Mould Changeover: The Order of Work and the First Block

19 November 2026 · 6 min read

Quick answer

A mould changeover on a block machine means taking off one complete mould set, the frame, cores, base plate, guiding assembly and positioning mechanism, and fitting another set cut for the same pallet. The work is short in steps and long in checks: isolate and lock the supply, release hydraulic pressure, lift on the lifting points, clean the seating faces to bare metal, seat the new set, torque in the drawing order, then run one pallet at reduced speed and measure the blocks before the counter starts. In a plant that sells two products, the changeover, not the cycle time, sets the weekly output.

Get a price on WhatsApp Or send a written enquiry

What exactly comes off the machine?

A block machine mould is not a plate. It is a matched set of five machined parts: the frame that bolts to the machine, the cores that form the voids, the base plate that sets the bottom face, the guiding assembly that keeps the punch square, and the positioning mechanism that puts the set back in the same place every cycle. The set is cut from wear-resistant alloy steel, machined on CNC to micron level and heat treated, which is why a change is an operation on a precision assembly and not a swap of a consumable.

That is why a second mould is ordered against three identifiers rather than a product name: the machine model, the pallet dimensions, and the revision number stamped on the frame. A set cut for a 1,350 by 880 by 25 mm pallet will not seat on a machine built around 1,400 by 1,400 by 30 mm. The pallets alone separate the models: 980 by 680 mm on the QST6-15, 980 by 860 mm on the QST8-15, 1,100 by 880 mm on the QST1000, 1,350 by 880 mm on the QST1200, 1,350 by 1,150 mm on the QST1500 and 1,400 by 1,400 mm on the QST1800. The QST1500 board carries 30.7 percent more area than the QST1200 board, and the QST1800 board 65 percent more.

In what order is the work done?

The sequence below avoids the two failures that cost the most: a set dropped on its guide pins, and a set seated on grit. It assumes the machine is stopped, the panel is locked out and the hydraulic circuit reads zero.

  • Isolate and verify. Lock the main breaker, keep the key with you, and confirm the pump cannot start. The rest of the work is done with hands inside the mould area.
  • Release pressure and lower the table. Let the gauge fall to zero, whether the machine holds 31.5 MPa as the QST8-15 does or 25 MPa as the QST6-15 does, and bring the table to its lowest position so the set travels the shortest distance.
  • Disconnect what ties the set to the machine: fasteners, the hydraulic couplings on the core puller where one is fitted, and the position sensor bracket. Bag and label the fasteners by position, because they belong to the set.
  • Lift on the lifting points only. Use the eyes provided and four legs, with a spreader where the hook is single. A sling passed through the cavities bends a core, and a bent core is a new set, not a repair.
  • Clean the four seating faces to bare metal. This is the step that decides the next thousand blocks. Cured mix and old film become a step of a few tenths of a millimetre, and that step prints on every block the set will make.
  • Seat the new set and torque in the drawing order. Bring the fasteners down evenly in a cross pattern rather than taking one to full torque and letting the rest follow.
  • Run one pallet at reduced speed, then measure before counting. The first pallet is a test piece, not production.

Why do the seating faces matter more than the bolts?

A set that sits a few tenths of a millimetre off its seat on one corner does not produce reject blocks at once. It produces blocks that are thinner at one end, pass a casual glance, and fail a buyer's caliper three weeks later, when the pack is already on a truck. Because the base plate is machined to micron level, the grit under it is coarser than the tolerance it is sitting on.

The same logic applies to the guiding assembly and the positioning mechanism. A worn guide bush lets the punch travel off square, and the symptom is a wall thickness that varies from one side of the block to the other. Read the block rather than the machine: a hollow block that breaks with one thin wall and three thick ones is telling you the set is out of position, not that the mix is wrong.

What changes when only the product changes?

Most plants change products inside one pallet size and one machine, and then the changeover is a straight swap of a set cut for the new shape. The pallet stays, the machine stays, and only the cavity count and the cycle belong to the new product.

ModelPalletCycleInstalled power
QST6-15980 x 680 x 20 mm15 to 23 s34.4 kW
QST8-15980 x 860 x 22 mm15 to 23 s44.9 kW
QST10001,100 x 880 x 25 mm15 to 23 s48.9 kW
QST12001,350 x 880 x 25 mm15 to 25 s57.6 kW
QST15001,350 x 1,150 x 30 mm15 to 23 s69.1 kW
QST18001,400 x 1,400 x 30 mm15 to 25 s104 kW

How is the first block proven?

The counter is not evidence. Five readings are, and they are taken on the first pallet of the new set.

  • Dimensions on three blocks from that pallet: length, width and height, measured with a caliper rather than a tape.
  • Wall thickness on the same three blocks, on all four sides, because the variation between sides is what exposes a set that is not square.
  • The arris and the bottom face. A rounded edge or a rough face points at the base plate and the cores, not at the mix.
  • Cavity count against the drawing, counted on the set itself. Do not divide pallet area by block area, because that is an estimate, not a count.
  • Ten cycles under load against the contract. A QST1200 runs 15 to 25 s and a QST1800 15 to 25 s, and the loaded figure on your mix is the one that counts.

What does it cost, and what do you send for a second mould?

Treat the change as a block of hours in the shift plan rather than a task between two orders. Send five items: the machine model, the pallet size measured with a tape rather than read from a brochure, the product drawing with dimensions and wall thickness, the cavity count you want to run, and a photograph of the revision stamp on the current frame.

Frequently asked questions

How long does a mould changeover take?

Time your own first change and use that figure, because the answer depends on the lifting method and the number of fasteners. A set lifted on its eyes with four legs, with fasteners bagged by position, comes off in a fraction of the time of a set slung through the cavities. The cleaning of the seating faces is the part that cannot be shortened without printing the result on every block the set makes.

Can the mould be changed without a crane?

Not on the automatic models. The set is a machined steel assembly and the machine has lifting points for it. A forklift with a jib can substitute where headroom allows, but a sling through the cavities bends cores, and a bent core changes wall thickness on every block that follows.

Does a new mould need a new pallet fleet?

Only if the machine model or the pallet size changes. Inside one pallet size, a new set is cut for the same boards and the existing fleet keeps working. This is why the pallet size is the first question in a mould order and the last thing a buyer should change late in a project.

Price guides
Machines that fit this
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us