Block Machine Supplier List: Building a Shortlist of Three
18 November 2026 · 7 min read
Quick answer
A block machine supplier list is cut down by documents, not by price. Four tests remove names: the supplier can show a mould drawing for your first three products, it builds the press it quotes, it stocks moulds and wear parts for the exact models on the offer, and it can name the commissioning crew. Three offers are then normalised onto one Incoterm, one mould set, one pallet fleet, one spare parts list and one commissioning scope, because a quotation that itemises fewer than five lines cannot be checked.
Which four tests cut a long list down to three?
A block machine supplier list grows faster than the plant it is meant to equip, because every trader with a catalogue and every agent with a workshop photo can be added. It becomes useful at the moment you stop adding names and start removing them. Four tests do the removing, each answered from a document, not a sales call.
The first test is product range fit. A supplier whose catalogue was built around kerb stones will not hold a mould for the 390 × 190 × 190 mm hollow block that sells in your market, and one that sells only small pallet machines cannot supply the 1,400 × 1,400 × 30 mm pallet a QST1800 runs on. Write your product mix as a list of dimensions first, then strike out every supplier that cannot show a mould drawing for the first three items.
The second test is whether the supplier builds the press it quotes. Ask for the moulding host model, its installed capacity in kW and its working mass in t, then ask where the frame is welded. A trading office can repeat a QST1500 at 20 t and 69.1 kW from a catalogue; it cannot say what the frame weighs before the press head goes on. The third test is stock: moulds and wear parts held for the exact models on the offer. The fourth is people: a named commissioning crew, a count of technicians, and an acceptance procedure you can read.
How do you put three offers on one basis?
Three offers standing on three different bases cannot be compared, and the distance between the bases is usually larger than the gap in price. Normalise first. Fix one delivery term for all three, then ask each supplier to quote the same mould set, pallet fleet size, spare parts list and commissioning scope, so that a lower number means a lower cost.
The pallet fleet is the line most often left out. A QST1800 runs a 1,400 × 1,400 × 30 mm pallet and a QST1500 a 1,350 × 1,150 × 30 mm one, so the fleet a supplier quotes is a statement about the machine, not an accessory. Ask for the pallet count as a number and the price of one spare pallet. A fleet that runs short stops the line mid-shift, and the cycle time does not slow down while somebody finds more.
Commissioning works the same way. A scope counted in days is not the same scope as days plus people plus what gets signed at the end. Write it as days, as technicians and as the test the line has to pass, and the three offers collapse into one column of comparable numbers.
| Basis | What you fix for all three | What moves the total |
|---|---|---|
| Delivery term | One term and one named destination | Freight and risk split |
| Mould set | Number of moulds and the product dimensions each one makes | Pieces per mould, so output per cycle |
| Pallet fleet | Pallet dimensions, thickness and quantity | Machine served, plus the whole fleet cost |
| Spare parts | One list, one quantity per item | First months of uptime |
| Commissioning | Days, technicians, and the acceptance test | Who pays for the extra week |
The five lines every quotation has to itemise
A quotation that arrives as one total is a quotation you cannot check, and a supplier who refuses to break it down is telling you something about the rest of the file. Ask every name on the shortlist for the same five lines, in the same order, and the comparison takes an hour instead of a week.
The same page has to reach past the host. The cuber and the pallet feeder belong on it, not in a later annex: a QS-1200A cuber weighs about 18,000 kg and handles about 3,800 pallets per shift, and a QS-1200 pallet feeder cycles in about 13 seconds with 3 stacks in the magazine. If those figures are absent, the host numbers describe a plant that does not exist.
- Machine line: moulding host model, installed capacity in kW, working mass in t, cycle time, and the pallet size the machine is built around, since the frame follows the pallet.
- Mould set: how many moulds, the product dimensions each one forms, the pieces per mould and the mould drawing revision. A QST6-15 forms 6 hollow blocks of 390 × 190 × 190 mm in one mould, so the mould is half of the machine decision.
- Pallet fleet: dimensions, thickness, quantity, and the unit price of a single spare pallet, which is the number that tells you how a fleet grows later.
- Spare parts list: wear parts by part number and quantity for the first year, and a note on which of them your local workshop can supply instead.
- Commissioning and acceptance: how many technicians travel, for how many days, what test is run on your mix, and the number it has to reach before the machine is signed for.
Three red flags that end the conversation
Three signs end the conversation however close the total looks, and none is a matter of money. All three are cheap to check before the deposit and expensive to discover after it, because a supplier who fails one fails in the same place once the machine stands on your slab, and the remedy then is a new mould or a second visit, both arriving by sea.
- A quotation with no mould specification. If the file does not name the product dimensions, the pieces per mould and the mould material, the machine has no output figure at all, only a cycle time that was measured on somebody else's product.
- A pallet size that does not match the named model. A QST1200 uses a 1,350 × 880 × 25 mm pallet and a QST1000 a 1,100 × 880 × 25 mm one, so a file pairing a 1,400 × 1,400 mm pallet with either model has copied a price list, not configured a machine.
- A commissioning promise with no named crew and no written acceptance procedure. Sending an engineer is not a scope. Ask how many technicians, for how many days, and what the acceptance test measures on your mix.
What one page should you sign off before the deposit?
One page, read against the offer: the serial number and drawing revision of the moulding host, the pallet drawing with dimensions and thickness, the mould drawing with product dimensions and pieces per mould, the cuber model, and the names of the technicians who will commission the line. Every item is checkable, which is the point. You are not buying a promise, you are buying a machine whose parts can be counted.
Two more lines belong on the same sheet: the acceptance test, run on your mix at the factory before shipment if you can attend, and the spare parts list with part numbers. The factory test shows whether the machine holds cycle time on a real mix, and the part numbers are what your local workshop will ask for later.
Sign the page and the proforma together: the proforma names the money, the page names the machine the money buys, and both have to describe the same pallet, mould set and crew.
Send your own numbers with the inquiry
A shortlist of three is only as good as the brief behind it. Send the product mix with the dimensions of each item, the pallet size you intend to run, the destination port and the power supply you have. The reply is a quotation itemised on the five lines above, with the mould set and the pallet fleet priced separately.
If the model is still open, send the product list and the shift target through the inquiry form instead, and the shortlist gets built backwards from the products. Three offers on one basis beat ten catalogues, and the buyer who normalises first is the one who runs the acceptance test.
Frequently asked questions
How many block machine suppliers should a buyer shortlist?
Three is the workable number. Two leaves no tie-breaker when one offer turns out to be a catalogue copy, and five or six cannot be normalised by one person in a week. Three suppliers also make the factory acceptance test practical, because a buyer can attend three tests and cannot attend eight, and the visit is where the offer is confirmed or exposed.
What must a block making machine quotation itemise?
Five lines: the machine line with model, capacity and pallet size; the mould set with product dimensions and pieces per mould; the pallet fleet with dimensions, thickness and quantity; the spare parts list by part number; and the commissioning scope with technicians, days and the acceptance test. A quotation without those five cannot be set beside another offer, because each one hides a cost that reappears after the deposit.
Does the supplier have to build the press it quotes?
Not always, but the buyer has to know which case applies. A supplier that welds its own frame can answer what the frame weighs, which revision the anchor holes follow and how the mould clamps. An office that resells can still be useful, but only if it names the factory, passes the mould drawing through to that factory, and takes responsibility for the acceptance test, in writing.
Which pallet size should the shortlist fix first?
The one that belongs to the model you will run at full output, not the one in the first offer you received. A QST1800 is built around a 1,400 × 1,400 × 30 mm pallet, a QST1500 around 1,350 × 1,150 × 30 mm and a QST1200 around 1,350 × 880 × 25 mm. Fix it before you ask for prices, then every offer is priced on the same fleet.
What should a buyer verify before paying the deposit?
One page: the host serial number and drawing revision, the pallet drawing, the mould drawing with product dimensions and pieces per mould, the cuber model, and the names of the commissioning technicians. Add the acceptance test and the spare parts numbers. Check the page against the offer before the proforma is signed, because after the deposit the only remaining leverage is the balance.