Turnkey Block Making Plant: Scope, Cost Lines, Handover
18 November 2026 · 8 min read
Quick answer
A turnkey block making plant covers seven units and the conveyors between them, and it stops at the buyer's boundary: the foundation, the transformer, the pallet fleet, the crew accommodation and the spare parts stock stay outside. Two plants quoted on the same QST1800 at 34 t and 104 kW can differ by more than the machine, because one contract names the terminal points and the other leaves them to the site.
What does a turnkey block making plant contain?
A turnkey block making plant is a scope list before it is a price. Seven units do the work: the block machine, the batching machine that weighs the aggregate, the mixer that feeds it, the pallet feeding machine, the curing line or rack system, the cuber, and the packing station. Take one out and the plant still runs, slower, with a man doing the missing step by hand. That is the test we apply to every scope sheet. A quotation that lists a QST1800 at 34 t and 104 kW and stops there is a machine offer, not a plant.
The chain sets the pace, and the slowest unit sets the output of the whole line. A QST1800 moulds a pallet in 15 to 25 seconds, the QS-1200 pallet feeder refills the magazine in about 13 seconds, and a QS-1200A cuber takes 15 to 18 seconds per layer. When one of those three numbers is out of step with the other two, the plant runs at the speed of the weakest link and nobody notices it before the third shift.
Batching and mixing are where a cheap scope hides. A PL series batching machine with three-point weighing and fast plus slow dosing, feeding a planetary mixer, holds a mix ratio through a wet aggregate day. A volumetric feed with a hand valve does not. The difference never appears on the machine list, which is why the machine list is the wrong document to compare.
Who owns each interface between the units?
An interface is any point where one party's work ends and the other's begins. Turnkey contracts fail at those points far more often than at the machines, because both sides read the same word and mean different work. Write the boundary on one sheet, in the units the contractor will measure: the anchor bolts and the grout, the cable from the panel to the machine terminal box, the water line to the mixer inlet, the cement silo outlet flange, the air at the filter regulator.
Our position is simple. We own everything from the machine terminal box inward, and we own the interface drawings that tell the other trades where to stop. We do not own the slab the machine stands on, the transformer that feeds the panel, or the pallet fleet the line circulates. Those sit with the buyer, and a contract that blurs them is a contract that will be argued about on site.
| Interface | Where the boundary sits | Who carries it by default |
|---|---|---|
| Foundation and anchor bolts | Concrete, grout and levelling to the drawing revision we supply; template positions and bolt size come from us | Buyer's civil contractor |
| Power to the line panel | Cable, breaker and meter up to the panel terminals; internal wiring and the PLC from the panel inward | Buyer, up to the panel |
| Transformer and incoming supply | The supply itself and its sizing, at the voltage you confirm in writing | Buyer |
| Water and cement silo | Water line to the mixer inlet valve, the silo, the screw conveyor and the cement supply | Buyer |
| Pallet fleet | Pallets in the size the mould is cut for, plus the spare ratio you choose | Buyer |
| Yard and curing space | Hardstanding for cured stacks, forklift lanes, and a curing bay sized to the pallet count | Buyer |
| Installation crew | Travel, visa, accommodation and food for the erection team | Buyer |
| Spare parts stock | First fill of wear parts and a second mould set, on a list agreed with us | Buyer |
Which cost lines sit inside the turnkey number?
Inside: the seven units, the conveyors and transfer cars between them, the line control panel with its PLC program, one mould set in the size you specify, the general arrangement and foundation drawings at the manufactured revision, commissioning on your mix, operator training, and sea packing.
Outside: civil works, the transformer and the incoming supply, the pallet fleet, accommodation for the erection crew, the spare parts stock, inland transport and clearance at destination. Each of those is a real line in your budget and each is large enough to change the decision. A pallet fleet for a line that moulds on 1,400 × 1,400 × 30 mm pallets is not a rounding item. It is a second purchase with its own lead time, and it has to be ordered before the machine arrives or the cuber has nothing to stack.
The honest way to read two offers is to align them on the same boundary before comparing totals. One number may carry the transfer cars and the line panel, another may price the host machine and leave every conveyor to the site. Both totals can be correct and the cheaper one can still cost more, because the missing conveyors are bought later at single-unit prices with a second freight bill attached. Ask for the exclusion list in writing, in the same units as the inclusion list.
The pallet fleet is the line's real capacity limit
A block machine's cycle time is a promise about one pallet, not about a shift. The pallet count in circulation decides what the plant ships, and it is the figure buyers most often get wrong. Choose the cure hours yourself: at 20 seconds per pallet and 12 hours of curing, the arithmetic gives 2,160 pallets in the system before a single spare. Fewer pallets and the press waits for an empty one. More pallets and money stands in the yard doing nothing.
The cuber sets the figure downstream. A QS-1200A takes 15 to 18 seconds per layer and reaches about 3,800 pallets per shift with one operator, lifting 18 standard hollow blocks or 125 standard solid bricks per layer into a 1,000 to 1,200 mm square stack. If the press runs faster than the cuber can clear, the surplus stands in the curing bay and the pallet fleet grows to cover the queue.
What the handover sheet must state
Handover is a document event, not a handshake. The sheet is signed at the end of commissioning and it is the only thing that settles a dispute a year later, when the crew has changed and nobody remembers what was promised on the phone. Sign it with the plant running, not with the plant complete on paper: a line that only reaches part of its stated cycle on the day is a line that will be argued about at full cycle.
- Every unit by model and serial number, against the layout revision that was built, not the one in the offer.
- Cycle time and pallets per shift demonstrated on your mix, your pallet and your product, with the pallet count in the curing bay written next to the figure.
- The interface list with both ends named: panel terminals, mixer inlet, silo outlet, air at the regulator.
- Electrical schematics, a backup of the PLC program and the parameter set the line runs on, handed over on a drive.
- The mould set delivered, its product drawing, and the changeover time the crew was trained to reach.
- The outstanding items list, each with an owner and a date, including what the buyer still owes on civil works or power.
What do we need from you before the number means anything?
Four answers change the plant more than any option list: the product mix you intend to sell, the pallet size you will run, the destination port, and the power at the site, including whether you already have a transformer or have to size one.
Send those four through the inquiry form with the shift target and the yard outline. The reply is a scope sheet with the interfaces drawn, the exclusion list attached, and a unit list that matches the revision we will manufacture.
Frequently asked questions
What does turnkey mean in a block plant contract?
A turnkey contract puts the machines, the conveyors between them and the commissioning into one scope, and fixes the boundary at named terminal points. It does not move the foundation, the transformer, the pallet fleet or the yard inside that scope unless the contract says so in words. Read the exclusion list before the total, and check that both sides describe the same terminal points.
Should the pallet fleet be bought from the machine supplier?
Where you buy pallets matters less than when. The size has to match the mould and the pallet line: 1,400 × 1,400 × 30 mm on a QST1800, 1,350 × 880 × 25 mm on a QST1200. Order them so they land with the machine, because a press that waits for every empty pallet loses the output the cuber was bought for.
How is capacity in a turnkey offer verified?
At commissioning, with your mix and your product, by counting pallets through the line over a full shift and writing that count on the handover sheet. Name the product and the pallet in the same line, because a figure quoted on a standard solid brick does not carry over to a hollow block. A QS-1200A, for instance, takes 18 standard hollow blocks or 125 standard solid bricks per layer.
What stays outside a turnkey block making plant?
Civil works, the transformer and the incoming supply, the water line and the cement silo, the pallet fleet, yard hardstanding, the erection crew's travel and accommodation, the spare parts stock, and clearance at the destination. Every one of those is a separate contract with its own lead time. Ask for them as a written list, price them with your local contractor, and add them to the plant number before comparing two offers.
Can our own crew install a turnkey line?
Yes, if the crew has erected this class of machine before and the drawings arrive before they do. A QST1800 stands at 34 t and carries 104 kW, and a frame set out of level shows up later as a pallet line that will not hold tolerance. If the crew is new, keep the factory supervisor for the first press run and the first cuber cycle, and write that support into the handover sheet.