Which Mixer Is Suitable for Concrete Block Production?

31 October 2026 · 6 min read

Quick answer

Size the mixer from one moulding cycle, not from the block machine's power. On a QST6-15, six hollow blocks of 390 x 190 x 190 mm need about 0.1 cubic metres of mix every 15 to 23 seconds, which is 16 to 25 cubic metres an hour. A vertical shaft planetary mixer such as the CMP suits face-critical eco-bricks and PC imitation-stone products, and a horizontal twin-shaft forced action mixer suits dry block mixes at volume.

Get a price on WhatsApp Or send a written enquiry

No buyer sets out to choose a mixer. The block machine is chosen first, and the mixer follows from two numbers: the volume of mix one moulding cycle consumes, and the surface the finished block has to carry. Which mixer is suitable for concrete block production is an arithmetic question before it is a catalogue question. On a QST6-15 with a 980 x 680 mm tray, one cycle holds 6 hollow blocks of 390 x 190 x 190 mm, and that is the batch a drum or a pan has to deliver.

How much mix does one moulding cycle need?

Start from the product, not the machine. A hollow block of 390 x 190 x 190 mm fills 0.014 cubic metres of envelope, and six of them, the QST6-15 count per mould, come to 0.084 cubic metres. A hollow block holds less concrete than its envelope because of the voids, so treat the figure below as an upper bound and set your own mix weight against the mould. Check that against the tray envelope: 980 x 680 mm at 190 mm deep is 0.127 cubic metres, so the six blocks fill about two thirds of the space the mould sweeps. Add a quarter for compaction, for the spread left on the pallet top and for what stays in the pan, and one cycle asks for roughly 0.106 cubic metres.

Then apply the cycle. At 15 to 23 seconds a batch, the machine calls for 157 to 240 batches an hour, which is 16 to 25 cubic metres of mixed material an hour. That is the demand figure. It is a worked example from published tray and cycle data, not a rating for any mixer, and it is the number a supplier should be asked to meet.

Which mixer keeps the face the product needs?

Two types cover this demand and they are not interchangeable. A vertical shaft planetary mixer, the CMP, carries its tools on an arm that sweeps a complex path with no dead zone in the pan. The batch turns over against the pan wall from the first second, so pigment, cement and fines keep the same relationship to the last. CMP capacity is set against your moulding cycle and batch size, which is why the 0.106 cubic metres above is what a supplier needs from you.

Permeable eco-bricks of the sponge-city type have to be even across the open face, and PC imitation-stone bricks have to match in colour from one pallet to the next. That is a mixing uniformity problem, and it is where the planetary pan earns its place. A horizontal twin-shaft forced action mixer works differently: two counter-rotating shafts throw the mix across the trough, which suits dry-hard, semi-dry-hard and plastic mixes at volume. It is the mixer fitted to the QST1200 ready-mix plant, and the QS-1200 series runs from a 500 litre discharge at 25.5 kW to 1,500 litres at 75 kW, with blades cast in high chromium manganese alloy for crushed stone.

Standard hollow blocks and pavers sold by the truckload do not need a pan. A trough with two shafts and a 500 litre discharge will make them, shift after shift, for less per cubic metre.

Why does batching decide whether the mixer is worth buying?

A mixer can only blend what it is handed. Feed it a loader bucket count and it will produce a uniform mix of the wrong ratio, consistently, all shift. The PL series batching machine doses to a pre-set aggregate ratio with fast and slow dosing, weighed by high-precision three-point induction sensors, and a vibration device keeps the hopper throat open so the aggregate that was weighed is the aggregate that arrives at the mixer.

A site that buys a planetary pan and weighs aggregate by the bucket has bought the pan for nothing. The weighing error repeats in every batch, so strength varies by pallet and the curing yard hides the cause. Three-point sensing and a two-speed feed cost less than the step between two mixer classes, and they change the block more.

What are the three mistakes buyers make most often?

Three errors sit inside most mixer enquiries, and each one is visible in the quotation.

  • Sizing to the block machine nameplate. The 34.4 kW on a QST6-15 is the press and vibration drive, not a mixing duty, and matching it lands the buyer in the 50.2 kW class of the QS-1200 series, 1,000 litres at 50 cubic metres an hour, against the 0.106 cubic metres a cycle actually asks for.
  • No gate clearance for the loader. Discharge sits at 1,500 mm on the JS500 and 3,800 mm on the JS1000, so the skip or loader that fills the mixer and the block machine hopper that empties it have to be laid out before the order, not after.
  • Buying on slump. Slump is a test for wet ready-mix concrete. Block mix is dry and stiff, pressed and vibrated into shape, and it is judged on even moisture and a face that holds, not on how far a cone settles.

What moves the price of a mixing group?

Five lines, and none of them is the paint. Volume comes first: a 500 litre discharge and a 1,500 litre discharge are different castings, shafts and bearings, and the motor and gearbox follow, 25.5 kW at the bottom of the QS-1200 series and 75 kW at the top, with machine weight running from 4,000 kg to 9,080 kg.

The other four are wear liners, weighing, the batching hopper and the gate. Pan and trough liners, blade tips and the gate edge see aggregate every 20 seconds, so the alloy in them is a line item. Weighing means load cells, three-point sensing and the two-speed dosing that makes them usable. A batching hopper means a bin, gate and conveyor for each aggregate, sized by your gradation.

Ask for the quotation split along those lines. One total hides which line is thin, and a thin liner or a single-speed feed is paid for again in the second year.

Which answers settle the size before you order?

Write six answers before anyone quotes you a mixer.

  • Batch volume: pieces per mould times block volume plus your compaction allowance, which is 0.106 cubic metres on the QST6-15 example.
  • Cycle time: 15 to 23 seconds, which turns that batch into 16 to 25 cubic metres an hour.
  • Face: permeable eco-bricks and PC imitation-stone bricks point to a vertical shaft planetary mixer, standard blocks and pavers at volume to a twin-shaft.
  • Batching: three-point weighing, fast and slow dosing, and a vibration device on the hopper.
  • Layout: gate height and loader clearance, and the height of the block machine feed hopper.
  • Spares: one spare set of blades and liners in the first order, not the second.

A mixing group is bought twice, once at order and once at the second mould change, when the product list has moved toward face work or toward volume. Put the batch volume and the face requirement on paper first, and the choice between a pan and a trough makes itself.

Frequently asked questions

How do I size a mixer for a concrete block machine?

Take one moulding cycle as the batch. On a QST6-15, six hollow blocks of 390 x 190 x 190 mm occupy 0.084 cubic metres, and a quarter allowance for compaction brings that to about 0.106 cubic metres. At 15 to 23 seconds a cycle the machine wants 157 to 240 batches an hour, so the mixer has to deliver 16 to 25 cubic metres an hour.

Is a planetary mixer or a twin-shaft mixer better for blocks?

Neither is better in general, the product decides. A vertical shaft planetary mixer gives a batch with no dead zone in the pan, which is what permeable eco-bricks and PC imitation-stone bricks need for an even face and a repeatable colour. A horizontal twin-shaft forced action mixer handles dry-hard, semi-dry-hard and plastic mixes at volume, and it is the lower cost route for standard hollow blocks and pavers.

What output does a QST6-15 need from its mixer?

About 0.106 cubic metres a batch, which is 16 to 25 cubic metres an hour at the 15 to 23 second cycle. That sits under the 25 cubic metres an hour of the smallest unit in the QS-1200 twin-shaft series, a 500 litre discharge at 25.5 kW, so a mixer one class larger is buying buffer, not capacity.

Can a block plant run without a batching machine?

It can run and it will make blocks, but not the same block twice. Counting loader buckets leaves the aggregate ratio to the operator, and the error repeats in every batch, so strength varies from pallet to pallet and the curing yard hides the cause. A PL series batching machine with three-point weighing and fast plus slow dosing removes that variance before the mixer sees the material.

Does a bigger mixer make better blocks?

No. Batch size does not change density or face quality, mixing uniformity, weighing accuracy and the moisture in the mix do. A 1,500 litre drum mixing a dry block mix gives the same block as a 500 litre trough when both are fed and timed correctly. Buy the batch your cycle needs and put the difference into weighing and liners.

Price guides
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us