Block Making Machine Capacity Comparison: Output per Shift

9 November 2026 · 7 min read

Quick answer

Capacity is pallet area multiplied by cavities per mould multiplied by cycles per hour, so a comparison only holds inside one mould and one product. At a 20 s cycle, eight hours give 1,440 pallets on every class; the class that wins is the one with the 1,400 x 1,400 mm pallet, provided the mixer, the pallet fleet, the curing yard and the cuber can absorb that flow.

Get a price on WhatsApp Or send a written enquiry

A block making machine capacity comparison usually settles on one impressive number in a quotation, and that number travels worst of all. Capacity is not a property of the press. It is the product of three measurable things: the area of one pallet, the number of cavities in the mould, and the cycles the machine completes in an hour. Move the pallet from 980 x 680 mm to 1,400 x 1,400 mm and the same 20 s cycle carries 2.9 times the mould area, with nothing else on the machine changed.

The specification figures used here are ours, and every derived number is arithmetic written out in the same sentence, so you can repeat it with a stopwatch and a tape. That matters when two suppliers quote the same model class and the totals differ by a third.

The arithmetic behind every capacity claim

Start with the pallet, not with the bricks. A QST6-15 pallet is 980 x 680 mm, which is 0.67 m2 of moulding area. The machine completes a cycle every 15 to 23 s, so at 20 s it makes 180 cycles in an hour. Eight hours hold 28,800 s, and 28,800 divided by 20 gives 1,440 pallets in a shift. That is the first half of the calculation, and every term is checkable on the floor.

The second half is the mould. Pallets become blocks only when you multiply by the cavities cut into the steel plate, and cavities are set by the drawing you order. The same frame carries a six-cavity mould for 390 x 190 x 190 mm hollow block, or a mould for a much smaller unit with far more pockets. Two buyers with identical machines and different moulds do not own the same capacity.

A capacity figure quoted without pallet size, cycle time and cavity count is therefore not a comparison. It is one number from one plant, on one mould, making one product, across one shift length.

Four machine classes on the same basis

Take the four classes we build, hold the shift at eight hours and the cycle at 20 s. All four put 1,440 pallets through that shift, so the difference is how much material each pallet carries.

ClassPallet (mm)Cycle (s)Vibration (kN)Power (kW)Weight (t)Published shift capacity
QST6-15980 × 68015-236834.4128,640 to 11,520 hollow blocks, 390 x 190 x 190 mm
QST8-15980 × 86015-239544.914Up to 90,000 standard bricks
QST12001,350 × 88015-2515057.617Up to 120,960 standard bricks
QST18001,400 × 1,40015-2528010434Up to 220,000 standard bricks

Read the second column against the last. The QST1800 pallet is 1.96 m2 against 0.84 m2 on the QST8-15, which is 2.3 times the area, and its published 220,000 standard bricks a shift is 2.4 times the 90,000 of the QST8-15. Area and published output move together, but only roughly: the mould decides how much of the pallet becomes saleable block.

The hydraulic press class sits on the same arithmetic with a different purpose. Moulding area runs from 850 x 700 mm on the QS600 to 1,440 x 850 mm on the QS1500, the cycle is 20 to 25 s, and total power runs from 46.9 to 88.4 kW. Even the largest press moulds 1.22 m2, about 62% of a QST1800 pallet, and spends it on pavers and kerbs.

Where the plant, not the press, becomes the limit

A press on a 20 s cycle asks its plant for a pallet every 20 s, 1,440 times in a shift, and each request is a physical event somewhere behind the machine. Four points answer it, and the slowest one sets the real shift output. A press faster than any of the four simply waits, and the wait never appears on the specification sheet.

Plant pointWhat it capsSymptom the buyer sees
Mixer and batchingThe volume of mix per cycle, and whether a batch reaches the hopper inside one cycleShort feeds, thin corners, the press idling with a half-filled feeding box
Pallet fleetThe boards in circulation between the magazine, the machine and curingThe press waits for an empty board, or green blocks are stacked before they hold
Curing areaHow many filled pallets can stand undisturbed, and for how longBlocks stripped early, corners lost at the cuber, a share of the shift returned as breakage
CuberPallets per shift: 1,700 on the QS-1000G-A, 2,000 on the QS-1000G-B, about 3,800 on the QS-1000G-C and the QS-1200AA queue of cured pallets, forklifts waiting, and the press stopping because the green side is full

The cuber is the easiest of the four to size because its number is published. At 16 to 18 s a layer, eight hours give 1,600 to 1,800 layers, and the QS-1000G-A is rated at about 1,700 pallets a shift, so arithmetic and rating agree. The double-station QS-1000G-C and the QS-1200A are rated about 3,800 each. The margin between the press count and the cuber count is the only thing that absorbs a jam, a mould change or a truck that arrived late.

Does a bigger press always deliver more blocks?

No. Delivered output is the smallest of the four plant numbers, not the largest figure in the quotation. A QST1800 carries 104 kW and 34 t of frame, and none of that matters if the cuber handles 1,700 pallets while the press pushes 1,920 at the fast end of its cycle, or if the curing yard cannot hold a shift of filled pallets, or if the mixer cannot deliver a batch inside one cycle.

Pallet count is the most common self-inflicted cap. Every cycle needs an empty board at the magazine and a place in curing for the filled board that just left. A fleet sized on the best cycle, with no allowance for boards standing in the kiln, gives a press that stops every few minutes.

Which class fits which order book?

The class follows the order book, not the ambition. Three questions settle it: how many block sizes you sell, whether the yard can cure what the press makes, and whether the plant runs one shift or two.

  • QST6-15, 34.4 kW, 12 t: one product family, one shift, 1,440 pallets at 20 s, which is 8,640 to 11,520 hollow blocks of 390 x 190 x 190 mm on the six-cavity mould.
  • QST8-15, 44.9 kW, 95 kN, 980 x 860 mm pallet: 26% more pallet area, published up to 90,000 standard bricks, and room for pavers beside hollow block.
  • QST1200, 57.6 kW, 150 kN, 1,350 x 880 mm: a mixed order book on two shifts, published up to 120,960 standard bricks.
  • QST1800, 104 kW, 280 kN, 1,400 x 1,400 mm: contract supply, with the cuber and the pallet fleet sized to its 1,440-pallet shift first.
  • QS600 to QS1500 presses, 46.9 to 88.4 kW, 20 to 25 s: pavers, kerbs, PC stone and thin-wall units, where face and edge carry the price.

Compare a class on your own product, your own pallet and the hours your crew really works. A shift with a mould change, a mixer wash-down and a truck loading at the gate is not 28,800 s of pressing.

How do you verify capacity on a trial run?

Watch twenty consecutive cycles with a stopwatch and write down each interval. The average gives you the cycle time. The longest interval gives you what the plant costs per cycle.

  • Cycle time over 20 cycles, timed from mould close to mould open, on the product and mould you intend to buy.
  • Pallets fed per hour, counted at the magazine, not read off the panel.
  • Green strength and corner loss: lift one fresh block by hand and look at the arris.
  • Empty pallets at the magazine when the shift ends. A short stack is a plant limit, not a fault.

Ask for the trial on your block size and your mix, and ask what the plant did in the hour before it. A machine shown on a fresh mould, a full pallet magazine and an empty cuber is showing its best twenty minutes, not its shift.

Frequently asked questions

How is block machine capacity calculated for one shift?

Multiply pallet area by the cavities in the mould to get the volume per cycle, then multiply by cycles per hour and by shift hours. A 980 x 680 mm pallet holds 0.67 m2, and at a 20 s cycle the machine completes 180 cycles an hour, which is 1,440 pallets in an eight-hour shift. Cavities come from the mould drawing, so one frame gives different totals on different products.

Why do two machines with the same cycle time produce different totals?

Because cycle time sets the number of pallets, not the number of blocks. A 980 x 680 mm pallet carries 0.67 m2 of mould area, a 1,400 x 1,400 mm pallet carries 1.96 m2, so at 20 s both make 1,440 pallets and the larger one moves 2.9 times the material. Cavity count then decides how much of that area becomes saleable block.

What limits output before the press does?

The mixer, the pallet fleet, the curing yard and the cuber, usually in that order of discovery. The press asks for a pallet every 20 s, and the slowest of the four answers the request. A 1,700-pallet cuber behind a press that pushes 1,920 at the fast end of its cycle is a plant that queues every day, and the queue gets reported as a machine problem.

Should a hydraulic press be compared with a block machine by brick count?

No. The press line from QS600 to QS1500 moulds 850 x 700 mm up to 1,440 x 850 mm at a 20 to 25 s cycle, and its work is pavers, kerbs, PC imitation stone and thin-wall units where the face and the edge carry the price. Compare square metres of finished product per shift and surface quality, because brick count measures a different job.

What should be measured on a trial run before ordering?

Time twenty consecutive cycles and keep the longest interval, not the average. Count pallets at the magazine rather than reading the panel, watch the cuber through a full layer sequence, and look at the corners of a block you lift by hand. Then ask how many empty pallets were waiting when the shift ended, because that number describes the plant around the machine.

Price guides
Machines that fit this
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us