Factory planning

Block Making Plant Feasibility Study: Numbers That Decide

20 November 2026 · 6 min read

Quick answer

A block plant feasibility study splits into two kinds of number. The market side, meaning selling price, cement and aggregate delivered at your gate, labour, land, power tariff and transport radius, can only be collected locally and must never be invented. The machine side is already fixed: on a QST6-15, a 15-23 s cycle at 6 hollow blocks of 390 x 190 x 190 mm gives 8,640-11,520 blocks per 8 h at 34.4 kW. Build the market side from three quotations and treat the machine figure as a ceiling.

Get a price on WhatsApp Or send a written enquiry

Which numbers can only come from your own market?

A block making plant feasibility study fails in one of two ways. The writer invents the local market and the bank finds out at due diligence, or the writer spends six weeks chasing prices and never builds the output side at all. The work divides cleanly, and that division is the whole method. Some figures exist nowhere except in your own city and only you can collect them. Other figures are fixed by the machine you are buying, and copying those from a catalogue is bookkeeping, not research.

  • Selling price for each product, in the sizes and strengths your buyers already use. Three competitor price lists, not one, and the grade each list refers to.
  • Cement and aggregate delivered at your gate. A quarry price and a gate price differ by the cost of the last thirty kilometres, and the study needs the second.
  • Labour rate per shift crew, and the supervisor above it. A crew of four at an invented rate is wrong in two lines at once.
  • Land or shed, the slab under the machine, and the yard area for curing. Rent and purchase are separate lines and both belong in the capital table.
  • Power tariff and the incoming capacity at the site. The demand of the line is fixed by its installed capacity, while the supply in front of it is not.
  • Transport radius, meaning the distance at which delivered block stops competing with a plant closer to the buyer.

Which numbers come from the machine specification?

Six figures on a specification sheet need no local research at all: the forming cycle, the pieces per mould, the output those two produce over a shift, the installed capacity, the machine weight and the overall dimensions. On a QST6-15 running a 390 x 190 x 190 mm hollow block, the cycle is 15-23 s at 6 blocks per mould, the shift figure is 8,640-11,520 blocks per 8 h, installed capacity is 34.4 kW with 3.0 kW on the stacker, the machine weighs 12 t and measures 9,450 x 3,300 x 2,700 mm.

Those physical figures are financial figures in disguise. Twelve tonnes of machine and its vibration decide the slab, not the catalogue. The 9,450 x 3,300 x 2,700 mm envelope sets the shed height and the lifting gear that places the press, 34.4 kW plus 3.0 kW on the stacker sets the incoming supply and any generator behind it, and the 980 x 680 x 20 mm pallet sets the pallet count, which is a capital line of its own.

These are the only numbers in the file that arrive already proven, because they are measured on a machine that exists. Everything else is your market or your assumption.

FigureQST6-15What it sets in the study
Forming cycle15-23 sPallets per hour, and therefore the shift ceiling
Hollow block per mould6 blocks of 390 x 190 x 190 mmBlocks per pallet, and the product the cost table is built on
Shift output, hollow block8,640-11,520 per 8 hThe volume the unit cost table is divided by
Installed capacity34.4 kWIncoming supply, cable size, generator behind it
Stacker power3.0 kWAdded to the load list, not to the press alone
Machine weight12 tSlab, foundation, lifting plan, freight
Overall dimensions9,450 x 3,300 x 2,700 mmShed height, floor area, access for the low-bed
Pallet size980 x 680 x 20 mmPallet count in the fleet, and a capital line of its own

Working the shift output from the cycle time, in the open

Take the same machine at the fast end of its cycle. One cycle is one pallet, so 3,600 s divided by a 15 s cycle gives 240 pallets an hour, 240 pallets times 6 blocks per mould gives 1,440 blocks an hour, and 1,440 blocks over an 8 h shift gives 11,520 blocks. Run the chain backwards to check the other end: 8,640 blocks a shift is 1,080 blocks an hour, which is 180 pallets an hour, one pallet every 20 s.

That arithmetic describes the machine at the mould and nothing beyond it. It ignores the pallet that has to come back, the mould cleaned between grades, the mixer waiting on a cement delivery, the cuber stopped because the curing area is full, and the truck that arrives at four in the afternoon. A study that ends at 11,520 is a catalogue with a formula written on it.

So carry the ceiling into the model as a ceiling and run the plant at a share of it. What belongs in the revenue line is shift output multiplied by an availability you are willing to defend in a meeting, and 60% of the shift is the stress case most lenders accept.

The six tables a feasibility study has to carry

Six tables, and each answers one question that a lender or a partner asks in sequence: what the market buys, what must be paid before the first block, what a block costs to make, which stage limits the others, how many blocks cover the costs, and what breaks the plan first.

The unit cost table is where most drafts die quietly. Cement and aggregate are priced per tonne at the gate, so the table needs a mix design stating kilos of cement per block before those prices turn into a cost per piece. Pallet wear is a cost per pallet divided by the blocks it carries over its life. Rejects belong in that table as a measured percentage, never as zero.

Break-even is one figure at the bottom of that table: the blocks per shift at which the plant covers its costs. Set it against the shift ceiling that came out of the cycle time, and the gap between the two is the margin the plant has to sell into.

Sensitivity is the table a reviewer turns to first. Price down 10%, cement up 10%, availability down to 60% of the shift. If break-even stays under the ceiling in the third case, the file has room in it. If it does not, the partner has found the only question worth asking.

TableQuestion it answersWhere the numbers come from
Demand and product mixWhat the market buys, in which sizes and gradesYour own survey of buyers and competitors
Capital cost, line by lineWhat must be paid before the first blockMachine, moulds, pallets, foundation, incoming supply, forklift, curing area
Unit cost per blockCement, aggregate, power, labour, pallet wear, rejectsYour delivered prices divided by the shift output
Capacity and the bottleneckWhich stage limits all the othersCycle time, cuber capacity, curing area, truck loading
Break-even volumeBlocks per shift at which cost equals revenueThe capital table, the unit cost table, your price
SensitivityWhat breaks the plan firstPrice down 10%, cement up 10%, availability at 60%

What do most versions of this study get wrong?

Three habits account for most studies that fail review, and each one is cheap to avoid.

  • The catalogue as the study. A supplier's shift figure is a ceiling at a stated cycle. It becomes plant production only after availability, changeover and rejects are applied, and none of those three is printed in a catalogue.
  • Capital without working capital. The machine is paid for once; cement, aggregate, pallets, power and the crew are paid every month before the first invoice is collected. A sheet that lists only equipment shows a plant running out of cash in its best month.
  • Capacity at a full shift, thirty days a month. Eight hours of uninterrupted running is a test condition, not a calendar. Maintenance, holidays, power cuts and rain on the curing yard all come out of the same 8 h.

Building the file that survives a credit committee

The machine side can be finished before you commit to anything. Cycle, pieces per mould, shift output, installed capacity, weight, envelope and pallet size are all fixed by the model you pick, so a two-page sheet covering two or three models is a morning's work, and it settles the capacity argument early.

The market side takes longer and holds the value. Send the local figures with a source beside each one, the product mix you mean to sell, and the incoming capacity at the site. With those in hand, the machine columns can be filled from a real specification, and the study stops being a document about machines.

  • Product mix and sizes, with the price each one fetches.
  • Cement and aggregate delivered prices, with the mix design you intend to run.
  • Shed dimensions, slab condition, incoming capacity and yard area for curing.
  • The shift pattern you can staff, and the availability you are prepared to defend.

Frequently asked questions

What is the first number to fix in a block making plant feasibility study?

Fix the shift output ceiling from the machine you are considering, because it is the only figure that is already measured. On a QST6-15 the 15-23 s cycle at 6 hollow blocks per mould gives 8,640-11,520 blocks per 8 h. Every revenue line and every unit cost in the file is divided by that volume, so an estimate built on a guessed output carries the error everywhere.

How many blocks per shift should the study assume?

Use the lower end of the published range, then apply an availability factor. A machine rated 8,640-11,520 hollow blocks per 8 h is quoting a test condition, not a calendar. Putting 60% of the shift into the model at the low end gives a number a lender will not challenge, and any month that beats it is a bonus rather than a shortfall.

Do I need a bank-grade study before ordering a block machine?

No. Order the machine-side sheet first: cycle, pieces per mould, shift output, installed capacity, weight, dimensions and pallet size for two or three models, all taken from specifications. That settles the capacity decision in an afternoon. The full six-table study is needed when a lender or a partner puts money in, and it can be built on top of that sheet without redoing the machine columns.

Which cost lines do buyers usually leave out?

Moulds beyond the first set, the pallet fleet, the slab and foundation, the incoming cable and panel, the forklift and clamp, the curing area and its handling, and spare parts for the first year. Working capital is the biggest omission: cement, aggregate, power and the crew are paid every month before the first invoice is collected, and that gap is a capital requirement, not a cash flow detail.

How should a local price be handled when it cannot be confirmed?

Put the assumed value in the cell, mark it as assumed in the next column, and carry it into the sensitivity table. A cement price that moves 10% or a selling price that falls 10% should each be a row in that table. A reviewer accepts a labelled assumption and argues with its size; a reviewer who finds an invented figure presented as fact stops reading the rest.

Price guides
Machines that fit this
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us