How Long Does Installation Take for a Block Making Line?

2 November 2026 · 7 min read

Quick answer

A block making line takes three to five weeks from site handover to the first saleable block, and the crew's own work is about one week of that. The rest belongs to concrete: a foundation needs seven days of cure before the base frame is set and 28 days to reach design strength. Power connection, container sequencing and the approval of the first mould run on separate clocks, and any of them can move the date.

Get a price on WhatsApp Or send a written enquiry

How long does installation take for a block making line? Three to five weeks from the day the site is handed over to the day the first block passes the acceptance check, and only about one of those weeks belongs to the erection crew. The calendar is set by concrete, power and shipping, three items the machine supplier does not control. Buyers who plan for the crew's week and forget the other three are the ones who pay demurrage and keep a crane idle.

The phases below are the ones we work to, and each has an owner. Read the owner column before the duration column: a phase that belongs to the buyer cannot be accelerated by paying the supplier more.

PhaseDurationOwner
Foundation, cure and anchors7 days before base frame, 28 days to design strengthBuyer civil works
Power supply and transformer2 to 4 weeks lead time on a new transformerBuyer utility
Unloading and reassembly2 to 4 daysBoth
Erection and alignment3 to 5 daysErection crew
Wet commissioning and first mould2 to 3 daysErection crew
Acceptance run and training2 days, then 7 and 28 day rechecksBoth

What does the machine itself take once it is on the foundation?

About one week, and that week is dense. Day one takes the lift path and the level, day two the mechanical alignment of the frame, the guides and the pallet line, day three the hydraulics and the vibration settings, day four the first mould and the cycle that the machine actually delivers, days five and six the training matrix, and day seven the measured acceptance run. A 12 t QST6-15 and a 34 t QST1800 both fit that sequence, but not the same crane.

The number that sets the crane is the heaviest single module, not the machine weight on the specification sheet. Ask for the lifting plan with the general arrangement drawing, because a frame that ships in three bolted sections is lifted three times and each lift needs its own rigging.

How long does the foundation hold up the schedule?

Seven days is the shortest honest answer, and 28 days is the real one. Concrete poured for a block machine base frame has to be cured before the frame is set, or the anchors pull out under the vibration, and it has to reach design strength before the press runs at full cycle. If the foundation is poured after the machine ships, the site will be ready at about the same time as the container, which is the tightest workable sequence.

Two details stretch the seven days into three weeks more often than buyers expect. The anchor bolt layout has to match the drawing revision that was actually manufactured, not the one in the offer. And the floor around the base has to carry the pallet line and the forklift, so a slab that was poured for a shed usually needs a thicker section under the machine and a level tolerance the crew can measure.

Why does a larger model add weeks that a small one does not?

Compare the shipping envelope. The QST6-15 measures 9,450 x 3,300 x 2,700 mm and weighs 12 t, on a 980 x 680 x 20 mm tray with 34.4 kW installed. The QST1800 measures 15,500 x 5,500 x 3,200 mm and weighs 34 t, on a 1,400 x 1,400 x 30 mm tray with 104 kW installed. A 40 foot container gives about 12 m of internal length, 2.35 m of width and 2.39 m of height, so neither machine travels assembled and the large one needs far more modules, a heavier crane and a bigger foundation.

Power is the second multiplier. A 104 kW installed load on the QST1800 against 34.4 kW on the QST6-15 is not a cable change, it is a transformer decision, and a new transformer is a utility lead time rather than a purchase. That is where a plant loses three weeks before a single bolt is tightened.

What has to be ready before the crew arrives?

Four items, and they are checked on the first morning. If any is missing the crew waits, and waiting days are the most expensive days in the project because the flights and the hotel are already paid.

  • Foundation poured to the latest general arrangement drawing, cured, with anchors set and the base area clean and level.
  • Power at the confirmed voltage and frequency, with the panel, the earth and the phase rotation checked before the first start.
  • Lifting capacity for the heaviest module, plus a clear path from the unloading point to the foundation.
  • Pallets, water and compressed air at the marked points. Pallets are the item ordered last and needed first: the machine cannot make a single block without them.

What delays a block line most often?

In our experience the machine is rarely the delay. The transformer, the crane booking and the pallet order are. A customs hold on the container that carries the electrical panel adds days that no erection plan can recover, and a mould that is approved late means the first trial block waits for steel instead of for concrete.

The fix is a dated list rather than a promise. One page with the foundation date, the power date, the crane date, the pallet delivery date and the crew arrival date, signed by both sides, prevents most of the arguments that follow a late start.

When is the line considered finished?

Not on the day the crew leaves. The line is finished when a measured run holds its cycle, the block dimensions are inside tolerance, and the seven day and 28 day breaks confirm the mix. On a QST6-15 the acceptance run is judged at a 15 to 23 second cycle and 8,640 to 11,520 hollow blocks in an eight hour shift, and the number is written in the handover record with the mould set, the tray size and the mix batch beside it.

Two recheck dates go into the same record. The seven day break tells you whether the mix is right, and the 28 day break tells you whether it is stable. A supplier who will not put those dates in writing is leaving the last month of the schedule to chance.

Frequently asked questions

How long does installation take for a block making line?

Three to five weeks from site handover to the first saleable block. The erection crew's own work is about seven working days: alignment, hydraulics, vibration settings, the first mould, training and the acceptance run. The rest of the calendar is foundation cure, power connection, container unloading and the 28 day strength review, and those belong to the buyer's site rather than to the machine.

Does the foundation have to be poured before the machine arrives?

It should be, and it needs seven days of cure after pouring before the base frame is set. A foundation poured when the container leaves the factory will usually be ready within a week of arrival, which is the tightest sequence that still works. Pouring after the machine is on site adds the full cure period to the schedule and leaves the crate open on the ground.

How much power does the site need for a block line?

Start from the installed capacity of the host and add the mixer, the conveyor, the stacker and the compressor. The QST6-15 is listed at 34.4 kW with a 3.0 kW stacker, the QST1200 at 57.6 kW and the QST1800 at 104 kW with a 3.7 kW stacker. A QST6-15 line in practice wants about 30 kW of usable supply, and the starting current of the vibration motors is what the transformer has to survive.

Can the line run while the building is still unfinished?

It can run, and it should not be handed over. Dust, rain and direct sun all change the green strength of a block before the seven day break, and a roof over the press and the pallet line is cheaper than a batch of cracked blocks. Keep the machine area covered, keep water off the foundation and leave the curing area open to air before you call the acceptance run.

Who supplies the crane and the concrete?

The buyer supplies the crane, the concrete, the power connection and the pallets, because all four are local works that a supplier cannot price from another country. The supplier supplies the machine, the lifting plan, the erection crew, the alignment instruments and the acceptance record. Put that split in the contract line by line, since the most common dispute after a late start is a crane that neither side ordered.

Price guides
Machines that fit this

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us