A high position cuber system capacity per hour is 3600 divided by the layer cycle, capped by the press that feeds it. A 15 second layer is 240 layers an hour, a 12 second layer 300. The high position unit carries no published pallets-per-hour figure, so size it from the press pallet rate and the curing area, not from a headline number.

Get a price on WhatsApp Or send a written enquiry

A high position cuber system capacity per hour is decided by three numbers, and only one of them belongs to the cuber. The layer cycle sets how fast one stack is built. The press sets how many loaded pallets arrive each hour. The curing area sets how many stacks can wait. The figure a plant can plan on is the smallest of the three.

Published cycles across the family run from 12 to 15 seconds per layer on the QS-1000G-C, 15 to 18 seconds on the QS-1000G-B and QS-1200A, and 16 to 18 seconds on the QS-1000G-A. Dividing 3600 by the cycle turns each of them into layers per hour, the same unit as pallets per hour.

How do you turn a layer cycle into pallets per hour?

One layer carries one pallet, so the arithmetic is one division. A 15 second cycle gives 3600 / 15 = 240 layers per hour. Twelve seconds gives 3600 / 12 = 300, eighteen seconds gives 3600 / 18 = 200. Multiply by shift hours after that step: 240 layers an hour across eight hours is 1,920 pallets, before stoppages and mould changes.

The same division over the family exposes a gap in the published capacity column. The QS-1000G-A at 16 to 18 seconds derives 1,600 to 1,800 pallets in eight hours, and its published 1,700 sits inside that band. The QS-1200A at 15 to 18 seconds derives 1,600 to 1,920, and its published 3,800 is twice the top of it. The QS-1000G-C derives 1,920 to 2,400 against 3,800 published.

Two readings follow. A published pallets-per-shift figure is counted on the maker's own basis: stations, bricks in a layer, and how much of the shift the line really runs. A derived figure counts the cycle alone. Use the cycle to compare machines and the published figure to plan a shift, and never multiply one by the other.

UnitCycle per layerLayers per hour (3600 / cycle)Published capacityPower
QS-1000G-C double station12 to 15 s240 to 300about 3,800 pallets per shift44 to 45 kW
QS-1200A low position15 to 18 s200 to 240about 3,800 pallets per shift34.15 kW
QS-1000G-B simple cuber15 to 18 s200 to 240about 2,000 pallets per shift29 kW
QS-1000G-A fixed cuber16 to 18 s200 to 225about 1,700 pallets per shift15 kW
QS-1200B high positionnot published200 to 300, family bandnot published, built to press and productnot published

What limits throughput beyond the cuber itself?

A cuber able to build 300 layers an hour is worth little behind a press that delivers 144 pallets. Four limits sit outside the machine.

  • Press pallet rate. The QST6-15 moulds a pallet every 15 to 23 seconds, so 3600 / 23 = 156 up to 3600 / 15 = 240 pallets an hour. The QST1200 and QST1800 run 15 to 25 seconds, which is 144 to 240. No cuber can add a pallet the press did not make.
  • Curing time. Bricks must stand before they are cubed, and every hour of standing needs pallet positions. If the product needs 20 hours and the press makes 240 pallets an hour, the area must hold 4,800 loaded pallets.
  • Pallet return. A stack that leaves with self-retained forklift holes instead of a pallet takes one pallet out of the return loop, which shows up as output in a plant short of pallets.
  • Product fit. A clamp rated for brick above 50 mm cannot lift a thin tile, and a stacking limit of 1,300 mm caps the layers a finished stack holds.

Why the high position unit carries no pallets-per-hour figure

The QS-1200B is built to the press, the pallet and the product, so one published rate would be wrong for most plants. Its cycle is not published either, and the only honest band is the family 12 to 18 seconds, which is 200 to 300 layers an hour. What is fixed is the mechanism: pallet loading and lifting machines, a pallet pusher with a first brick pusher, and a second and third brick pusher with a rotating table.

Self-retained holes move the constraint rather than remove it. With no pallet under the stack, the yard stops storing and returning pallets, and the clamp lifts the stack itself. Throughput then follows the press rate at the intake and the curing area at the discharge.

Two questions therefore belong in any quotation: which press it will sit behind, and how many pallet positions the curing area has. Those answers set the cycle the unit is built to run, and no single hourly figure can stand in for them.

Where the money sits in a high position cuber

The price blocks are structural and hydraulic before they are electronic. The frame carries the stack, the pushers move bricks, the table turns every layer, and each addition buys cycle time or takes work off the yard.

  • Steel and station count. Columns, guides and frame grow with stack height and with the number of stacking positions, and a two station machine carries twice the frame and pushers.
  • Pushers and rotating table. A pallet pusher, three brick pushers and one rotating table, each a cylinder, a pair of guides and a wear surface. That count separates a simple cuber from this one.
  • Pallet loading and lifting machines. Two machines at the front. Keep pallets and you pay for both plus the fleet behind them.
  • Hydraulics. Pump, valve block and clamp cylinders sized to stack height and clamp load. Weak hydraulics under a tall stack show up as drift, and drift as a layer out of square.
  • PLC and touch screen. The money is in recipe memory and sensors, not in the screen. Recipes shorten changeover, and changeover minutes are capacity.
  • Installation and commissioning days. The team stays on site as long as the tie-in to the existing conveyor route takes. A retrofit that keeps the original cuber running loses less output than a replacement.

Power and floor area the unit adds to the line

Installed power runs from 15 kW on the QS-1000G-A to 44 to 45 kW on the QS-1000G-C, with 29 kW on the QS-1000G-B and 34.15 kW on the QS-1200A. No figure is published for the QS-1200B, so the supply is sized from the configuration ordered. In a plant with a limited transformer, 15 kW and 44 kW are a generator decision.

Floor area is the second addition. Ask for the drawing that includes the pallet lifting machine, the pushers and the conveyor route, because the frame rarely closes an aisle. The low position QS-1200A occupies 12,000 x 3,000 mm and weighs 18,000 kg. A high position unit stacks above floor level, so the forklift access is drawn around the discharge end.

Should the existing cuber stay in service during a retrofit?

It can, and in a plant that sells everything it makes it should. The QS-1200B connects at the finished product discharge position, so the original cuber remains in service while the new unit is tied in.

That arrangement has a cost. Two stacking points mean a diverter on the conveyor, two sets of pallet positions, and a written rule about which product runs on which machine. Left to the operator, that rule becomes a queue.

Bring four figures to the quotation and the sizing settles itself: pallets an hour from the press, curing hours for the product, pallet positions in the yard, and the stack height the product allows. Those four decide whether the unit runs at 200 layers an hour or at 300.

Frequently asked questions

How many layers per hour does a high position cuber build?

The cycle the unit is set to decides it, and the division is the whole answer. At 15 seconds per layer, 3600 / 15 = 240 layers an hour. At 12 seconds it is 300, at 18 seconds 200. Published cycles across the family run 12 to 18 seconds, so 200 to 300 layers an hour is the band the machine is built inside.

Why is there no pallets-per-shift figure for the QS-1200B?

Because the unit is configured to the press, the pallet and the product, so a single number would mislead most buyers. What is published is the mechanism: pallet loading and lifting machines, a pallet pusher with three brick pushers, a rotating table, and forklift holes retained inside the stack. Capacity is sized from the press rate and the curing area behind it.

What caps the hourly output of a cuber line?

The slowest item in the chain, which is often the press. A QST6-15 runs a 15 to 23 second cycle, which is 156 to 240 pallets an hour, and no cuber downstream can exceed that input. Curing caps the other end: 240 pallets an hour with 20 hours of curing needs 4,800 pallet positions, or the cuber stands and waits.

Does a high position cuber need pallets in the yard?

Not for the finished stack. Forklift holes are retained inside the stack itself, so a clamp or a fork can lift the whole stack with no pallet underneath, and the pallet fleet stops growing with output. Loaded pallets still arrive from the press, and the pallet loading machine plus the pallet lifting machine handle them at the front of the unit.

Can the unit be added without stopping the plant?

On most sites yes. The unit connects at the finished product discharge position, so the original cuber stays in service and production continues while the new machine is tied in. Two stacking points do need a diverter on the conveyor and a written rule about which product runs on which machine, or the gain turns into a queue at one of them.

What drives the price of a high position cuber?

Five blocks decide it, and the control panel is the smallest of them. Steel and the number of stacking stations come first, then the pallet pusher, three brick pushers and the rotating table, then hydraulics sized to stack height and clamp load, then the days on site for installation and commissioning, and finally whether the old cuber keeps running beside the new one.

Price guides
Machines that fit this

Want an engineering opinion on your project?

Tell us what you want to produce and which raw materials you have, and we will recommend the right machine.

Talk to an engineer

Related reading

Request a quotation

A machine list, a layout drawing and a price, usually within one working day.

We reply within 12 hours. Your information is never shared.

WhatsApp Us