How Many Concrete Blocks Can a Machine Produce Per Day?

1 November 2026 · 6 min read

Quick answer

Daily output is pieces per mould multiplied by cycles per hour and by shift hours. On the QST6-15 row, 6 hollow blocks of 390 x 190 x 190 mm per mould at 20 seconds a cycle is 180 cycles an hour, 1,080 blocks an hour and 8,640 in eight hours; at 15 seconds it reaches 11,520. The press is rarely the limit once the mixer, pallet circuit, curing yard and cuber are counted.

Get a price on WhatsApp Or send a written enquiry

How many concrete blocks can a machine produce per day is not a number the supplier decides. The forming cycle writes it: pieces per mould, cycles per hour, paid hours, minus whatever stops the press. Two plants on the same model can land half a band apart. The arithmetic below runs on published row data, then meets the four systems that usually run slower than the press.

The output chain: pieces per mould, cycles per hour, hours paid

The chain has four inputs. Pieces per mould comes from the mould, not from the frame: on a QST6-15 a hollow block mould of 390 x 190 x 190 mm carries 6 pieces, while a standard brick mould of 240 x 115 x 51 mm carries 32 to 36 because the pockets are smaller. Cycles per hour comes from the forming cycle: 3,600 seconds divided by 20 seconds is 180 cycles, divided by 15 seconds is 240. Hours paid is the shift you actually run. Stopped time is the subtraction.

The product of the first three is a ceiling, never an average. The subtraction is not a courtesy discount, it is a list of named events: a mould change, the first hour while the mix is trimmed, a mixer batch that arrives after the mould is empty, an empty pallet magazine, a cuber a layer behind. Ask for it in hours, not as one efficiency percentage.

Worked example: 6 hollow blocks per mould on a 15 to 23 second cycle

This is an example built from published row data, not a specification for a site. Six hollow blocks of 390 x 190 x 190 mm sit in one mould on a 980 x 680 mm pallet, and the row quotes 8,640 to 11,520 pieces per 8 hours. At 20 seconds a cycle, 3,600 seconds give 180 cycles an hour, 180 times 6 pieces give 1,080 blocks an hour, and eight hours give 8,640. At 15 seconds, 240 cycles times 6 pieces give 1,440 an hour, and 11,520 per shift.

The brick mould on the same frame explains the wider band. A standard brick of 240 x 115 x 51 mm runs 32 to 36 to the mould; 32 pieces at 180 cycles an hour is 5,760 bricks an hour, which is 46,080 in eight hours, and the quoted 61,440 sits where a fast cycle meets a full mould.

How many cycles fit in a shift?

Eight hours is 480 minutes and no press forms through all of them. There is a warm-up, a mix trim after the first pallets, and at least one mould change in a plant selling more than one product. The slow end of the cycle alone costs a third: at 23 seconds, 3,600 seconds give about 156 cycles, 6 pieces give roughly 939 blocks an hour, and eight hours about 7,500, against 11,520 at 15 seconds.

Shift length is where two quotations quietly diverge. An eight hour figure and a 24 hour figure are not the same claim, and the second carries three crews, night lighting and maintenance with nowhere to sit. Ask which hours are counted, and whether they are paid hours or machine hours.

Which bottleneck decides the real daily number?

Once the plant is complete, the press is rarely the slowest unit in it. The pallet feeder cycles in about 13 seconds against a 15 to 23 second forming cycle, close enough that an empty magazine stops the press within a minute. The cuber works by layer: 15 to 18 seconds on a QS-1200A at roughly 3,800 pallets per shift, 16 to 18 seconds on a QS-1000G-A at about 1,700 pallets per shift.

The mixer sets a floor under the cycle, because a batch has to be ready before the next mould fill, and the weighing time belongs to that floor. The curing yard sets a ceiling on pallets in circulation: each one is under the press, in transit, or standing in curing, and when the third state runs out of floor the press stops for a reason that has nothing to do with concrete. Handling closes the chain: a forklift clamp takes 40 hollow blocks or 500 to 800 standard bricks per bite, 5 hollow layers or 10 brick layers, which decides how many truck loads a shift finishes.

Why the daily target picks the machine class, and the price

The daily figure is the first decision, not the last, because it selects a class, and the class carries the two largest cost blocks: installed capacity and steel weight. The compact end runs 34.4 kW and 12 t on the QST6-15, 44.9 kW and 14 t on the QST8-15, then 57.6 kW and 17 t on the QST1200, and 104 kW and 34 t on the QST1800. A buyer asking for 100,000 standard bricks in eight hours is not shopping inside the compact class, because the top of that class is 61,440, and the step up moves the transformer and the foundation with it.

Read a quotation as six blocks rather than one number: the host machine at the class the output requires, mould sets at one per product, the mixer and batcher sized to the cycle, the pallet fleet, curing and cubing, and freight with commissioning. Output sets the first and third blocks, the mould count weights the second, the pallet count the fourth and fifth.

What a quotation request has to state

Two suppliers can both answer 10,000 blocks a day and mean different machines. The written request is what closes that gap before the numbers are compared.

  • Block size and pieces per mould as the mould will run them: 390 x 190 x 190 mm at 6 per mould, or 240 x 115 x 51 mm at 32 to 36 per mould.
  • Shift length in hours and shifts per day, and whether cleaning, start-up and mould change sit inside those hours.
  • Target pallets per shift, a figure a plant manager can count at the gate, because it sizes the pallet fleet, the curing floor and the cuber.
  • Whether the figure asked for is an 8 hour number or a 24 hour number, since the two differ by a factor of three before any stoppage is counted.
  • The product mix and how often it changes, because a mould change is stopped time and a plant selling four products pays for it four times.

How do you test an output claim before you sign?

Compare only inside one product. A static press forming 16 pieces of 200 x 100 x 60 mm per mould on a 20 to 25 second cycle, and a vibration machine forming 6 hollow blocks of 390 x 190 x 190 mm on a 15 to 23 second cycle, are not comparable on blocks per hour, because the piece differs. Convert both to pieces per hour at a stated cycle and a stated mould count, and the comparison becomes arithmetic.

Then check the cycle against the frame. The 15 to 25 second band covers the QST1200 at 57.6 kW and the QST1800 at 104 kW and 34 t, and the heavier machine does not form faster inside that band, it forms the same band with more steel and more mould area. Where a claim beats the class, ask which product and which fill it was measured on.

Frequently asked questions

How many blocks does a QST6-15 make in a day?

On the published row, 8,640 to 11,520 hollow blocks of 390 x 190 x 190 mm in eight hours at 6 pieces per mould, and 46,080 to 61,440 standard bricks of 240 x 115 x 51 mm at 32 to 36 per mould. Those figures assume forming runs through the shift, and a plant with a slow cuber or a short pallet fleet lands under the bottom of the band.

Why is my machine making fewer blocks than the catalogue figure?

The loss is usually outside the press. Check four things in order: whether the mixer delivers a batch inside the forming cycle, whether the pallet feeder at a 13 second cycle keeps the magazine full, whether the cuber keeps up at 15 to 18 seconds a layer, and whether the curing yard has floor for every pallet in circulation. A press on a 15 to 23 second cycle cannot make up time lost at any of those four.

Does a 24 hour figure mean three times the 8 hour figure?

Not in practice. The arithmetic triples the hours, so the ceiling triples with them, but a 24 hour plant needs three crews, lighting, a curing yard that keeps turning over and maintenance windows the day shift used to absorb. Ask whether the figure counts paid hours or machine hours, and whether cleaning and mould changes sit inside it.

Which machine class covers 10,000 blocks in a day?

For hollow blocks of 390 x 190 x 190 mm, 10,000 pieces in eight hours is 1,250 an hour, and 6 pieces per mould puts that at about 208 cycles an hour, under 18 seconds a cycle, which sits inside the 15 to 23 second band of the QST6-15 on paper. The decision then rests on the mixer, the pallet count and the curing floor.

Is a faster forming cycle always more output?

Only if the plant behind it matches. Cycle bands overlap heavily: 15 to 23 seconds on the compact frames, 15 to 25 seconds on the QST1200 and QST1800, 20 to 25 seconds on the QS600 static press at 16 pieces of 200 x 100 x 60 mm per mould. A shorter cycle with a slow cuber and a thin pallet fleet produces a queue rather than a day of blocks.

Price guides
Machines that fit this
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us