Buying guide

Block Machine Third Party Inspection: What to Book

19 November 2026 · 6 min read

Quick answer

A block machine third party inspection is a paid visual and functional check carried out at the supplier works before the container is loaded, run against a checklist the buyer writes. The inspector confirms the nameplate model, pallet dimensions, installed power, mould cavity count and hydraulic hold pressure against the contract, then times a real cycle. It proves the machine is the one on the order. It does not test your foundation, your power connection or your raw materials.

Get a price on WhatsApp Or send a written enquiry

What single question does the inspection answer?

A block machine third party inspection settles one dispute before it starts: is the machine in the works the machine described on the order? Every photograph, gauge reading and signed page it produces is evidence for that one point. Buyers book it because the balance falls due against a machine most have seen only in photographs of another machine, and because the distance between a factory in China and a site in Iraq is measured in weeks at sea.

It is not a warranty, and not a second opinion on the design. The inspector will not tell you whether a QST1200 at 57.6 kW fits your shift target, or that your pallet fleet is too small; those are commercial judgements made before the order. What the inspector does is narrow: measure the delivered object against the document you signed, and hand you pages you can put in front of a supplier who disagrees.

Where does it happen, and when?

The inspection happens at the supplier works, on the assembled machine, after it is wired and run for its own factory test, and before it is crated and loaded. That window carries the whole value of the exercise. Booked earlier, the inspector photographs a frame with no hydraulic station on it. Booked later, the machine sits inside a container and the only thing left to inspect is a packing list.

The buyer appoints the inspection body, pays it, and instructs it in writing. An inspection body of the buyer's choice beats a familiar name, because the instruction sheet is where the work is defined: which model, which serial number, which pallet size, which mould revision, and which numbers count as a pass. Send the contract, the mould drawing and the packing list with the appointment.

What does the inspector actually check against the contract?

The nine lines below separate a real inspection from a walk around the machine with a phone camera. Each has a figure on the order or on a drawing, and each can be read off the machine itself: 31.5 MPa on the hydraulic gauge, 44.9 kW on a QST8-15 plate, 980 × 860 × 22 mm on the pallet.

  • Nameplate and model. A QST8-15 plate reads 14 t, 9800 × 3600 × 2800 mm and a 980 × 860 × 22 mm pallet. A plate that disagrees with the order is a stop, not a note.
  • Pallet size, measured with a tape rather than read from a brochure. A QST1200 runs 1,350 × 880 × 25 mm and a QST1800 1,400 × 1,400 × 30 mm, so the pallet names the model as firmly as the serial does.
  • Installed power, summed from the motor plates. A QST8-15 is 44.9 kW, a QST1200 57.6 kW, a QST1800 104 kW. The total shows whether the machine holds its cycle on a wet mix or is run below it.
  • Mould cavity count against the drawing. Count the cavities in the mould bolted to the machine and read the revision number stamped on its frame. Do not divide pallet area by block area; that is not a cavity count.
  • Hydraulic hold pressure. Rated pressure is 31.5 MPa on the QST range and on most static presses, including the QS1000 with its 600 mm bore. Watch the gauge through the hold, record any drop and its duration, and photograph the gauge.
  • Vibration force, read from the settings and confirmed during the run: 95 kN on a QST8-15, 150 kN on a QST1200, 280 kN on a QST1800.
  • Cycle time, no-load and loaded. Time ten cycles and compare the average with the contract, which reads 15 to 23 seconds on a QST8-15 and 15 to 25 seconds on a QST1200. The loaded figure on your mix decides everything.
  • Random spares against the packing list. Count the crates, open them, match part numbers and quantities line by line. A wear plate missing in the works is a parcel; missing on site it is a stopped line.
  • Serial numbers photographed and archived: frame, motor, hydraulic pump, PLC and mould frame, for the spare parts desk a year later.

Which pages must the report contain?

A report that arrives as a cover page and a paragraph of praise has no use. Name the pages in the appointment letter. The report is what you send to the supplier when something fails, and what you file when nothing does.

  • Identification page: contract number, model, serial number, works address, date and inspector name.
  • Scope page: what was inspected, what was not, and the buyer's checklist quoted line by line.
  • Measurement page: pallet dimensions, cavity count with the drawing revision, installed power as summed, each with the instrument used.
  • Hydraulic page: the hold reading against the 31.5 MPa rating, hold duration, any drop, and a gauge photograph.
  • Test run page: cycle timings with and without load, cycles timed, product photographs, and the mix used.
  • Packing page: crate count and contents against the packing list, random spares counted and photographed.
  • Conclusion page: pass, pass with numbered observations, or hold, signed and dated, each observation tied to the checklist line that failed.

What the inspection cannot cover

Four things sit outside the works gate, and no inspection body can report on them from there. The foundation is one: the inspector sees a machine on a factory floor, not on your slab, and anchor layout, slab thickness and concrete curing are site questions. The power connection is another: cable, transformer and protection at your end are not part of the machine, and a machine that ran clean in the works can still trip on your supply.

Installation and commissioning is the third. A pass at the works says the machine was assembled correctly once, by the people who build it, and says nothing about the crew that reassembles it after a sea voyage. Raw material adaptation is the fourth: your aggregate gradation, cement and moisture were not in the test, so a machine that held 15 to 23 seconds on the factory mix may not hold it on yours until the mix is adjusted.

Why does your own checklist decide the result?

Here is the part an order rarely states. The inspector measures against the checklist you give it and nothing else. Send a sheet that says only that the machine must match the contract, and the inspector confirms that the machine matches a contract which may say nothing about cavity count, mould revision or pallet thickness. The report comes back clean, you pay the balance, and what you bought is a clean report.

So the checklist is your document, written out of the order: model and serial, the three overall dimensions, pallet size and thickness, installed power, vibration force, rated pressure, cavity count with the drawing revision, cycle seconds, spares by part number, packing list. Read the mould drawing yourself. If it shows a layout you cannot sell into your market, a perfect inspection confirms the wrong mould perfectly.

Book three things at once: the checklist, the report pages, and a hold point in the payment that releases the balance against the report rather than a loading photograph. The machines span 14 t on a QST8-15 to 34 t on a QST1800, so freight on a mistake is not small. A report is only as sharp as the sheet the inspector holds.

Frequently asked questions

When should a block machine third party inspection be booked?

At the factory test run, after the machine is assembled and wired and before it is crated. That is the only point where the machine can be measured and also run under load. Booked before assembly the inspector sees components, booked after packing the inspector sees closed crates, and neither produces a cycle time you can set against the contract.

What does the inspector check on a block machine?

Nameplate model and serial number, pallet dimensions and thickness, installed power summed from the motor plates, mould cavity count against the drawing revision, hydraulic hold pressure against the rated 31.5 MPa, vibration force, loaded and no-load cycle seconds, random spares against the packing list, and photographs of every serial number on the machine.

Does a third party inspection replace my own acceptance test?

No. The inspector measures against the checklist you provide, so an incomplete checklist produces an incomplete pass. The buyer still has to read the mould drawing, fix the product dimensions, and decide which cycle time and pallet size the order requires. Do that reading before the appointment, because the report can only be as strict as the sheet behind it.

Can an inspection confirm the machine will work on my raw materials?

Not fully. The loaded run uses the mix available at the works, not your aggregate, cement and moisture. A machine that holds its cycle on the factory mix can still run slower on yours until the mix is adjusted and the vibration settings are tuned to it. Treat the works test as a mechanical check and plan a trial mix during commissioning.

Which documents should go to the inspection body?

The signed contract or proforma, the mould drawing with its revision number, the pallet drawing, the packing list and the spare parts list by part number. Add your own checklist with the pass figure written against each line. A body that receives only a model name will confirm a model name, which is the cheapest and least useful report on offer.

Price guides
Machines that fit this
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us