Machine selection

Block Machine Capacity for a Road Project

22 November 2026 · 6 min read

Quick answer

Capacity for a road project is read from the daily draw the contract creates, then turned into pallets per hour by dividing 3,600 by the cycle in seconds. A QST6-15 on a 980 x 680 mm pallet at 15 to 23 seconds sits between 156 and 240 pallets an hour. Choose the smallest class whose slow end covers the draw, then buy curing space and a second shift before a second machine.

Get a price on WhatsApp Or send a written enquiry

A road contract does not arrive as a machine question. It arrives as a quantity, a product list and a date: so many metres of kerb, so many square metres of interlocking paver, and a drainage run that wants hollow blocks on site before the first layer of asphalt goes down. Block machine capacity for a road project is therefore read backwards from that delivery window. The machine class comes from the daily draw the window creates, never from a nameplate figure on a brochure.

The contractor who buys on the nameplate usually ends up with a larger press than the contract needs and a smaller curing area than the delivery date allows. The two are bought separately and they fail together: a press that fills more pallets an hour than the yard can hold simply stops earlier in the shift.

A road contract pulls three product families

Road work is not one product. Kerb stones come in profiles that follow the drawing, interlocking pavers come in a thickness the wearing course sets, and hollow blocks sit behind the kerb line in drainage runs and culverts. Each family brings its own pallet fill, its own mould and its own settling behaviour. A plant that is fast on pavers can be slow on kerbs, because the cycle is not the only clock in the building: the mould must fill evenly before the press closes, and a narrow kerb profile fills differently from a wide paver bed.

  • Kerb stones: the highest value per pallet, the fewest pieces on it, and the profile that decides your mould spend.
  • Interlocking pavers: a wide bed, a fast fill, and the product most likely to be ordered in several colours.
  • Hollow blocks for drainage and culverts: the heaviest pallet of the three, and the one that exposes a weak vibration setting.
  • Edge units and channel sections: ordered late and in small numbers, which is where changeovers multiply.

What does each product change cost you?

Every product change stops the press, empties the mould, fits another and restarts. The changeover is measured in hours, and the first pallets after it are settling pallets: the mould has to find its fill, vibration amplitude has to be trimmed for a different mass, and the operator watches the first stacks instead of the counter. Those pallets are usually downgraded or returned to the crusher. On a road contract the change is not occasional, because a kerb line, a paver yard and a drainage run are called off in sequence, so the changeover count belongs in the tender arithmetic rather than in maintenance.

Buy one mould per product family you actually contracted, and run each family in a block of days rather than alternating daily. The changeover then costs one lost shift a week instead of one lost shift a day.

Pallets per hour: 3,600 divided by the cycle

Output on these machines is counted in pallets, not in blocks, because the pallet is what leaves the press and what occupies the yard. Pallets per hour is 3,600 divided by the cycle in seconds. A QST6-15 running a 980 x 680 x 20 mm pallet at a 15-23 s cycle gives between 156 and 240 pallets an hour. A QST8-15 with a 980 x 860 x 22 mm pallet and the same 15-23 s cycle gives the same band on a larger bed. A QST1200 with a 1,350 x 880 x 25 mm pallet at 15-25 s gives 144 to 240.

Run the multiplication at the slow end before signing, then at the fast end to see the ceiling, because the gap between the two is what a slow mould fill, a cold morning or a mix that wants more vibration takes back. Installed power moves with the class: 34.4 kW on the QST6-15 at 25 MPa rated pressure, 44.9 kW on the QST8-15 at 31.5 MPa with 95 kN of vibration force, and 57.6 kW on the QST1200 at 31.5 MPa with 150 kN.

Which model class covers which daily draw?

Read the daily draw off the tender, not off the brochure. A contract that calls for a few hundred kerb units a day sits in the QST6-15 class, where a 980 x 680 mm pallet and 34.4 kW of installed capacity are enough and the yard stays compact. A programme that runs a paver yard and a kerb line at the same time moves up to the QST8-15, whose 980 x 860 mm pallet buys about a quarter more pallet area without a change in cycle time. Feeding several sites from one plant puts you in the QST1200 class, with 1,350 x 880 mm of pallet, 57.6 kW installed and 150 kN of vibration force to fill the wider bed.

ModelPalletCyclePallets per hourInstalled
QST6-15980 x 680 x 20 mm15-23 s156-24034.4 kW
QST8-15980 x 860 x 22 mm15-23 s156-24044.9 kW
QST12001,350 x 880 x 25 mm15-25 s144-24057.6 kW
QST18001,400 x 1,400 x 30 mm15-25 s144-240104 kW

How much curing space does the first delivery need?

Blocks cannot leave the yard on the day they are pressed. Every pallet that comes off the machine stands somewhere until the concrete can take handling, so the yard has to hold the whole production of the stand time before the first truck loads. At 200 pallets an hour, one 8-hour shift leaves 1,600 pallets standing, and a second shift stacks another 1,600 on the same slab. That figure, not the press, sets the slab you pour and the drainage under it.

  • Pallet count: pallets standing in the yard are pallets not circulating under the press, so a tight yard quietly caps the daily draw.
  • Slab and drainage: a yard that holds water softens the bottom layer of every stack in it.
  • Aisle width between stacks, because a forklift or a clamp needs room to set a stack down without touching the next one.

Why is a second shift cheaper than a second machine?

A second machine adds a press, a second mould set, a second stacker and a second operator, and it doubles the curing area at the same instant. A second shift adds people and power, and it runs on the press, the moulds and the yard you already own. Inside a fixed delivery window the shift is the cheaper way to raise the daily draw, because the plant is paid for once and then run twice.

The limit is the crew and the maintenance window, not the press. Two shifts leave no daylight for a mould change, so the change has to be planned at handover, with the next mould on the floor and the next pallet stack staged before the first shift ends. That is a scheduling habit and it costs nothing to install.

The three numbers to bring to a quotation

A quotation for a road contract is either exact or approximate, and the difference is three numbers the buyer already holds before any supplier is called.

  • Daily draw per product: pallets a day for kerbs, for pavers and for drainage blocks, taken from the tender quantities divided by the working days you really have.
  • Delivery window: the date of the first truck and the date of the last, because the window decides whether one machine on one shift is enough.
  • Site power: the transformer capacity you can actually connect, measured against an installed draw of 34.4 kW on the QST6-15, 44.9 kW on the QST8-15 and 57.6 kW on the QST1200.
  • Add the ground area you own and the stand time your mix needs, and the class, the mould set, the yard and the shift pattern all fall out of the same sheet.

Frequently asked questions

How do I size a block machine for a road contract?

Convert the tender into a daily draw in pallets, then divide 3,600 by the cycle in seconds to get pallets per hour. Multiply by the hours you plan to run. Pick the smallest class whose slow end still covers the draw, then check that the yard can hold the whole production of the stand time before the first truck loads.

Does one machine cover kerbs, pavers and hollow blocks?

One press can run all three, but not at the same rate and not without a mould change between them. Each product needs its own mould, and the first pallets after a change are settling pallets. Budget one mould per family and plan the call-off sequence so each family runs in a block of days rather than alternating with another product daily.

How many pallets per hour does a 15 second cycle give?

240 pallets an hour, because 3,600 divided by 15 is 240. At the slow end of the same band, 23 seconds, the figure drops to about 156, and a 25 second cycle on the larger models gives 144. Quote the band rather than the fast end, since the slow end is what the plant actually averages over a shift with real mix and real mould fills.

How much yard space does curing take before the first delivery?

Enough for every pallet pressed during the stand time. At 200 pallets an hour, each 8-hour shift adds 1,600 pallets to the ground, plus aisles for the clamp or forklift. Buyers usually count the press first and the slab second, which is why yards run out of room in the first week of a road programme.

Should I add a second machine or a second shift?

A second shift first, while the delivery window is the constraint. It adds crew and power and uses the press, moulds and yard already paid for. A second machine only makes sense when the draw exceeds what two shifts can press, or when two products must run at once and the changeover cost is larger than the second press.

Price guides
Machines that fit this
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us