Block Factory Project Report: What the Numbers Must Show

24 November 2026 · 7 min read

Quick answer

Six figures decide whether a block factory project report survives review: blocks per shift built from pieces per mold and cycle, a capital list that reaches every line, a cost per block, three price levels, three output levels and a payback month. A QST6-15 with 6 hollow blocks per mold and a 15 to 23 second cycle supports 8,640 to 11,520 blocks per 8 hours. A report that shows the source of each number is one a lender can act on.

Get a price on WhatsApp Or send a written enquiry

A block factory project report is the file a buyer hands to a partner, a bank officer or his own family before money moves. Those readers will not stand on the site, so every figure must survive a question about its source. It carries a production basis, a capital list, a cost per block, a revenue case and four numbers that decide whether the project stands.

Each line answers one question: what is the source? A figure with no source is treated as zero by the person lending, and one unsourced figure contaminates the page around it.

What goes on the first page of a block factory project report?

The first page states how many blocks the plant can make in one shift, from three inputs: pieces per mold, seconds per cycle and effective working minutes. The QST6-15 on a 390 x 190 x 190 mm hollow brick gives 6 pieces per mold, a forming cycle of 15 to 23 seconds and a published output of 8,640 to 11,520 blocks per 8 hours. That range is the honest part. The low end is a shift with pallet returns, mold cleaning and a mix change; the high end is a clean run.

A daily figure from a vendor headline, with no mold, product or hours attached, cannot be audited, and a reader who cannot audit it will discount it. Write the assumption on the same line as the number: product size, pieces per mold, cycle in seconds, effective minutes, expected rejects. If the buyer's mix pushes the cycle to the top of the 15 to 23 second range, the report should already show that case.

The capital list has to reach the line item, not the category

A turnkey total is the first thing a bank officer deletes, because it cannot be checked against a quotation. The list must reach eight lines: host machine, foundation and embedded parts, transformer and incoming line, pallet fleet, curing area and racks, mold sets, forklift and clamp, first year of spare parts. Each line carries a physical number, not an adjective. The QST6-15 is 12 t on a 9,450 x 3,300 x 2,700 mm frame, and that weight sets the concrete and the embedded plates. Its 34.4 kW installed capacity plus 3.0 kW on the stacker sets the incoming line.

Then mark, line by line, what the machine quotation includes. Ours covers the machine, its mold sets and the stacker. Foundation, transformer, incoming cable, pallets, forklift, freight, customs, installation crew and commissioning spares are bought locally and belong in the buyer's list. Leaving them out does not look cheaper to a lender. It looks incomplete, and the contingency added costs more than the missing lines.

Why must operating cost be written per block rather than per month?

A monthly cost has no denominator, so nobody can act on it. When output falls the monthly total barely moves and the cost per block rises. Write the cost per block, with each component on its own line: cement and aggregate, electricity, pallet wear, mold wear, labour, rejects, freight. Then the report shows which line hurts when a price moves.

Electricity is the line most often estimated instead of measured. The figures sit on the machine sheets: 34.4 kW installed on the QST6-15, 104 kW on the QST1800, and a mixing side running from 25.5 kW on a JS500 up to 75 kW on a JS1500 at 25 to 75 m3/h. Multiply running hours by the buyer's own tariff. We do not put a tariff in a report.

Rejects and pallet wear are the two lines buyers understate. A cuber handling about 3,800 pallets a shift moves a fleet of trays through abrasion daily, and every cracked tray returns as a cost per block. A reject rate written low on paper and measured higher in the yard loses a lender's trust faster than a high number honestly stated.

Revenue needs three price levels and three output levels

One revenue line is a forecast. Three are a range, and a range is what a lender can price. Give three prices (low, base, high) and three output levels (pessimistic, base, optimistic), then name the assumption behind each. Say which of the six is weakest. In most reports it is the output line, because a price can be checked against the local market in one afternoon while nobody walks the yard with a stopwatch.

Use production data that can be defended. The QST6-15 on a 390 x 190 x 190 mm hollow brick gives 8,640 to 11,520 blocks per 8 hours, and the QST1200 is published up to 120,960 standard bricks per 8-hour shift. Pick the level that matches the mold and the product named in the report, and keep the same product across all three cases. Pairing a standard brick output with a hollow block price is the usual arithmetic error in the file.

Which four numbers will an investor ask for first?

Four numbers carry the decision, and all four come out of the rows above with no new inputs. Cost per block answers whether the plant can sell at the local price. Break-even daily output answers how empty the yard can be before the month turns negative. Payback month answers how long the capital stays exposed. Resale value answers what is left if the plan fails.

  • Cost per block. Sum the seven operating lines, then divide by the blocks sold in that month, not the blocks produced.
  • Break-even daily output. Monthly fixed cost divided by the margin per block, converted to blocks per shift with the cycle and pieces per mold.
  • Payback month. Capital list total divided by monthly net cash, with the ramp up months shown.
  • Resale value. A press of 12 t or 14 t holds value in its frame and hydraulics, less in molds that fit one product size.

The resale line is the one buyers skip and lenders do not. A press is a movable asset; a mold set for a 390 x 190 x 190 mm block is not, because the next owner may make pavers. Write the resale figure as a share of the capital list and name the molds that travel with the machine. A blank box reads as a machine the buyer keeps forever, which is a different risk story.

What the report leaves blank, and who fills it

We do not put prices in a report, because a price from one country is wrong in another before it is read. The money columns belong to the buyer, filled from local quotations for cement, aggregate, power, labour, pallets and freight. What we supply has to be exact before any quotation becomes comparable: model data, footprint, pallet size, cycle, installed capacity and a method for testing output on the buyer's own mix.

  • Model data: 34.4 kW installed plus 3.0 kW on the stacker, 12 t, a 980 x 680 x 20 mm tray and a 15 to 23 second cycle on the QST6-15.
  • Layout drawing: 9,450 x 3,300 x 2,700 mm for the host, plus curing area, pallet storage and forklift lanes, drawn on the buyer's plot.
  • Capacity test: a timed shift on the buyer's mix, counting pieces per mold, cycles per hour and rejects.

Build the file in that order and the numbers defend themselves. Send the plot size, the product mix and the power available, and the machine data, the layout and the test method come back as documents to attach to the report.

Report sections and the number each section must carry

Report sectionNumber that must appearWhere the number comes fromThe usual inflated version
Production basisPieces per mold, cycle in seconds, effective minutesMold drawing, machine sheet, one timed shiftDaily output copied from a vendor headline
Capital listEight lines, each with weight in t or installed kWMachine quotation plus local contractor quotationsOne turnkey total with no breakdown
Cost per blockSeven operating lines per blockMeter readings, purchase invoices, shift logMonthly cost divided by the best month output
Revenue caseThree prices, three output levels, one assumption eachLocal price survey and a timed trial shiftOptimistic output sold at the base price
Investor returnsCost per block, break-even output, payback month, resale valueThe four rows above, no new inputsResale value taken from the new machine price

Frequently asked questions

What must a block factory project report prove first?

It must prove daily output from machine data, not from a vendor headline. Pieces per mold, seconds per cycle and effective working minutes produce the figure, and the report should show all three on the first page. One machine sheet lists 6 hollow blocks per mold and a 15 to 23 second cycle, which is why the published range runs from 8,640 to 11,520 blocks in 8 hours.

Why should capital cost be itemised instead of given as a turnkey total?

A turnkey total cannot be checked against a quotation, so a lender either rejects it or adds a contingency. An itemised list shows the machine, the foundation and embedded parts, the transformer and incoming line, the pallet fleet, the curing area, the mold sets, the forklift and the first year of spares, each with a source. It also shows which lines sit outside the machine quotation.

How do you turn a monthly budget into a cost per block?

Divide each operating line by the blocks sold in that same month, not by the blocks the plant was designed to make. Cement and aggregate, electricity, pallet wear, mold wear, labour, rejects and freight each get a column. Electricity is carried from installed capacity on the machine sheet, and the tariff comes from the buyer's own bill, never from the report.

Which output level in a block plant report is usually too optimistic?

The optimistic output case, because a price is tested against the local market within days while a daily output is rarely timed. Write the optimistic case with the same mold and product as the base case, name the effective minutes it assumes, and state what has to be true for the plant to reach it. A report that pairs an optimistic output with a base price fails the first review.

What does the payback month in a block factory report depend on?

It rests on three inputs the report already holds: the total of the capital list, the margin per block and the blocks actually sold each month. Payback is the capital total divided by monthly net cash, and the ramp up months belong inside the calculation rather than after it. A report that starts counting from full output hides the weakest period of the project.

Can the report be written before local quotations exist?

Yes, and that is the better order. Machine data, footprint, pallet size and cycle do not change with the country, so the production basis and the capital structure can be finished first. The money columns are then filled from local quotations for cement, aggregate, power, labour, pallets and freight. A file built that way stays comparable between two suppliers, which is what a bank wants to see.

Price guides
Machines that fit this
Machines used in this process

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us