every mark on the delivery receipt while the carrier is still there. Then open the crates in daylight and compare the contents with the packing list and the pre shipment photographs. A machine signed for as clean is a machine you own, damage included.

Get a price on WhatsApp Or send a written enquiry

The shipping file closes on the day the vessel sails and reopens on the day the truck stops at your gate. Between those two dates the machine has been lifted at least twice, driven over a road, stood in a container through a temperature swing, and lifted again. Most of what goes wrong in that period is visible in the first hour, if somebody is standing there with a checklist and the authority to write on the delivery receipt. Packing and marking belong to the pre shipment article; this page covers the receiving end, in the order the work happens.

What do you check before the truck is unloaded?

Start with the paper and the outside of the crates, in that order. The packing list gives the case count, the gross weight and the dimensions, and the driver's transport document should agree with it. A short count or a missing case number is settled before anything is lifted, not after the truck has left.

Then read the crate. Strapping cut and re tensioned, a panel lifted and refastened, fresh rust along a seam, a corner that has taken a hit: each is a question to ask before the crane is rigged. Photograph the four faces of every case with the number readable, then the painted weights and lifting points, because the rigging plan is built on those.

  • Case numbers and the total count, against the packing list line by line.
  • Gross weight and outer dimensions on each case, against the transport document.
  • Lifting points and the centre of gravity mark, before the rigging plan is fixed.
  • Strapping, welded stops and crate panels, for cuts, tears and fresh rust.
  • Signs that the crate stood in water or was opened in transit.

Which lifting gear does the arrival need?

The weight painted on the case is the number to plan against, and the spread is wide. A QST6-15 arrives at 12 t inside 9,450 by 3,300 by 2,700 mm, a QST1800 at 34 t inside 15,500 by 5,500 by 3,200 mm, and a pallet free QSMT1000 at about 12,000 kg on a 6,800 by 1,800 mm frame, which is low mass on a long body with no pallet magazine to spread the load.

Match the gear to the heaviest package, not to the total, and check the ground under the outriggers. A yard just levelled for the foundation is often soft at the edge, and an outrigger that sinks during the lift bends a frame before the machine has run a cycle.

ModelWeightOverall dimensionsPallet
QST6-1512 t9,450 × 3,300 × 2,700 mm980 × 680 × 20 mm
QST8-1514 t9,800 × 3,600 × 2,800 mm980 × 860 × 22 mm
QST120017 t11,500 × 4,550 × 2,800 mm1,350 × 880 × 25 mm
QST150020 t11,500 × 4,550 × 2,800 mm1,350 × 1,150 × 30 mm
QST180034 t15,500 × 5,500 × 3,200 mm1,400 × 1,400 × 30 mm
QSMT1000about 12,000 kg6,800 × 1,800 × 2,750 mmpallet free

What damage is visible, and what stays hidden?

Visible damage is the easy half: a bent guard, a cracked panel, a chipped mould edge, a flattened hose, a magazine rail out of line, a fan cowl pressed against the motor. Photograph each one where it sits, with a scale in the frame, before anything is straightened. The hidden half shows up at first power on: condensation inside a sealed crate, rust on machined faces, a sensor knocked out of position, a relay shaken loose, a motor fan that lost a blade.

That is where the pre shipment photographs and the no load test video earn their keep, because they show the same detail before the machine travelled.

How do you record it so a claim survives?

The delivery receipt decides most claims, and it is signed once. Write the exception on it before the driver leaves: which case, which face, what was seen, how many photographs were taken. A receipt signed clean, with the damage reported afterwards by telephone, is the weakest position a buyer can hold, because the carrier will point to the signature and the argument moves to the policy.

Keep the crate, the strapping and the packing until the machine has run under load. Do not repaint, do not reweld, and do not ship anything back before the inspection is agreed in writing.

  • The four faces of each case, with the case number readable.
  • Each damaged area with a scale in the frame, before any repair.
  • The open crate before unpacking, showing how the contents sat.
  • The packing list and the transport document in one photograph.
  • The machine nameplate, so the serial number in the claim is the one on the machine.

Where does the machine stand while the foundation cures?

Concrete under a base frame needs about seven days before the frame is set and 28 days to reach design strength before full cycle running. That wait is not idle time if the machine is stored properly. Put it under cover on timber bearers, panels off for ventilation, still protected from rain and from the dust of the civil work.

Two items suffer most. The cabinet collects condensation when the night turns cold, so keep the door closed and the desiccant fresh. The moulds and pallet faces rust and distort, so oil the machined faces, store the set flat on its base plate and keep pallets on level ground rather than against a wall.

Which parts come out of the crate on day one?

Unpack the documents first and keep them out of the yard: the foundation drawing at the revision that was manufactured, the electrical diagram, the manual, the spare parts list and the test report. The anchor layout on that drawing is what the civil contractor builds to, and it follows the frame revision, which follows the pallet.

Then count the loose items against the packing list on the day they are unpacked: foundation bolts and shims, mould clamp spanners, the controller backup, sensors packed separately, hoses shipped dry. A missing shim set is a week of waiting, and a missing backup is a conversation while the line stands still.

What should travel with the machine so this works?

Three things make the inspection possible: a packing list that matches what was loaded, photographs and a short video of the machine running before packing, and the foundation drawing at the manufactured revision. Ask for all three in writing, and confirm that the case numbers on the list are the numbers painted on the crates.

Before the order, tell us the discharge port, the unloading gear at site and the access road into the yard. Those three answers set the packing, the lifting points and whether the machine travels whole or in modules.

Frequently asked questions

What if the crate is damaged but the machine inside looks fine?

Note it anyway. The receipt describes the cargo as received, and a dented panel is a fact whether or not the machine was hit. Then inspect the machine at the point where the panel was struck, photograph it, and keep the panel until the machine has run under load.

Can the machine be stored outdoors until the foundation is ready?

For a short period with a proper cover and timber bearers, yes, but the electrical cabinet and the moulds should come indoors. The cabinet is the part that fails from condensation rather than from rain, and a mould set left on wet ground rusts on the faces that set the block dimensions.

Who pays for damage found at the destination?

It depends on where the damage happened and on what the documents prove, which is why the photographs and the noted receipt matter more than the argument afterwards. Packing faults are the supplier's scope, handling damage is the carrier's, and both are covered by the cargo insurance certificate that travels with the set.

Should the machine be started before the foundation is poured?

Only a no load check of the panel, the vibration motors and the hydraulic unit, and only if the machine stands level on solid ground. A frame that is not supported at all its points twists under its own press, and the full cycle test belongs on the finished foundation.

Price guides
Machines that fit this
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us