Block factory equipment for Dubai projects

25 October 2026 · 6 min read

Quick answer

Block factory equipment for Dubai projects is sized in three steps. Fix the product list and the weekly delivery first, then convert that into shift output against a host of 90,000, 120,960 or 220,000 bricks per 8 hour shift. Add cubing, wrapping and clamp handling last, and fit the line to the shed, yard and power you already have.

Get a price on WhatsApp Or send a written enquiry

Block factory equipment for Dubai projects is scheduled backwards from the handover date, not forwards from the machine price. A project order fixes the product, the tolerance the contractor will measure and the week the first lorry leaves the gate. The equipment list follows from those three, and it is why two buyers with the same budget finish with two different machine lists.

A yard that sells from stock loads a mixed lorry and waits for the next order. A plant feeding a project cannot work that way. The blocks go to one site, in one specification, on one programme, and the pack is opened in front of the contractor. A plant sized around the press alone will not hold that rhythm.

What changes when a plant sells to projects instead of yards?

The product set stops moving. A retail yard keeps five or six moulds and swaps them when a customer asks for a different block. A project plant may run two profiles for a season, and that changes the mould argument. You can justify a spare set, because the cycle count on the working set is predictable and the mould becomes a consumable with a known replacement week.

Tolerance moves to the pallet. The press sets density, but the board under it decides whether the corner survives the lorry. A 20 mm pallet that has lost its edge shows up as a chipped corner on site three weeks later. Pallet discipline belongs in the schedule, and it starts with a feeder that presents boards squarely.

The delivery rhythm pushes cubing and packing up the list. A site lifts packs with a crane or a clamp, and a feeder handing over a board about every 13 seconds sets the floor under that rhythm. The product has to leave the plant cubed, square and wrapped, so the cuber and the wrapper become the units that decide how many lorries the yard turns in a day.

The core line, and the options that set the schedule

Read this list as a schedule, not a catalogue. Each line either sets the daily output, sets the number of pallets in circulation, or sets the pack that leaves the gate. A host rated at 220,000 bricks per 8 hour shift with a cuber that cannot keep up is a yard full of stacks.

  • Host machine: QST8-15 up to 90,000 standard bricks per 8 hour shift, QST1200 up to 120,960, QST1800 up to 220,000. Derate the figure for mould changes before you set it against the delivery schedule.
  • Mixing and batching: the planetary mixer holds colour and surface consistency, and the batching machine doses aggregate to the stored ratio, which sets the floor under the press cycle.
  • Pallet feeder QS-1200: 3 kW, about 13 seconds per delivery cycle, a bin holding three stacks. It removes one operator per shift and the human pause that breaks the rhythm.
  • Cuber systems: QS-1200A stacks 1,000 to 1,200 mm squares up to 12 layers of solid brick, QS-1000G-B runs about 16 seconds per layer at roughly 2,000 pallets per shift, and the double-station QS-1000G-C runs about 13 seconds at roughly 3,800 pallets.
  • Pallet-free option: QSMT1000 forms and cubes the wet block online, up to 135,000 bricks of 240 x 115 x 50 mm per 8 hour shift, with no pallet fleet.
  • Press family for pavers and kerbstones: 31.5 MPa working pressure, an 18 to 22 seconds cycle and a moulding area up to 1,440 x 850 mm for large-format pavers, kerbstones and curbstones.
  • Packing and handling: a cantilever wrapper with top film closes five sides of the pack, and a forklift clamp lifts 500 to 800 standard bricks or 40 hollow blocks per bite, up to 10 layers, onto the lorry.

Does the product mix decide one machine or two?

Count the profiles first, then the tonnage. Hollow blocks, solid blocks, interlocking pavers, kerbstones and curbstones do not share one cycle. A kerbstone uses the 1,440 x 850 mm moulding area at 31.5 MPa and runs slow, a 240 x 115 x 50 mm solid brick is light and fast, and on one host the fast product pays for the slow one every hour.

Mould count follows the changeover budget. Each profile needs its own matched set, and a set standing on the rack still has to be stored and protected. Four profiles in one week with a planned changeover window on one host is cheaper than two hosts standing half idle. A second machine earns its place on volume, not on variety.

The site constraints to design around

Four constraints fix the layout before a model number is chosen. The shed has to hold the host, the pallet magazine, the cuber and the wrapper in one line, with room for a forklift to turn at the discharge end. Most buyers measure the host and forget the wrapper, which needs clear space on two sides.

The yard and curing area come next. Blocks need days under cover before they are cubed, and the number of stacks standing at once is daily output multiplied by curing days. A yard sized for the machine and not for the curing time is the commonest reason a plant cannot ship on the day it promised.

Power and water are last and usually underestimated. Add the installed capacity of host, stacker, cuber, wrapper and compressor, not the press alone, and read what the panel actually delivers. Water volume and pressure at the mixer, plus silo position, decide whether batching sits inside the shed or beside it. The site plan has to arrive before the list is frozen.

How the auxiliary equipment ships, and what travels crated

The host travels as a heavy frame, usually split into frame, hopper and hydraulic unit, and it loads by crane at both ends. The cuber and the wrapper travel partly dismantled, because their working height exceeds a transport frame. Ask for the transport dimensions and lifting points before you book the lorry that meets the container.

Two items travel crated on their own, and each is a claim waiting to happen. The mould set goes in its own crate with the cavity faces blocked, because a mould that takes a knock forms a chipped block for the rest of its life. The control cabinet goes sealed with the wiring labelled at both ends, because a cabinet that arrives damp costs a week of fault-finding. Belts, hoses and spare mould parts travel in one numbered case tied to the packing list.

Which details must reach us before the list is frozen?

Send six items and the list can be fixed in one round. Without them every figure in the quotation is a placeholder, and the revisions come out of the commissioning week.

  • Product list with drawings: every block, paver, kerbstone and curbstone you sell, with dimensions and face pattern, so the mould count settles.
  • Daily output per product in pieces, and the week each product is due on site.
  • Shift pattern: hours per shift, shifts per day, and the days per week the plant will really run.
  • Site plan at a stated scale, with shed outline, yard, curing area, gate and lorry turning circle.
  • Power and water: what the panel delivers, and the water volume and pressure at the mixer position.
  • Destination port, so transport frames, crate marks and lifting points match your discharge equipment.

Frequently asked questions

How do I turn a project delivery plan into a shift output figure?

Take the largest single product volume the project needs in one week and divide it by the delivery days you can run. That gives pieces per day. Divide again by the shifts you will staff to get pieces per shift, then compare against the host figure: 90,000 standard bricks per 8 hour shift on QST8-15, 120,960 on QST1200, 220,000 on QST1800. Choose the machine that covers the peak week, not the average week.

What is the difference between a pallet line and a pallet-free line?

A pallet line carries every wet block on a board through forming, curing and cubing, so the plant owns a pallet fleet, a return conveyor and a repair bench. A pallet-free line such as QSMT1000 stacks the wet block online as it leaves the mould, up to 135,000 bricks of 240 x 115 x 50 mm per 8 hour shift, and removes that fleet. The pallet-free route suits a narrow product range, not a mix of shapes.

How many moulds should a plant keep for a project order?

One matched set for every profile plus one spare for the profile that runs most hours. A project plant changes moulds rarely, so wear concentrates on one set and its replacement week is predictable. The spare keeps the line running while the worn set is re-cut. Four profiles with a planned changeover window on one host is cheaper than two hosts standing half idle.

Why do you need my site plan before quoting the equipment list?

Because the layout decides which units fit and in what order. The shed has to hold host, pallet magazine, cuber and wrapper in one line, the yard has to hold output multiplied by curing days, and the panel has to carry the installed capacity of all of them. Without the plan, sizes are guesses and the correction lands after the machines arrive.

How are the mould and the control cabinet shipped?

Both travel crated on their own, never loose with the frame. The mould crate blocks the cavity faces so no edge touches steel in transit, because a knocked mould forms chipped blocks for the rest of its life. The cabinet crate is sealed and the wiring is labelled at both ends, so a damp arrival is visible and a reconnect becomes a labelling job instead of a trace.

Price guides
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us