Block Machine Foundation: Four Figures the Civil Contractor Needs

17 November 2026 · 5 min read

Quick answer

A foundation is sized on four figures, and the machine price is not one of them: the mass, the load at each support point, the anchor bolt layout at the drawing revision that was manufactured, and the level tolerance the pallet line needs. Average mass per square metre of footprint is about 385 kg on a QST6-15 and about 399 kg on a QST1800, yet a pallet-free QSMT1000 reaches about 980 kg, so the smallest machine in the yard can be the hardest floor.

Get a price on WhatsApp Or send a written enquiry

What four figures does the design start from?

Mass, and the position of the mass. Load per support point, which is not the total divided by four on a machine whose press end carries the ram, the vibration unit and a hopper of mix. Anchor bolt layout at the revision that was manufactured. Level tolerance on the finished top, measured the way the erection crew will measure it.

Everything else, from concrete grade to reinforcement, belongs to the structural engineer who signs the drawing. The supplier's job is to put the four figures on one sheet and keep them consistent with the machine that actually ships, not with the one in the offer.

How much mass lands on each square metre?

Mass per square metre barely moves from the smallest pallet machine to the largest, 385 kg against 399 kg, because the footprint grows with the frame. That is a useful sanity check on a quotation: a model that claims a much larger output on a footprint that did not grow is claiming more force per square metre than the frame can carry.

ModelWeightFootprintFloor areaAverage mass per m²
QST6-1512 t9,450 × 3,300 mm31.18 m²about 385 kg
QST8-1514 t9,800 × 3,600 mm35.28 m²about 397 kg
QST120017 t11,500 × 4,550 mm52.33 m²about 325 kg
QST150020 t11,500 × 4,550 mm52.33 m²about 382 kg
QST180034 t15,500 × 5,500 mm85.25 m²about 399 kg
QSMT1000about 12,000 kg6,800 × 1,800 mm12.24 m²about 980 kg

Why is the average not the number to build to?

Because the machine does not stand on its whole footprint. The moulding station carries the ram, the vibration unit and the hopper at one end, while the stacker and the pallet magazine stand on their own supports, and the frame between them may carry nothing but its own weight. A slab designed on the average is a slab designed on a number that no single point ever sees.

Ask for the mass at each lifting point and the mass at each support point, with the position of every foot on the base drawing. A QST1200 and a QST1500 share an identical outline, and their support loads differ by a pallet and three tonnes, so the outline alone cannot be used to copy an old foundation.

Why can a small machine be the harder floor?

The QSMT1000 weighs about 12,000 kg on 6,800 × 1,800 mm, which is 12.24 m², or about 980 kg per square metre. A QST1800 carries 34 t on 85.25 m², about 399 kg. The pallet-free machine concentrates its mass because it has no pallet magazine and no pallet return to spread over, and that concentration goes into the floor.

The equipment around the host does the same. A QS-1200A cuber covers 12,000 × 3,000 mm, 36 m², and weighs about 18,000 kg, which is about 500 kg per square metre, more than any pallet machine on the list. A bay is designed on the highest mass per square metre in it, not on the host machine alone.

Which drawing revision do the anchors follow?

The one that was manufactured, not the one in the offer. Anchor holes are set relative to the frame, and the frame changes when the pallet changes: a QST1200 at 1,350 × 880 × 25 mm and a QST1500 at 1,350 × 1,150 × 30 mm share an outline but not the same pallet line.

Freeze the general arrangement revision before the first pour and write the same revision number on the foundation drawing. A foundation poured to revision A under a machine built to revision B is the most expensive kind of near miss in a block plant, because the concrete is not wrong, it is only in the wrong place.

When the pallet changes after the pour, the buyer has three routes and only one of them is cheap. Cut the anchors and re-pour, which costs the cure clock again. Fit a transition base frame, which is a steel part drawn after the fact. Or go back to the machine revision the foundation was poured for, which is a product decision taken at the last minute. Decide which route you can live with before the concrete truck is booked.

Seven days, then twenty eight days

Concrete under a base frame needs about seven days of cure before the frame is set, and 28 days to reach design strength before the press runs at full cycle. Pour while the machine is still at sea and the two clocks run at the same time, which is the tightest workable sequence for a plant that wants to start within a month of arrival.

Skip the cure and the vibration finishes the job: anchors pull out, the frame goes out of level, and the pallet line stops holding tolerance. The cost of that mistake is not the second pour. It is the crane booked twice, the crew standing idle and the demurrage behind the container.

The sheet to hand the civil contractor

One page, signed by both sides, before the first pour. The same sheet is what an erection crew reads on the first morning, so it saves a second cost that never appears in a budget: the waiting day.

  • General arrangement drawing at the manufactured revision, with the four overall dimensions and the base outline.
  • Machine mass, and the mass at each support point with the position of every foot.
  • Anchor bolt layout, anchor size and the revision number, identical to the machine drawing.
  • Level tolerance to be measured on the finished top, and who measures it before the crew starts.
  • Positions and masses of the pallet line, the cuber and the forklift lane, since each adds its own load to the same slab.
  • Drainage direction and the cable route from the panel to the machine terminal box.

What do you need from us before the first pour?

Send the model you intend to run at full output, the pallet size you will actually buy, and the bay outline with the crane standing position. The reply is the four figures above on one sheet, plus the general arrangement drawing at the revision that will be manufactured.

If the model is still open, send the product list and the shift target instead. The foundation follows the pallet, the pallet follows the product, so a decision made on paper is always cheaper than a decision made on a slab.

Frequently asked questions

How thick should a block machine foundation be?

Thickness, concrete grade and reinforcement are the structural engineer's figures, because they depend on the soil and on the slab below. What we supply is the input to that calculation: the mass, the mass at each support point with its position, the anchor layout at the manufactured revision, and the level tolerance the pallet line needs.

Is the foundation different for a QST1200 and a QST1500?

The outline is identical at 11,500 × 4,550 × 2,800 mm, but the mass is 17 t against 20 t and the pallet is 25 mm against 30 mm thick. Anchor positions follow the manufactured revision, so design for the model you will run at full output, not for the one first quoted.

Can the machine stand on an existing industrial slab?

Sometimes. Check the mass per support point against the slab you have, including any void, basement or mezzanine under the bay, and check the level tolerance the pallet line needs. A slab that carries a loaded forklift is not automatically a slab that carries 399 kg per square metre plus one concentrated foot.

How long after the pour can the machine run?

About seven days of cure before the base frame is set and 28 days to design strength for a full cycle. A machine that arrives before the foundation is ready waits at the port or in the yard, and those waiting days cost the crane, the erection crew and the container demurrage together.

Price guides
Machines that fit this

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us