How Many Workers Does a Block Making Machine Need?

2 November 2026 · 7 min read

Quick answer

An automatic block making machine needs one operator at the panel, and the line around it needs five to seven people per shift. The machine is not what raises the number: at a 15 to 23 second cycle six hollow blocks come off every mould, so a QST6-15 produces 8,640 to 11,520 blocks in an eight hour shift, which is 1,440 to 1,920 pallets to feed, lift, rack and cube. Labour follows the pallets, not the press.

Get a price on WhatsApp Or send a written enquiry

How many workers does a block making machine need? One to run it, and four to six more to keep the line moving. The confusion comes from counting the machine instead of the material flow: a block plant is a pallet operation that happens to have a press in the middle, and the pallets are what people handle.

The arithmetic is blunt. A QST6-15 forms six hollow blocks of 390 x 190 x 190 mm per mould on a 980 x 680 x 20 mm tray, at a cycle of 15 to 23 seconds. In an eight hour shift that is 8,640 to 11,520 blocks, which means 1,440 to 1,920 pallets leaving the press, one every cycle. At the fast end of the cycle the machine releases a pallet every 15 seconds; nobody also mixes, inspects and racks at that rhythm alone.

Why the machine does not set the crew size

Automation moved the labour, it did not delete it. Thirty years ago a block plant was a moulding table, a hand cart and a curing yard, and the crew did everything. On a modern line the press, the stacker and the cuber took over the repeated movements, so the people who remain do the four jobs a sensor cannot: judge the mix, inspect the green block, drive the forklift and repair the machine.

That is why a plant with a QST1800 at 104 kW and a plant with a QST6-15 at 34.4 kW run almost the same crew. The large machine makes eight times the investment but not eight times the pallets per person, and the difference shows up in the shift plan rather than in the headcount.

Who has to be on the floor in each shift?

Five roles cover an automatic line, and each one has a stop condition attached to it. If a role is missing the line still runs, but it runs without the check that role exists to make.

  • Control operator at the panel: starts the cycle, watches pressure and mould filling, stops the line when a block sits crooked. One person, and the only one who can stop production in a second.
  • Mixer and batching: cement, sand, aggregate and water, plus the moisture check that keeps the block from crumbling at the corners.
  • Pallet and forklift: feeds empty pallets to the stacker, takes green pallets to the racks, brings cured pallets back for cubing. At 1,440 to 1,920 pallets a shift this is a full-time job, sometimes two.
  • Green block inspector: dimensions, void shape, corner integrity, and the sample that goes to the seven day break. Without this role the first bad batch is found by the customer.
  • Mechanical and electrical cover: hydraulic leaks, vibration motor mounts, sensors and the panel. On a small plant this is one person on call rather than one person idle.

How many pallets has the crew actually to move?

Read the last column as a labour figure. Every pallet is lifted, pushed, racked and later cubed, so the crew size tracks the pallet count far more closely than it tracks the kilowatts. That is also why a second shift is not a marginal decision: it duplicates the whole crew, not one person.

The practical threshold sits near 1,500 pallets a shift. Below it one forklift driver can feed the stacker, clear the racks and keep the aisle open. Above it the driver becomes the bottleneck, and a plant running 1,920 pallets on a 15 second cycle with one driver loses minutes at every change of direction, which is why the sixth person on the payroll is usually a second driver.

MachinePieces per mouldShift outputPallets per shift
QST6-156 hollow blocks, 390 x 190 x 190 mm8,640 to 11,5201,440 to 1,920
QST120063 standard bricks, 240 x 115 x 51 mmup to 120,9601,920
QST1800largest mould on a 1,400 x 1,400 mm trayup to 220,000set by the mould

How many workers for a compact or semi automatic line?

More, not fewer, and this surprises buyers. A QT4-15 at 22.9 kW and 6,200 kg on an 850 x 560 x 20 mm tray costs a fraction of a QST1800, but it ships without the automatic pallet feed and the cuber, so people replace machinery. Expect eight to twelve per shift, with most of the extra hands on pallet handling and cubing.

A static press line is the other extreme. The QS600 presses 16 pavers of 200 x 100 x 60 mm per mould on a 900 x 700 x 20 mm tray at a 20 to 25 second cycle, so the pallet count per shift is lower and four to five people can hold the line. The comparison that matters is cost per thousand blocks, not headcount on its own.

What changes the crew count fastest?

Four things, and only one of them is the machine. A cuber removes two people from the end of the line because it stacks cured blocks without hand labour. A finger car curing system removes the forklift driver from the rack aisle. A packing station for export adds two people back. And a product change to a bigger block reduces pieces per mould, which cuts pallets per shift and quietly cuts the crew requirement with it.

There is a floor to this. However automated the line, one person must stand at the panel and one must be able to open a hydraulic valve. A plant that plans for one operator and no cover is one failed sensor away from a stopped shift.

How should labour cost enter the choice of machine?

Convert the crew into a cost per thousand blocks before comparing two quotations. A five person line and a ten person line differ by five wages, and that gap has to be paid back by the extra output of the larger machine. On a QST6-15 at 11,520 hollow blocks a shift, five wages spread over 11.5 thousand blocks is a small number; on a compact line running 3,000 blocks a shift with ten people it is several times larger.

Training is the cheapest line in that comparison. Operators who understand the mould, the mix and the cycle keep output near the published figure, and output that falls twenty percent costs more per month than the training week costs once.

Frequently asked questions

How many workers does a block making machine need?

One operator at the panel and five to seven people per shift for the line around it. The machine itself needs a single trained operator, but the pallets have to be fed, lifted, racked and cubed, the mix has to be batched, the green blocks have to be inspected and someone has to be able to repair a leak. On compact lines without automatic pallet handling the number rises to eight or twelve.

Can one person run an automatic block machine alone?

For a short run yes, for a shift no. At a 15 to 23 second cycle the press releases a pallet every cycle, so one person at the panel cannot also change pallets, inspect corners and keep the mixer fed. A single operator is realistic on a static press line pressing 16 pavers every 20 to 25 seconds, and still needs cover for the forklift and for maintenance.

Does a bigger machine need more workers?

Slightly, not proportionally. A QST1800 at 104 kW produces up to 220,000 standard bricks a shift against 8,640 to 11,520 hollow blocks on a QST6-15, but both keep one operator at the panel. The extra people go to pallet volume, curing racks and cubing, so the crew grows by one or two rather than by a factor of ten. The shift plan changes more than the headcount.

How many workers are needed for two shifts?

Double the crew, not the machine. Two shifts of a five to seven person line means ten to fourteen people, usually with one maintenance technician shared across both and a supervisor on each shift. The machine runs the second shift without extra capital, which is why plants move to two shifts before they buy a second press, and why the wage bill is the number to check first.

Can the crew be reduced after the plant is running?

Yes, by removing handling steps rather than by removing checks. A cuber and a finger car curing system take two or three people off pallet work, and a well trained operator can run the panel and the mixer in sequence on a slow product. Removing the inspector is where plants save a wage and lose a batch, since the first sign of a mix change shows in the green block.

Price guides
Machines that fit this

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us