Block Making Plant Equipment: Cost Beyond the Press
29 October 2026 · 7 min read
Quick answer
A block making plant is the press plus five purchases the press cannot run without: batching, a mixer, a pallet fleet, curing space and a cuber, with the transformer sized last and usually forgotten. On a QST6-15 the host draws 34.4 kW and on a QST1800 it draws 104 kW, so the power line can move the total more than the host model does. Price the five, then compare presses.
Buying block making plant equipment rarely fails at the press. It fails at the parts nobody priced. The moulding host is one line on the quotation, and around it sit five more purchases that decide whether the plant reaches the cycle printed in the catalogue: batching, mixing, pallets and circulation, curing, and cubing with packaging. Add the electrical capacity that feeds them all and the real scope appears.
Quotations for the same host come back at very different totals for this reason. Some equipment travels with the host as one package, some is quoted separately because it depends on your building, and some is chosen by output and then forces the site power to grow. Read a quote line by line and the gap stops looking like negotiation.
What equipment does a block making plant need besides the press?
Six groups, and each is sized from the host cycle rather than from a catalogue page. A host finishing a pallet every 15 to 23 seconds sets the rate the rest of the plant must hold.
- Batching. A PL series batching machine weighs aggregate on a pre-set ratio with three-point induction sensors, doses fast then slow, and runs a vibration device against bin bridging. Capacity is set from your block machine cycle, so it is quoted with the host.
- Mixing. A CMP vertical shaft planetary mixer moves the batch on a complex path for a uniform mix and discharges through a gate for fast turnaround. Capacity is quoted against your moulding cycle and batch size, so ask for the figure in writing.
- Pallets. The board follows the host and nothing else fits: 980 x 680 x 20 mm on a QST6-15, 980 x 860 x 22 mm on a QST8-15, 1,350 x 880 x 25 mm on a QST1200, and 1,400 x 1,400 x 30 mm on a QST1800. A QS-1200 feeder holds 3 stacks and adds a board every 13 seconds on 3 kW.
- Curing. The QSDJ belt-rack line lifts each layer onto its own rack level and moves it on a lithium battery transfer car. The QSRGY finger-car line positions a sub-car by encoder under a mother car and cures in a single layer as standard.
- Cubing and packaging. The QS-1000G-A fixed cuber runs 16 to 18 seconds per layer at about 1,700 pallets a shift on 15 kW, the QS-1000G-B 15 to 18 seconds at about 2,000 pallets on 29 kW, and the QS-1000G-C double station 12 to 15 seconds at about 3,800 pallets on 44 to 45 kW. A QS forklift clamp lifts 500 to 800 standard bricks or 40 hollow blocks.
- Electrical capacity. Installed power climbs from 34.4 kW on a QST6-15 to 44.9 kW on a QST8-15 and 104 kW on a QST1800, and the stacker on the host adds 3.0 kW or 3.7 kW. This line decides transformer size and cable section.
Which items come inside the host quotation and which are priced separately?
Three rules sort a quotation quickly. Anything sized by the host cycle travels with the host. Anything sized by your building or yard is quoted separately. Anything sized by output caps the plant if it is bought small.
- Inside the host package. The mould set, one pallet set, the stacker, and the hydraulic and electrical components named in the specification. Board size is fixed by the model.
- Quoted separately, sized by the host. The batching machine, the mixer and the cuber, because each is calculated from the cycle and the batch. Ask for capacity figures on the quotation.
- Quoted separately, sized by the site. The pallet fleet, the curing line, the transformer and cable, the foundations and the forklift clamp. This is where two quotations for the same press separate.
How do pallets and curing space change the total?
Pallets are a multiplication, and the line most buyers underestimate. A host at 23 seconds finishes 156 pallets an hour; cure for 24 hours and the plant needs 3,744 boards in circulation before a single spare is counted. The same host at 15 seconds passes 240 an hour and needs 5,760. On a QST1800 those boards are 1,400 x 1,400 x 30 mm.
Curing space then decides how many of those boards come back each day. A rack set holding fewer positions than the host fills in one curing cycle becomes the ceiling of the plant, and no press capacity fixes that. Measure covered floor and clear height before choosing a curing line.
Why does the cuber decide whether the press is a bottleneck?
A cuber takes cured pallets off the line, and its cycle must be shorter than the host's. Put the QS-1000G-A at 16 to 18 seconds per layer and about 1,700 pallets a shift behind a QST1800 forming every 15 to 25 seconds, and the cuber becomes the ceiling, while the 104 kW host waits.
Move up the range and the arithmetic closes: 2,000 pallets a shift on the B at 29 kW, 3,800 on the C at 44 to 45 kW. That power step lands on the transformer before it lands on the cuber.
- Match by pallets per shift. Multiply the host hourly rate by the shift hours and compare with the cuber figure, not with its price.
- Pay for the double station only when the host can feed it. A 3,800 pallet cuber behind a host forming 1,700 is idle capital on 19,000 x 7,500 mm of floor.
- Plan the yard with the clamp in mind. One bite of 500 to 800 standard bricks or 40 hollow blocks sets truck loading speed, and the forklift must be rated for it.
How much power must the site actually supply?
Add the host, the stacker and the cuber and the connected load passes the host figure by a wide margin. A QST6-15 draws 34.4 kW, its stacker 3.0 kW and a fixed cuber 15 kW, so the site is sized on their total, not on the press alone. On a QST1800 the host draws 104 kW and the C cuber adds 44 to 45 kW. The transformer and main cable follow that total, and lighting, the mixer and the batching machine sit on top of it.
This item arrives last on most quotations, because the machine supplier quotes machines and the electrical contractor quotes cable. Put the connected total on one sheet and hand it to both.
In what order should block making plant equipment be bought?
Order matters because each purchase fixes the next. Settle the product mix and the host first, calculate every other line from it, and run the site work in parallel with delivery.
- Host and mould set. Cycle and pallet size fix everything downstream, so this is the only line chosen on its own.
- Power check. Connected load, transformer rating and cable route belong before the signature, because the answer can change the building.
- Batching and mixing. Capacities are quoted against the host cycle, so they are ordered and sized in the same conversation.
- Pallets and curing. Fleet count from the hourly rate and curing hours, rack positions from covered floor and clear height.
- Cubing, packaging and handling. The cuber sits above the host pallet rate and the clamp is matched to the forklift, not to the plant.
- First-year spares and commissioning. Wear parts, one spare mould set where the product mix is wide, and the commissioning window written into the contract.
Frequently asked questions
What equipment is included in a block making plant beyond the machine?
A working plant adds batching, a mixer, a pallet fleet with its feeder, a curing line, a cuber and packaging, plus the transformer and cable that carry the load. The host forms one pallet per cycle and none of those stages is optional. Batching and mixing are sized from the cycle, pallets from the curing hours, and the cuber from the pallet rate the host produces.
How much does block making plant equipment cost beyond the press?
No single figure applies, because the extra lines are sized by your building and yard rather than by the host. What can be stated is the shape of the bill: a pallet fleet in the thousands of boards, a curing line with racks or a kiln, a cuber between 15 and 45 kW, and a transformer sized on the connected total rather than on the host alone. Ask for each line as a separate item.
Why is electrical capacity often missing from a quotation?
Machine suppliers quote machines, and transformers and cable belong to the electrical contractor, so the item falls between two documents. The gap is wide: 34.4 kW on a QST6-15 against 104 kW on a QST1800, before a 15 kW or a 44 to 45 kW cuber is added. Confirm the connected load in writing before the transformer is ordered.
Which cuber suits a host on a 15 to 23 second cycle?
The fixed QS-1000G-A at 16 to 18 seconds per layer and about 1,700 pallets a shift fits a compact host and keeps one operator busy. Step to the B at 2,000 pallets or the C at 3,800 when the host can feed them. A cuber rated above the host wastes capital, and one rated below it caps the plant.
Can the equipment be bought in stages?
Yes, and it is the usual path: host with batching and mixer first, manual handling with a forklift clamp, then the curing line and the cuber as orders grow. The risk sits in the layout, because a curing area laid out for manual stacking rarely accepts a rack line later. Reserve the floor and the clear height for the final layout on day one.
Want an engineering opinion on your project?
Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.