Block Machine Sample Blocks Test: Cost and Acceptance

21 November 2026 · 6 min read

Quick answer

A sample batch is the first run after installation: blocks pressed from the agreed mix on the agreed mould, cured, measured and crushed. Its cost sits in four lines, the cement and aggregate consumed, the machine hours diverted from planned output, a mould if the profile is new, and the crushing tests at 7 and 28 days. A QST6-15 presses 6 hollow blocks of 390 x 190 x 190 mm per mould, so a defensible batch fits in a few moulds, and criteria signed before pressing decide acceptance.

Get a price on WhatsApp Or send a written enquiry

A sample batch is the first production run after installation, and the block machine sample blocks test is where a buyer stops inspecting a machine and starts judging a product. A fixed quantity of blocks is pressed from the agreed mix on the agreed mould, cured, then measured and crushed. The QST6-15 presses 6 hollow blocks of 390 x 190 x 190 mm per mould, so 28 moulds give 168 blocks: enough to test at two ages, few enough to write off. Every later argument about dimensions, corners or strength is settled by what this batch proved.

What is a sample batch, and what does it settle?

The batch is defined before it is pressed: a quantity, a mix version, a mould, a pallet type and a place to cure. It is not a handful of blocks lifted off the stack at the end of a shift, because those blocks carry no record of the settings that made them. A sample batch is pressed as one continuous run, with the machine settings written down as they are dialled in, and the blocks stay together from the press to the curing rack and from the rack to the laboratory.

Three things are settled at once. The machine has to hold the profile on the mould drawing through a full cycle, at 15 to 23 seconds on a QST6-15 or 20 to 25 seconds on a QS600 static press. The mix has to suit this machine's vibration and pressure rather than a recipe that worked on another press. And the operator has to show that a whole shift can repeat what the first pallet proved. That is a different checkpoint from the factory acceptance test, which proves the machine before shipment: the batch here proves the product in your own yard, against your drawings and your contract.

What does a sample batch cost?

The batch is small, but it is not free, and its cost sits in a short list a buyer can write before the first pallet is pressed. Power runs through the same account: a QST6-15 carries 34.4 kW installed, metered at a tariff you confirm on site. Output is the line most often forgotten: a machine rated at 8,640 to 11,520 hollow blocks in an 8 hour shift gives up a countable quantity for every hour the sample holds the press.

  • Cement and aggregate consumed, since the material leaves either as product or as scrap.
  • Machine time and pallets against planned output: a shift on samples is a shift not producing saleable blocks, and a loaded 980 x 680 x 20 mm pallet is out of circulation while the batch cures.
  • A mould or a mould modification when the profile is new. It is the largest line and the only one that keeps its value, because the mould stays in production.
  • Two crushing tests, one at 7 days and one at 28 days, each with its own specimen set and laboratory submission.

How do you keep the sample batch small?

Press the batch during the commissioning run. The machine has to cycle anyway while the anchor bolts are checked, the panel is proven and the operator learns the sequence, and those first pallets may as well be the sample. Do that, and the machine time line falls close to nothing, so the batch costs little more than its material.

Keep the quantity at what the tests need. Two ages, a few specimens for each, plus one retained set for the file: that fits inside a handful of moulds. Anything past it is production wearing the label of proof. A QST6-15 throwing 32 to 36 standard bricks of 240 x 115 x 51 mm per mould reaches laboratory quantity in a very short run.

  • Use the mould shipped with the machine for the first batch, and save a new profile for the second.
  • Record the settings on the first pallet and hold them for the batch, so a failure traces to a change, not a guess.
  • Book the laboratory before pressing, so the 7 day specimen is not waiting in the yard for a slot.
  • Keep rejected blocks on a marked pallet instead of re-pressing them: the failed set is the evidence for the retest.

What is measured on the blocks?

Five checks, in order, because the first four run in the yard and the fifth cannot.

Dimensions are read against the mould drawing, not against a block from another plant. The pallet is the reference surface the block cures on: a 980 x 680 x 20 mm pallet that is bowed or worn shows as a height scatter across the batch before it shows in a drawing check, so measure on a pallet you know is flat.

Mass per block catches what the eye misses. Weigh the whole set, since a wide scatter inside one batch points to an uneven feed or a mix losing water, and both grow as the shift goes on. Face and corner quality are judged as the block leaves the pallet: a torn corner then is a green strength or stripping problem, a torn corner after curing is handling.

The crushing test is the one result that cannot be argued with, which is why the batch is aged twice. Seven days shows whether the mix and the curing are on track while there is still time to correct them, and 28 days is the number acceptance is written against. A QS600 static press gives 16 pieces of 200 x 100 x 60 mm per mould at 20 to 25 seconds, and on a paving brick the face and the arris carry most of the decision, so the visual standard is photographed, not described.

CheckMeasured againstWhen
DimensionsThe mould drawing, all three axes and the wall thicknessAfter curing
Mass per blockThe batch mean and the spread inside the batchSame day
Face qualityNo cracks, no honeycomb, no drag marks from the feed boxAs stripped
Corner integritySquare corners after pallet transfer and after curingAs stripped and after curing
Compressive strengthThe crushing test on the cured specimen setAt 7 days and at 28 days

Which acceptance criteria must be written before pressing?

Every criterion that will be used to reject the batch has to exist in writing before the first mould is filled. Written afterwards, it turns into an opinion, and the two sides will each hold a different one about the same chipped corner. Put the criteria in an annex to the order and sign it before the commissioning run, not on the morning the result arrives. A criterion agreed in advance is a quality gate. The same sentence agreed afterwards is a renegotiation, and the side holding the blocks is in the weaker seat.

  • Dimension limits and tolerance, axis by axis, with the mould drawing revision quoted.
  • The minimum compressive strength at 28 days, and the age used for the early check.
  • The laboratory, the specimen size and the test method, named rather than implied.
  • The visual standard, ideally with a photograph of an accepted face and a rejected one.
  • The failure path: one retest on a second batch from the same mix, a mix change, or rejection of the machine.

How does an accepted batch become the reference?

An accepted batch is worth more than its blocks. Keep a sealed retained set, photograph the accepted faces and corners, and write one report carrying the machine settings, the mix version, the mould serial and the curing dates, signed by both sides. That file is what the next dispute is measured against, and it answers a contractor faster than any argument about the machine.

It also sets the baseline: operators train against it, a second mould is proven against it, and a change of cement or aggregate source is judged by pressing a small batch against the retained set, not discovered on a customer's wall.

Frequently asked questions

How many blocks should a sample batch contain?

Enough for two test ages, a few specimens for each, plus a retained set that stays sealed in the file. That usually means a handful of moulds, not a shift. On a QST6-15, 6 hollow blocks of 390 x 190 x 190 mm come off each mould, so eight moulds give 48 blocks and cover the laboratory with spares for a damaged specimen.

Does the sample batch replace the factory acceptance test?

No. The factory test proves the machine before shipment, on the supplier's floor, with the supplier's mix and power. The sample batch proves the product after installation, on your aggregate, your cement, your water and your curing. A machine can pass the first and still fail the second, which is exactly why both checkpoints exist and why the criteria differ.

What happens if the 7 day strength comes back low?

Check the setting record before touching the mix. A low early result usually traces to moisture in the aggregate, a shortened curing period or a cycle that ran short, and each of those is visible in the log from the batch. Correct the cause, press a small confirmation batch, and let the 28 day specimen decide unless the written criteria say the early result already fails.

Can rejected sample blocks be sold?

A block that failed on dimensions or on face quality may still sell as a second, if the buyer of that block knows what he is buying. A block that failed on strength should stay off the market until the cause is known, because the same mix is still in the mixer. Decide the rule in the acceptance annex rather than in the yard on the day.

Which side pays for the crushing test?

Most buyers pay their own laboratory for the first test, because they want a result they control. What must be agreed in writing is the second test, the one after a failure, and who carries it if the retest also fails. Naming that in the annex costs nothing at signature and removes the worst argument in the whole acceptance process.

Price guides
Machines that fit this
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us